i TWHf! CONCRETE CONSTRUCTION ABOUT THE HOME AND ON THE FARM THE RECOGNIZED TEXT BOOK OF CEMENT USERS REVISED EDITION 1909 PUBLISHED BY THE ATLAS PORTLAND CEMENT COMPANY 30 BROAD STREET NEW YORK SPECIFICATIONS FOR MIXING AND HANDLING "ATLAS" PORTLAND CEMENT Continued. PAGE Effect of External Agencies on Concrete 33 Fire Resistance 33 Water-Tightness 33 Corrosion of Metal Reinforcement 33 Sea Water 33 Acids 35 Oils 35 Alkalies 35 Freezing 35 Specifications for Posts 36 Fence Posts 36 Table of Quantity of Materials for Fence Posts 38 Cost of Fence Posts 41 Corner Posts 41 Table of Quantity of Corner Posts 41 Hitching Posts 41 Clothes Posts 4 2 Horse Blocks 43 Watering Troughs 44 Hog Troughs 51 Slop Tanks 52 Fertilizer Tanks 54 Rain Leaders 54 Retaining Walls 56 Table of Dimensions of Retaining Walls and Quantity of Ma- terials for Different Heights of Wall 57 Dams 58 Table of Dimensions for Small Dams and Quantity of Materials for Different Heights of Dams 59 Walls 60 Cellar and Basement Walls 60 Table of Thicknesses of Walls and Quantity of Materials for Dif- ferent Heights of Basement 62 Walls above Cellar or Basement 64 Columns 67 Steps and Stairs 69 Table of Dimensions of Stairs 74 Sidewalks 75 SPECIFICATIONS FOR Continued. PAGE Table of Quantity of Materials for Sidewalks . 77 Curbs and Gutters 79 Barns 81 Feed Troughs 81 Floors 86 Cellar Floors 86 Barn Floors 86 Feeding Floors 88 Runways from Stables 89 Drains 90 Tile Drains 91 Cesspools , 94 Box Stalls 95 Ventilation 95 Hog Pens 96 Dairies 98 Ice Boxes 100 Silos 103 Table of Data for Different Sizes of Silos 105 Hollow Wall Silos 112 Tanks 112 Square Tanks 113 Round Tanks 114 Reinforcement for Tanks 117 Table of Data for Different Sizes of Tanks 117 Grain Elevators 117 Corn Cribs 1 18 Cisterns 119 Square Cisterns 121 Well Curbs 121 Ice Houses 123 Root Cellars 126 Mushroom Cellars 129 Arch Driveways 130 Culvert Driveways 131 Water Pipes Under Driveways 132 Hen Nesting Houses 132 Chicken Houses 134 Green Houses 137 Concrete Greenhouse Tables 139 Concrete Greenhouse Trays 142 SPECIFICATIONS FOR Continued. PAGE Concrete Flower Boxes 142 Hot-bed Frames 144 Windmill Foundations 144 Concrete Roller ; 146 Dance Pavilion 148 Piazza 149 Lattice 1 50 Chimney Caps 151 Tree Surgery 152 Filling the Cavity 153 Concrete Aquariums 154 Concrete Blocks 1 54 Stucco Work Cement Plaster, Spatter Dash, Pebble Dash 156 Coloring for Concrete Finish 156 Concrete Culverts 1 59 Design of 5-Foot Arch Culverts 160 Design of 8-Foot Arch Culvert 160 Table of Amount of Materials for Arch Culverts 162 Table of Colors for Colored Mortars 158 Design of lO-Foot Arch Culvert 164 FOREWORD. The development of the American Portland Cement industry during the past decade has been one of the marvels of the age, and while Portland Cement Concrete has come to be recognized as the ideal building material for heavy work, comparatively little attention has been given to its use in the smaller construction about the home and on the farm. That active interest, however, is taken in this important subject by the suburbanite, the villager, and the farmer, is evidenced by the large number of letters of inquiry received by the agricultural and technical journals. During the past few years the price of lumber has advanced to almost pro- hibitive figures, and it is therefore only natural that a substitute material which affords the advantages of moderate cost, durability, and beauty should be looked upon with favor. It is not our purpose to enlarge upon the uses for which Portland Cement is now considered standard, but rather to direct attention to the economy of sup- planting wood, brick, and cut stone in divers ways by the more durable, sightly, and sanitary Portland Cement construction. In the following pages we shall endeavor to point out, in language free from technical terms, some of the uses for which Portland Cement Concrete is espe- cially adapted. CONCRETE CONSTRUCTION. Concrete construction dates back to the time of the Romans, who secured good results from a mixture of slaked lime, volcanic dust, sand and broken stone. Even this combination, crude in comparison with Portland Cement Concrete, produced an artificial stone which has stood the test of nearly two thousand years, as evidenced by many works in Rome which are to-day in a perfect state of preservation. "Portland Cement" is an invention of modern times its universal use the matter of a quarter of a century. The honor of its discovery belongs to Joseph Aspdin, of Leeds, England, who took out a patent in 1824 for the manufacture of "Portland Cement," so called because of its resemblance in color, to a then popular limestone quarried on the Island of Portland. Manufacture was begun in 1825, but progress was slow until about 1850, when, through improved methods and general recognition of its merits as a building material, commer- cial success was assured. About this time the manufacture of Portland Cement was taken up in earnest by the French and Germans, and, by reason of their more scientific efforts, both the method of manufacture and quality of the fin- ished product was greatly improved. Portland Cement was first brought to the United States in 1865. It was first manufactured in this country in 1872, but not until 1896 did the annual domestic production reach the million-barrel mark. I I < p w H W s Wonderful as the development of the general industry has been, the growth of the Atlas Portland Cement Company's plants has been even more so. Be- ginning in 1892 at Coplay, Pa., with the modest capacity of 250 barrels per day, its production has steadily increased through the construction of plants Nos. 2, 3, and 4, at Northampton, Pa., and plants Nos. 5 and 6, at Hannibal, Mo., until now the productive capacity is more than 40,000 barrels each twenty-four hours, or approximately fourteen million barrels per year. This production is greater than the capacity of any other Portland Cement company in the world. "ATLAS" Portland Cement is manufactured from the finest raw materials, under expert supervision in every department of the works. It is of the highest quality, being guaranteed to pass all usual and customary specifications, such as the specifications of the United States Gov- ernment and those of the American Society for Testing Materials, which latter specifications have been concurred in by The American Institute of Architects, The American Engineering and Maintenance of Way Association, and The Association of American Portland Cement Manufacturers. The quality of eastern and western "ATLAS" is identical. By virtue of its enormous produc- tion, The Atlas Portland Cement Company is able to develop and retain in its service the most skilled operating talent in the Portland Cement industry, which insures a thoroughly reliable and uniform product. "ATLAS" Portland Cement is guaranteed to be "ALWAYS UNIFORM." 10 Concrete, which is really an artificial stone, is made by CONCRETE mixing pieces of stone, such as broken granite or hard lime- stone, which may vary in size from a walnut to a hen's egg, with clean, coarse sand and first-class Portland cement, using enough water to make a mushy mixture about like heavy cream. The cement and water make the mass begin to stiffen in about half an hour, and in from 10 to 24 hours it becomes hard enough so that an impression cannot readily be made by press- ing on it with the thumb. In a month's time the entire mass becomes one hard stone. Conglomerate or pudding stone in nature is really a natural cement concrete, the large and small particles of pieces of stone and sand being cemented together in the course of ages in a similar way to that by which cement is made. Where a very strong mortar is required for laying brick or MORTAR stone, "ATLAS" Portland cement may be mixed with sand in proportions one part "ATLAS" cement to two and one-half parts sand. A characteristic of "ATLAS" Portland Cement is that it gives an especially greasy mortar. A mortar nearly as strong as the above, and which works still better under the trowel, can be made by mixing one bag "ATLAS" Portland cement with one barrel of clean sand and one-half pail of lime putty. The lime putty is made by thor- oughly slaking quick lime. The longer the time the putty can stand before using the better it is. It must never be used when hot or until the lime is thoroughly slaked. When laying up brick and stone with any kind of mortar they must be thor- oughly wet. Always use the best Portland cement obtainable. Natural CEMENT cement is not suitable for concrete. Whatever the kind of cement, unless it is of first-class quality, it may give trouble by not setting up and hardening properly. Portland cement is manufactured from a mixture of two materials, one of them a rock like limestone, or a softer mate- rial like chalk, which is nearly pure lime, and another material like shale, which is a hardened clay or else clay itself. In other words, there must be one material which is largely lime and another material which is largely clay, and these two must xx CEMENT be mixed in very exact proportions determined by chemical (Cont'd) tests, the proportions of the two being changed every few hours, if necessary, to allow for the variation in the chemical composition of the materials. "ATLAS" PORTLAND CEMENT then is made by quar- rying each of these two materials, crushing them separately, mixing them in the exact proportions, and grinding them to a very fine powder. This powder is fed into long rotary kilns, which are iron tubes about 5 or 6 feet in diameter, lined with fire brick and over 100 feet long. Powdered coal is also fed into the kilns with the ground rock and burned at a temperature of about 3000 degrees Fahrenheit, a temperature higher than that needed to melt iron to a liquid, and there is formed what is called cement clinker, a kind of dark, porous stone which looks like lava. After leaving the kiln, the clinker is cooled, crushed and ground again to a still finer powder, so fine, in fact, that most of the particles are less than 1/200 of an inch in size, and this grinding brings it back to the very light gray color character- istic of "ATLAS" Portland Cement. It is now placed in storage tanks or stock houses where it remains for a while to season before it is put into bags or barrels and shipped. The barrels weigh 400 pounds gross, or 376 pounds net. When shipped in bags, the weight is 94 pounds per bag, four bags being equal to one barrel. At the "ATLAS" plants, from the time the rock is taken from the quarry until it is packed in barrels or bags, all of the work is done by machinery, and a thorough chemical mixture takes place regulated by the experienced chemists in charge of the work. PACKING OF CEMENT. Portland cement may be obtained in paper bags, cloth sacks or wooden barrels. The most con- venient form for most users is the cloth sack. These sacks can be returned to the dealer from whom the cement was purchased and a rebate obtained for them if they are kept dry and untorn. HOW TO STORE CEMENT. Portland cement must be stored in a dry place, that is, in a barn or shed, for dampness is the only element which will injure its quality. The cement will become lumpy and even form a solid mass when kept in a damp place, and when in this condition it should not be used. All lumps which do not crumble at the lightest blow should be thrown out. Cement stored in a building must not be placed on the bare ground. Make a platform which is at least 6 inches above the ground, and store the cement on this platform. If the building has a concrete floor it is advisable to cover the floor with planking upon which to place the cement. Sand, crushed stone or gravel screenings passing when dry SAND (Fine a screen having ^-inch diameter holes is called the fine aggre- Aggregate) gate. Sand should be (i) clean, that is, free from dirt like vegetable loam, and (2) coarse.. If the sand contains vegetable matter, it is difficult to tell whether the sand is good, because a very small quantity a fraction of one per cent. may sometimes prevent the con- crete from hardening. When the job is small, however, an approximate idea of the quality may be obtained by exam- ining the sand in the bank and making up a specimen of concrete on the job as described below. The ordinary plan of taking a little sand in the palm of one hand and rubbing it with the fingers of the other to see if it discolors is of little value, and little can be learned from dropping sand in water, because it is not so much the quantity as the kind of impurity that counts. HOW TO TEST FOR A CLEAN SAND. Two rough tests are as follows: (a) Pick up a double handful of moist sand from the bank, open the hands, holding them with the thumbs up, and rub the sand lightly between the hands, keeping them about ^2 inch apart, allowing the sand to slip quickly between them. Repeat this operation five or six times, then rub the hands lightly together so as to remove the fine grains of sand which adhere to them, and examine to see whether or not a thin film of sticky matter adheres to the fingers; if so, do not use the sand, for it contains loam. A further test is to scrape some of this matter from the fingers on the end of a penknife and take a little of it between the teeth. If it does not feel gritty or sharp it indicates vegetable loam, which is bad. Do not use this sand, or if no other can be obtained test it further to make sure that there is not sufficient loam present to prevent the cement from getting thoroughly hard. 13 SAND (Fine Aggregate) (Confd.) The sand for the test given above must be moist, just as it conies from the bank. When dry the dirt will not stick to the fingers, hence this test cannot be used. Some idea can be obtained, however, by the appearance of the sand, even if it is dry. If it looks "dead," an appearance which is caused by the particles of dirt sticking in little lumps to the grains of sand, sometimes also making the grains of sand stick to- gether in little bunches when picked up, it is almost a sure sign of vegetable matter, and the sand should not be used. Fine roots in a sand will also indicate the presence of vegetable matter. (b) Make up two blocks of concrete, each about 6 inches square and 6 inches thick, using the same cement and the same sand and gravel or stone as will be used in the structure to be built, and mixing them in the same proportions and of the same consistency. Keep one block in the air out of doors for 7 days and the other in a fairly warm room. The specimen in the warm room should set so that on the following day it will bear the pressure of the thumb without indentation, and it should also begin to whiten out at this early period. The specimen out of doors should be hard enough to remove from the molds in 24 hours in ordinary mild weather, or 48 hours in cold, damp weather. At the end of a week test both blocks by hitting them with a hammer. If the hammer does not dent them under light blows, such as would be used for driving tacks, and the blocks sound hard and are not broken under medium blows, the sand as a general rule can be used. HOW TO WASH SAND. Sand cannot be washed simply by wetting the pile of sand with a hose, for this only washes or transfers the dirt to a lower part of the pile. Sand, provided it is not too fine, can be satisfactorily washed, however, by making a washing trough, as shown in Fig. i. For sands a screen with 30 meshes to the linear inch is necessary to prevent the good particles from passing through it. This must be sup- ported by cleats placed quite near together, or it will break through. The sand is shoveled on to the upper end of the trough by one man, while another one can wash it with a hose. The flow of water will wash the sand down the incline, and as the sand and water pass over the screen the dirty water will drain off through the screen, leaving the clean sand for use. By this arrangement the dirt which is washed out cannot in any way get mixed with the clean sand SAND (Fine Aggregate.) (Cont'd ) Fine. m&sh screen //n Boards Trough fo run otf'dirfy wafer Trough fo Ae fined v/jfh farrecf pa/zejr Fig. i. Washing Trough for Sand or Gravel. COARSE SAND. Sand should be coarse. By this we mean that a large proportion of the grains should measure 1/32 to y& inch in diameter, and should the grains run up to % inch the strength of the mortar is increased. Fine sand, even if clean, makes a poor mortar or concrete, and, if its use is unavoidable, an additional proportion of cement must be used with it to thoroughly coat the grains. If the sand is very fine a mortar or concrete made from it will not be strong. Sometimes fine sand must be used because no other can be obtained, but in such a case, double the amount of cement may be required. For example, instead of using a concrete one part cement to two parts sand to four parts stone, a concrete one part cement to one part sand to two parts stone may be used. NATURAL MIXTURES OF BANK SAND AND GRAVEL. Very often the sand and gravel found in a bank are used by inexperienced people just as it is found without regard to the proportions of the two materials. This may be all right in some cases, but generally there is too much sand for the gravel or stone, so that the resulting concrete is not nearly as strong as it would be if the proportions between the sand and gravel were right. It is better then to screen the sand from the gravel through a %-inch sieve, and then mix the materials in the right proportions, using generally about half as much sand as stone. By so doing a leaner mix can be used than where the sand and gravel are taken from the bank direct. The cost of the cement saved will more than pay for the extra labor required to screen the material. For example: Using even a very good gravel bank, a mixture one part cement to four parts natural gravel must be employed instead of one part cement to two parts sand to four parts of screened gravel. So much more cement is thus required with the natural gravel that a saving of one bag of cement in every seven is made by screening and remixing in the right proportion. CRUSHER SCREENINGS. Screenings from broken stone make an excellent fine aggregate, which can be substituted for sand unless the stone is very soft, shelly or contains a large percentage of mica. GRAVEL OR Gravel or broken stone forms the largest part of the mass PROICFN STONE (Coarse of a & ood concrete, and is called the coarse aggregate. If the Aggregate > concrete is to be used simply for filling, or in a low wall against which nothing is to be piled, clean cinders, screened to remove the dust, may sometimes be used for the coarse aggregate. The concrete made from them, however, is not strong and is very porous. Slag or broken brick are sometimes used for the coarse aggregate. The size of the stone is best graded from fine particles about % mcn diameter up to the coarser. The largest size pieces may be 2% inches where a foundation or a wall 12 inches thick or over is being built, while for thin walls and where reinforcement is used the largest particles had best be about ^4-inch size. With gravel the danger is apt to lie in the grains being coated with clay or vegetable matter which prevents the cement from sticking to them, and hence a very weak concrete results. The method for washing gravel should be the same as that described for sand (see page 14) and shown in Fig. i. The screen when washing the gravel should have openings % inch square. 16 WHAT NOT TO USE. Do not use dirty stone or gravel in any case. Avoid soft sandstones, soft freestones, soft lime- stones, slate and shale. The water used for concrete must be clean. It should not WATER be taken from a stream or pond into which any waste from chemical mills, material from barns, as manure, or other refuse, is dumped. If the water runs through alkali soil or contains vegetable matter it is best to make up a block of concrete, using this water, and see whether the cement sets properly. Do not use sea water. Concrete is composed of a certain amount or proportion of PROPORTIONS cement, a larger amount of sand, and a still larger amount of stone. The fixing of the quantities of each of these materials is called proportioning. The proportions for a mix of concrete given, for instance, one part of cement to two parts of sand to four parts of stone or gravel, are written 1 12 14, and this means that one cubic foot of packed cement is to be mixed with two cubic feet of sand and with four cubic feet of loose stone. For ordinary work use twice as much coarse aggregate (that is, gravel or stone) as fine aggregate (that is, sand). If gravel from a natural bank is used without screening, use the same proportion called for of the coarse aggregate; that is, if the specifications call for proportions i :2 14, as given above, use for unscreened gravel (provided it contains quite a large quantity of stone) one part cement to four parts unscreened gravel. If when placing concrete with the proportions specified, a wall shows many voids or pockets of stone, use a little more sand and a little less stone than called for. If, on the other hand, when placing, a lot of mortar rises to the top, use less sand and more stone in the next batch. In calculating the amount of each of the materials to use for any piece of work, do not make the mistake so often made by the inexperienced that one barrel of cement, two barrels of sand and four barrels of stone will make seven barrels of concrete. As previously stated, the sand fills in the voids between the stones, while the cement fills the voids between the grains of sand, and therefore the total quantity of concrete will be slightly in excess of the original quantity of stone. This point is very clearly shown in Fig. 2. GRADED STONE MIXTURE Fig. 2. Diagram Illustrating Measurement of Dry Materials and the Mixture.* PROPORTIONS (Cont'd) The following quotation from Concrete, Plain and Rein- forced,* by the well-known authorities, Taylor and Thompson, is printed as a guide to those who wish to build any concrete structure for which specific instructions are not given in the following pages. "As a rough guide to the selection of materials for various classes of work, we may take four proportions which differ from each other simply in the relative quantity of cement." "(a) A Rich Mixture for columns and other structural parts subjected to high stresses or requiring exceptional water- tightness: Proportions 1:1^:3; that is, one barrel (4 bags) packed Portland cement to one and one-half barrels (5.7 cubic feet) loose sand to three barrels (11.4 cubic feet) loose gravel or broken stone. "(b) A Standard Mixture for reinforced floors, beams and columns, for arches, for reinforced engine or machine founda- tions subject to vibrations, for tanks, sewers, conduits and other water-tight work: Proportions 1:2:4; that is, one barrel (4 bags) packed Portland cement to two barrels (7.6 cubic feet) loose sand to four barrels (15.2 cubic feet) loose gravel or broken stone. "(c) A Medium Mixture for ordinary machine foundations, retaining walls, abutments, piers, thin foundation walls, building walls, ordinary floors, sidewalks and sewers with heavy walls: Proportions 1:2^:5; that is, one barrel (4 bags) packed Portland cement to two and one-half barrels (9.5 cubic feet) loose sand to five barrels (19 cubic feet) loose gravel or broken stone. "(d) A Lean Mixture for unimportant work in masses, for heavy walls, for large foundations supporting a stationary load and for backing for stone masonry: Proportions i 13:6; that is, one barrel (4 bags) packed Portland cement to three barrels (11.4 cubic feet) loose sand to six barrels (22.8 cubic feet) loose gravel or broken stone." *Taken by permission from Taylor & Thompson's "Concrete Plain and Reinforced," John Wiley & Sons, New York, publishers. 18 Green timber is preferable, for, if seasoned, it is likely to swell and warp when brought in contact with moisture from the concrete. White pine is best, but fir, yellow pine or spruce are also suitable. If a smooth surface is desired, the form boards or planks next to the concrete must be planed and the edges tongued and grooved or beveled. Grease the inside of forms with either soap, linseed oil, mixed lard and kerosene, or crude oil, that is, petroleum, otherwise particles of concrete will stick to the forms when they are removed, thus giving an unnecessarily rough surface to the face of the concrete. Forms FORMS Fig. 3. Section of Forms Showing Method of Holding Sides of Forms. should not be greased when it is intended to plaster the surface of the concrete, but should be thoroughly wet immediately before placing the concrete. Lay the sheathing or form boards horizontally. These may be of i-inch, i*/2-inch or 2-inch lumber, the distance apart of the studding being governed by the thickness of sheathing selected. Place the studs not more than 2 feet apart for i-inch sheathing, nor more than 5 feet apart for 2-inch sheathing. They should be securely braced to withstand the pressure of the soft concrete, also of the ramming and tamping. In build- ing forms do not drive the nails all the way home. Leave the heads out so that it is possible to draw them with a claw hammer. The less hammering done around green concrete 19 the better. Avoid cracks in forms into which the mortar will force itself and form "fins" on the surface of the work. The length of time the forms should be left in place varies with conditions. Where no pressure is brought to bear on the concrete, forms can be removed within one-half to two days, or as soon as the concrete will withstand the pressure of the thumb without indentation. On very small work, like drain tile, two to four hours is sufficient time, provided it is carefully handled and left in place until thoroughly hard. On large and important walls one to three days are generally required, and if any water or earth pressure comes against the walls the forms should be left in place from three to four weeks. Slab forms can be removed in about one week, but the supporting posts under any beams and slabs must not be touched for a month after laying the concrete. Concrete forms are kept from separating or bulging either by using bolts or by wiring. Bolts as a general rule are more satisfactory on large work than wire, but as they cannot always be conveniently obtained, wires are used extensively. In Fig. 3 are sketched both methods for holding side forms together. The spacers are only placed between the forms to hold them the proper distance apart, and must be removed after some of the concrete is placed. Where wires are used, the forms are drawn together by twisting, as shown in the figure. This is done with a large nail or a hammer handle. CIRCULAR For a round structure two sets of circular forms are usually FORMS needed, namely, inner and outer forms, "A" and "B," Fig. 5. Both of these come into use when building a silo or other struc- ture having a thin wall, but in the case of a solid column only the outer form is necessary. Both inner and outer forms are made practically the same, except that the radius of the outer one is of necessity greater than that of the inner because of the thickness of the walls between the two forms. A simple method of drawing the circle for the outer form is as follows: Take a piece of string, attach one end to a long spike, marked "A," Fig. 4, and stick it into the ground. Measure off on the string one-half the diameter of the circle desired, tie a knot, through which force a nail (marked "B," Fig. 4), and, keeping the string stretched between these two points, draw a continuous line. Lay the boards around the line just made, nail them together firmly and then mark the circle out on them and saw to the line. After making two or CIRCULAR more forms, place them at equal distances apart, and put on FORMS (Cont'd) the sideboards in the manner shown in Fig. 5. These boards are called "Lagging." Oufer F'orn. B 5ecfiona of Circufar ror Ifcrffcof Section. Fig. 5. Circular Forms. Fig. 4. Laying Out Circular Forms. The quantity of tools will, of course, vary with the size of the gang of men. The following schedule is based on a small gang of two or three men, making concrete by hand : TOOLS AND APPARATUS Concrete Wheelbarrow. Square Pointed Shovel Three No. 3 square-pointed shovels. Two wheelbarrows (iron wheelbarrows the best). One tamper, a piece of 2 x 4-inch joist is sufficient. One garden spade or spading tool. One water barrel. Three water buckets. One sand screen, %-inch or %-inch mesh, for screening sand from the gravel. One measuring box (see Fig. 6). One mixing platform about 10 feet square built so substan- tially that it can be moved without coming to pieces, having a 2 x 3-inch strip around the edge to prevent the waste of mate- rials and water. This platform can be made of i-inch stuff, resting on joists about 2 feet apart, provided it is stiffened by being tongued and grooved. Fig. 6. Measuring Box for Sand and Gravel.* Concrete should be mixed as near the place where it is to be used as practicable, so as to avoid delay in getting it into place. If left standing any length of time it will set and become use- less. To avoid this, mix small batches at a time, using on a small job not more than a half barrel or two bags of cement to the batch. Should the cement take its initial set, i. e., begin to harden, before being placed in the forms, so that it lumps: when retempered, discard it, as the hardening qualities of cement are affected if disturbed after it has begun to set. If sand or gravel require washing, add to the above list of tools and apparatus : One washing screen for sand with 30 meshes to the linear inch. One washing screen for gravel with *4-inch meshes. *See footnote, page 18. 99 Too much attention cannot be paid to this important part of concrete making. The best and most convenient way to measure the sand and stone is to make a measuring box or frame as shown in Fig. 6. The inside dimensions of the box for different mixes of concrete are given in the table below, the size of the box being QUANTITY OF MATERIALS AND SIZES OF MEASURING BOXES. MEASURING +a ? rn Con- Size of Mix c & C oS Sand Gravel crete Measuring
a - o
gw 9 ; -s^
>
t)
.s
&
^2 II 8S
s s^^ 1 feg
tfl
rm ?!
oS g S 5^
e
^
8
^ "C o a r *j
rt
*-> o a. c M a
o-S^S 1 -SJI
E
*
-2 . s S S3
S -a S <" ^^
43 > C rA "S >>C>
*j O 00 O . rt c
s ls! sljl
|l|ll|1l
1 I "S JX^ rt
4111 11 r
Itll ^s-sg
^2^.? 'Sji'Sl
^C! P * B rt 5
>,S^ g ^ K^
ill 6 I-S ^
1-9 8 g| 1
3g s loljll
4MSa
P|^P|^
W W P
the middle or top of the beam instead of in the bottom, it would
certainly break under a very light load. There must be only
enough concrete outside of the steel to protect it from rusting
or fire. In floor or roof slabs of small structures this thickness
should be one-half inch to three-quarters inch below the
bottom of the steel, and for beams from one to one and one-
half inches.
A typical beam with its connecting floor slabs, the concrete
of both of which should be laid at the same operation, is shown
in Fig. 9. It will be seen that the beam reinforcement consists
of rods running lengthwise of the beam one-half or one-third
of these rods being bent up about one-third way from each end
and extending over the supports, as shown in Fig. 9 and for
the heavier beams U-shaped bars or stirrups are used which
pass under the longitudinal rods and up on each side of the
beam. The horizontal bars withstand the direct pull in the
bottom of the beam due to bending when a load is placed upon
it ; the U-bars or stirrups and the bent-up bars prevent diagonal
cracks, which sometimes occur under loading, and the bars
passing over the supports prevent the cracking of the beam on
top at the ends.
The steel in the slab is placed just above the bottom surface
at the center of the span and then bent upward over the sup-
ports as shown in the drawing.
Proportions for all reinforced concrete must not be leaner
than one part "ATLAS" Portland Cement, two parts clean,
coarse sand and four parts broken stone or clean screened
gravel. Maximum size of broken stone or gravel should not
be over one inch diameter in order to pass between and under
the steel rods. Consistency of concrete should be like heavy
cream.
COST OF CON- The cost of concrete work varies considerably on account
CRETE WORK o f tlie manv elements entering into the work. For instance,
the cost of building the various structures illustrated in this
book may be very small, as the work itself may be done by
the owner or farmer at odd times or with comparatively cheap
help, while in building with other materials, either brick or
wood, it is necessary to employ carpenters or masons. More-
over, even if the lumber for the forms costs nearly as much as
the lumber for a wooden structure, as is sometimes the case, it
32
need not be thrown away, but may be used again for other
purposes. If hired laborers and carpenters do the work it may
be stated as a general rule that concrete is always more expen-
sive in first cost than wood. On the other hand, concrete does
not rot, it does not burn, and it does not have to be painted, so
that it frequently may be cheaper in the long run. Besides
this, more unique and pleasing effects may be produced.
MATERIALS FOR ONE CUBIC YARD OF CONCRETE.
PROPORTION BY PARTS
Bbls.
Bbls.
Bbls. Gravel
Sand, in
or Stone in
Cement
Sand
Stone or
Gravel
1 Cubic
Yard
1 Cubic
Yard
1 Cubic
Yard
1
1$
3
2.00
3.00
6.00
1
2
4
1.57
3.14
6.28
1
2*
5
1.29
3.23
6.45
1
3
6
1.10
3.30
6.60
FIRE RESISTANCE. Concrete is one of the best fireproof
materials known. It resists intense heat better than iron,
steel, ordinary brick or stone, and in the San Francisco and
Baltimore fires it stood the test better than any other material.
It can therefore be depended upon to resist any ordinary fire.
Concrete is used extensively as a fire-protective covering for
steel, for which purpose about two inches is necessary. In
reinforced concrete the iron or steel should be imbedded one
or two inches for protection.
WATER TIGHTNESS. By mixing wet and using pro-
portions one part "ATLAS" Portland Cement to one and one-
half parts sand to three parts screened gravel and placing in
one continuous operation, so that no surface is allowed to
harden, or else by forming very good joints as described on
page 1 1 6, concrete is watertight under ordinary conditions.
Long walls to resist water pressure must be well reinforced
to prevent cracks due to temperature contraction, since con-
crete expands and contracts with changes of temperature just
like other materials.
CORROSION OF METAL REINFORCEMENT. Concrete
properly proportioned and mixed wet absolutely prevents any
metal imbedded in it from rusting.
SEA WATER. Concrete resists sea water, provided it is
properly proportioned with first-class materials and is carefully
laid.
EFFECT OF
EXTERNAL
AGENCIES ON
CONCRETE
33
i
LTfi'^J.l^Ijj
7
/
/
9
i h
\
. ; i 1 1
*k
Long/tuct/nal Section through Beam
\
\
>
( r
1
2
1
I
7/~
!
V
\
\
\
1
I
CO
^ -3
K O
a &
cn
r
34
ACIDS. After concrete has thoroughly hardened it resists
acids better than almost any other material. A substance like
manure, because of the acid which it contains, has been known
to slightly injure the surface of green concrete, but after the
concrete has hardened for at least a week it is proof against
injury.
OILS. When concrete is properly made and the surface care-
fully finished and is hardened before the oil comes against the
concrete, it can be depended upon to resist the action of almost
any oil.
ALKALIES. For use in the arid regions where there is
alkaline ground water, concrete should be especially rich, dense
and water-tight.
FREEZING. Concrete work should be avoided so far as
possible in freezing weather, as the frost will prevent the
bonding of different layers and will cause a thin scale to peel
off of the surface of concrete.
It is a good rule to follow, therefore, never to lay concrete
if the temperature is below freezing or liable to fall below
freezing in a day or two.
CONCRETE FENCE POSTS AT SIOUX RAPIDS, IOWA
35
POSTS.
FENCE POSTS. The use of concrete fence posts is becoming very general.
This is due not only to the scarcity and high price of good straight wood posts,
but to the almost unlimited life of the concrete post, its greater strength and
more pleasing appearance.
Concrete fence posts should be a little larger than wood fence posts, and
may be made either straight for the whole length or slightly tapering. Five
or six inches square at the bottom and four or five inches square at the top is an
ordinary size, or for convenience in molding they may not be made exactly
square, say, 6 inches by 5 inches at the bottom and 5 inches by 4 inches at
the top, this size being selected for the form shown in Fig. 10.
As a very slight heaving of a fence post by frost is not objectionable, they
hn.
>J2>Copper tV/re
Fig. 10. Design of Forms for Fence Posts.
do not need to be placed in the ground more than 2^2 feet, although if for any
reason they should be absolutely rigid the lower end should go below frost
line, which in the Northern States is as much as 4 feet down. The length of
the post is determined by the height which is desired above the ground.
Posts may be built separately, that is, in a separate form laid on the
ground, but the cheapest way is to build forms for a number of posts so that
several can be molded at the same time, and then the forms used for another
set as soon as the concrete has hardened.
36
To mold a lot of posts at one time build the forms in the following manner :
Select some place where the posts can be left in their original position for
at least ten days. Level off the ground and place the bottom planks, which
should be of i^-inch or 2-inch planed lumber, side by side upon 2 or 3 cross
sills, making a solid floor upon which to mold the posts. Place two i-inch
by 5-inch boards on edge parallel to each other and the height of the posts
apart and brace them on the outside with triangular braces as shown in the
CONCRETE FENCE POSTS AT FAR ROCKAWAY, L. I.
figure. To locate the center of first post stretch a line from one side across to
the other at right angles to the boards on edge as indicated by line AA. At
one end of this line AA measure 3 inches each side of it for the bottom of the
post and at the other end measure 2 inches each side of this line for the top of
the post. This will locate the boards BB for the sides of the posts. Nail
these intermediate boards at the ends with a nail or two to the two parallel
boards, allowing the heads to project so they can be pulled out with a claw
hammer.
Make the posts, as is shown in the sketch, with every alternate post lying
the opposite way. By so doing one intermediate board serves as a side to
two posts, thus requiring less lumber per post than by any other arrangement
37
of forms. With this method of construction also the least amount of ground
area is required for molding the posts and no bracing is necessary to support
the boards for the sides of the posts. Triangular i-inch bevel strips may be
placed on all edges, as shown in the cross section, Fig. 10, which will give the
posts a neat and pleasing appearance. These bevel strips can be obtained
readily from a mill, or they may be sawed from a i-inch board by ripping the
board lengthwise. If desired the top of the post can be finished with a taper
by simply inserting a triangular block, as shown at C in Fig. 10. Never plaster
the top of any post ; instead, remove the end form when the concrete is green
and smooth the surface with a trowel or float.
If straight instead of tapering posts are preferred, the same kind of a
form as has just been described can be used for molding them except that
the intermediate boards B are placed at right angles to the two long parallel
boards instead of at an angle to them, as shown, making them 5 inches apart.
The forms are now ready to fill and the quantity of materials for certain size
posts can be taken from the following table :
QUANTITY OF MATERIAL FOR FENCE POSTS
All Posts Are 4x5 Inches at Top; All Posts are 5 x 6 Inches at Bottom.
One-Half Small Single Load* of Sand Required per Barrel of Cement ; One Small Single
Load * of Screened Gravel or Stone Required per Barrel of Cement.
Proportion: 1 Part "Atlas" Portland Cement; 2 Parts sand;
4 Parts Gravel or Stone.
Length of Posts,
Feet
No. of Posts per Barrel
(4 Bags) of Cement
Weight per Post,
Pounds
5
6
7
8
9
20
17
14
12
11
130
160
180
210
234
* Small single load= 15 cubic feet.
The posts should be made with one part "ATLAS" Portland Cement,
two parts clean, coarse sand and four parts broken stone or gravel, about
i inch diameter particles. Grease or oil the form and fill the bottom of the
form with concrete to a depth of i inch, upon which place immediately two
pieces of ^4-inch round or steel rods or No. 6 wire i inch in from each side
and running the full length of the post. Then quickly fill the form to within
i inch of the top with concrete, tamping the wet concrete slightly to drive
out any air bubbles. Next place two more rods or wires, each i inch from
each side and fill in the rest of the concrete, spading the faces of the posts
next to the form boards to leave a smooth surface, and lightly trowel the top
surface. The end boards and the boards between the posts must not be
removed until the concrete is hard and the posts should not be handled or
moved for at least ten days without danger of cracking them. They should
be left for three or four weeks at least before using and kept damp by
sprinkling. The surfaces of the posts do not need to be finished off in any
special way, for they should be smooth enough without.
For fastening fence wire to the posts, the following method is suggested:
Take a piece of No. 12 copper wire 12 inches long, bend it in two and twist
the halves together, leaving the ends free for about 2 inches; these should be
made beforehand. While the concrete is being placed in the forms set two
or three of these copper wires in the concrete the proper distance for stringing
VIEW OF DELLWOOD PARK FENCE, JOLIET, ILL.
wires so that they will be imbedded in the post about 4 inches and leave the
two free ends to project from the post about 2 inches. See cross section of
post in Fig. 10.
Another very good method is to get a number of ^-inch or i-inch round
rods or wood dowells 6 or 8 inches long and place them vertically in the form
the proper distance apart for stringing wires. To hold them in place nail a
strip of wood across the top of the form beside the rod and drive a nail into
this strip and bend the nail around the rod so as to hold it up against the
strip. The rods should be well greased and left in the concrete about i day,
when they can be removed. If they are not well greased it will be almost
impossible to remove them without injuring the concrete. Through the holes
39
CONCRETE FENCE AT GEDNEY FARMS, WHITE PLAINS, N. Y.
CONCRETE GATE POSTS AT COLUMBIA, MO.
40
the fence wire can be strung, or a short piece of wire can be run through and
the ends twisted around the running fence wire.
There are several other methods of providing the same means of attaching
the fence wire to the posts. For instance, insert in place of the copper wire
described above a galvanized screw eye and run the fence wire through it or
attach it to the screw eye by means of wires.
CORNER POSTS. Corner posts should be made about 10 inches square the
full length of the posts and 9 feet long. On account of the weight of such a
large post it is easier to mold the posts in place, as they will weigh about 940
pounds, but if desired they can be made in the same manner as the other
fence posts just described. Reinforce corner posts with a ^j-inch rod in each
corner of the post instead of the No. 6 wire used for the smaller ones. Set a
corner post at least 3% feet in the ground. If special finish is necessary, refer
to method of treating horse blocks, page 43.
QUANTITY OF MATERIAL FOR CORNER POSTS
One-Half Small Single Load* of Sand Required Per Barrel of Cement; One Small Single
Load* of Screened Gravel or Stone Required Per Barrel of Cement.
Proportions: 1 Part "Atlas" Portland Cement to 2 Parts Sand to 4 Parts Gravel.
SIZE OF POSTS
No. of Posts per
Barrel (4 Bags)
Cement
Weight per Post,
Pounds
Length, Feet
Top, Inches
Bottom, Inches
6
12
12
2%
900
7
12
12
iy>
1,050
8
12
12
2Y
1,200
9
12
12
2
1,350
9
10
10
3
940
9
6
6
8
337
7
24
24
K
4,200
* Small single load =15 cubic feet.
COST OF FENCE POSTS. Seven-foot fence posts constructed as described
on page 36, without hiring outside help so that the cost of labor need not be
considered, can be made for about 2oc. to soc. each. They will cost from loc.
to 2oc. apiece more if the cost of labor is considered.
HITCHING POSTS. Hitching posts can be built and reinforced in the same
manner as finished fence posts. Make a post about 6 feet long so that it will
set about 2^ feet in the ground. Make forms and handle the concrete same
as described above for fence posts. Cast a long ^/2-inch diameter iron staple,
holding an iron ring, in the top of the post by passing it through a slot in the
head of the form before the concrete is poured, just as the staple is placed in
the clothes post described on page following.
41
A neat and inexpensive round hitching post
may be designated as the "stove-pipe" hitching
post. Dig a hole 18 inches deep and 10 inches
in diameter in the ground and fill with one part
"ATLAS" Portland Cement, two parts of clean,
coarse sand and four parts of screened gravel
or broken stone. Place on this base of con-
crete, before it has set, a section of 7-inch stove
pipe. For reinforcement place a i-inch gas pipe
in the center of the stove pipe and push it into
the soft base of concrete. Insert in top of post a
round hitching post ring. Leave the stove pipe
in place and paint it if desired, which makes a
very neat and attractive post. When the stove
pipe rusts off, the concrete post still remains as
attractive as ever.
CONCRETE CLOTHES POSTS AT WESTWOOD, N. J.
42
STOVE-PIPE HITCHING POST
AT COLUMBIA. MO
CLOTHES POSTS.
Clothes posts may be
made in the same general
way as the finished fence
posts, except that they
should be 6 inches square,
9 feet long, and rein-
forced with %-inch rods
in each corner instead of
No. 6 wire. Imbed an
iron staple y 2 inch in
diameter in the top of
the post for a clothes
line. This can be done
by cutting a hole in the
head of the form large
enough to pass the eye
of the staple through,
then placing the staple
before the concrete is
poured and hold it in
place by a wad of paper
to plug the hole. An-
other plan is to form a
hole near the top of the post by placing a greased dowel in the form before
pouring the concrete.
HORSE BLOCKS.
Horse blocks can be built solid in place.
Make a form or box, without a bottom, 36 inches long, 18 inches wide and
12 inches deep, inside dimensions. Grease this form and fill with concrete,
one part "ATLAS" Portland Cement, two and one-half parts clean, coarse
sand and five parts screened gravel or broken stone.
It is best not to plaster the top surface or sides of the block, for if it is
plastered it is apt to crack or peel off. The top surface should be smoothed off
with a trowel when the concrete is first laid, then in a few hours, as soon as it
has begun to stiffen, scrape off any light colored scum with a wire brush or
HORSE BLOCK, HITCHING POST AND SIDEWALK AT WESTWOOD, N. J.
horse curry comb, and trowel the surface again, preferably with a wood float,
but using no fresh mortar. The form should be removed the next day, or as
soon as the concrete is hard enough not to show thumb marks, and while the
concrete is green rub down the sides with a wood float or brick. Keep damp
by sprinkling for a week. If the surface thus left is not good enough, it may
be necessary to plaster it, even though at the risk of checking and cracking.
To do this pick the surface with a stone axe, wet thoroughly and trowel on a
coat of mortar one part "ATLAS" Portland Cement to one part clean, fine
sand, making the layer not over 1-16 inch thick.
43
The weight of a horse block of the above dimensions is about 675 pounds
and about two bags of cement are needed.
WATERING TROUGHS.
One of the most useful and essential devices about a farm is the small
watering trough, and when made of concrete it is not only of pleasing appear-
ance, but is practically indestructible. Moreover, if an inlet pipe with float
valve connection has been provided it needs absolutely no attention.
Watering troughs, like many other concrete structures, may be made
without steel reinforcement, but if so constructed the walls must be half again
as thick as when reinforced, and even then are more apt to crack. The size
and capacity of the trough varies with the purpose for which it is used, but
WATERING TANK, BOODY, ILL.
for troughs up to about 10 feet long by 2 feet wide by 2 feet deep the thickness
of the reinforced walls should be about 5 inches.
It is essential that a watering trough be water-tight. The conditions for
obtaining a trough which will not leak are (i) a richer mix of concrete than
is required for ordinary work; (2) enough water in mixing to give a sloppy
concrete, and (3) the placing of all the concrete at one operation. It is
extremely difficult to make any structure water-tight unless all three of the
above conditions are complied with.
44
FIELD TROUGH AT GEDNEY FARMS, WHITE PLAINS, N. Y.
WATERING TROUGH AT
45
HILL, L. I.
The best mix of concrete to use varies with the sand and gravel employed,
but generally speaking one part of "ATLAS" Portland Cement to one and one-
half parts of clean, coarse sand to three parts of screened gravel or broken
stone are advised, or if gravel from the natural bank is used without screening,
one part of "ATLAS" Portland Cement to three parts of natural bank run
gravel. If sand alone is available use one part "ATLAS" Portland Cement to
two parts sand.
The amount of excavation necessary for the foundation of a trough depends
upon the size. For a small trough level off the earth and tamp the ground
well before placing any concrete, but for a trough of large capacity a solid
WATERING TROUGH, DECATUR, ILL.
foundation should be used. To construct a solid and reliable foundation,
excavate about 12 inches and fill in 6 inches with either cinders or gravel from
which the sand has been screened, tamp this well and fill in 6 inches of
concrete, using only half the proportion of cement to sand and stone that is
used for the trough itself.
Next place the outer forms in position, brace and oil them well and mix
the concrete according to the directions given on page 24.
Place a 2*/2-inch layer of concrete in the form, and immediately after
46
placing and before the concrete has set, place a sheet of woven fence wire or
some other wire fabric over the concrete, bending it up so that it will come
to within one inch of the top of the forms at the sides and ends. Place 2%
inches more of the concrete in the bottom and ram lightly to bring the mortar
to the surface and smooth it off evenly. Have the inner form all ready and
as soon as the base is laid and before it has begun to stiffen set it, taking care
to keep it at equal distances from the sides, and then immediately fill in the
concrete between the outer and inner forms to the required height. The
time at which to remove the form depends upon several conditions, such as
the wetness of the concrete, the weather and the temperature, but generally
FIELD WATERING TROUGH, KNOXVILLE, IOWA
such forms can be removed within two days. After removing the forms, wet
the concrete thoroughly and paint the inside surface with pure "ATLAS"
Portland Cement mixed as thick as cream. Protect the trough from the sun
until it is filled with water keeping it wet for about a week. Do not fill with
water until a week after laying the concrete.
The outside surface can be finished off very satisfactory if done as soon as
the forms are removed by wetting the surface thoroughly with a whitewash
brush, using plenty of water, and rubbing it down with a wood float or board
47
or a brick. This will remove the marks of the form boards and make a very
pleasing appearance. (See directions for Finishing Concrete Surfaces, page
27.) A long trough is difficult to build because of the great amount of rein-
forcement required to prevent shrinkage cracks.
Where the trough is to be connected with an inlet and outlet pipe, it is
best to place the necessary pipes and connections in the forms before laying
the concrete. This will save a great deal of labor and trouble, but where
these connections cannot be made before placing the concrete, the holes for
them may be provided in the concrete by inserting greased wooden plugs irt
the forms in place of the pipes. These plugs can be easily withdrawn as soon
as the concrete has set.
Fig. ii. Design of Forms for Rectangular Trough.
The design of forms for a rectangular trough, shown above, is economical
in that the lumber for the outside forms does not need to be cut unless
desired, and can therefore be used for any other purpose, being practically
as good as new.
48
WATER TROUGH AT MONROE, N. J.
OLD BOILER TANK WATERING TROUGH AT COLUMBIA, MO.
49
Were it not for the more complicated form work, the circular shaped tank
would be built oftener because of the attractive effects which can be produced.
A simple and attractive circular form for a small watering trough is shown
in Fig. 12. It is made as follows:
Jbout 6 in..
'low Pipe
"Front Wagon
Wheel Tire.
Fig. 12. Design of Forms for Circular Trough.
Take an old wagon or buggy tire, lay it on the ground, and mark a line on
the inside of the tire. Excavate inside of tire 6 inches deep and place endwise
three i by 2-inch stakes about 3 feet long on the inside of the tire. Raise
the tire 2 feet above the ground to make the total inside depth of the trough
3 feet, and drive a nail in each of the three stakes under the tire to support it
at this height. Fill in the circle between these three stakes with slats or
flooring boards set on end and place a nail in each under the tire to hold them
at the top. To hold them at the bottom tamp a little sand at the foot of the
stakes. Mix one part "ATLAS" Portland Cement to one and one-half parts
of clean, coarse sand to three parts of screened gravel or broken stone and
lay about 4 inches of concrete. Place the reinforcement as described for
rectangular troughs, running it up on the sides so that it is about 2 inches
from the outside surface. After placing the reinforcement the rest of the
operations are the same as for a rectangular trough. The inside form may
be made by sawing a barrel in two, nailing each of the barrel staves to the
head of the barrel, and removing all but the top hoop. The construction of
the inside barrel form is clearly shown in Fig. 12. Oil the forms well before
placing the concrete.
The materials required for a circular trough like this are 3^2 bags of
"ATLAS" Portland Cement and i single load of sand and gravel. Two
men can make a trough in about one-half day each, and the cost is approxi-
mately $4.00 complete.
So
A single load of sand or gravel is considered as 20 cubic feet, or 3^ of a
cubic yard, and a double load as 40 cubic feet, or nearly i^ cubic yards.
A method of constructing a circular trough where a cut off section of an
old boiler was used, not only for the exterior form, but also as the outside
finish, is shown on page 49. This style of trough, although rather attractive,
is more expensive than the one just described on account of the cut off boiler
section, which in this case was about $10.00.
DIPPING TANK AT CHILLICOTHE, OHIO
HOG TROUGHS. A desirable hog trough can be made by building a
bottomless box 6 feet long and 12 inches broad by 12 inches deep. From a
2-inch plank saw out two triangles having a base of 12 inches and a height of
8 inches. Place these 5 feet 6 inches apart and nail a plank i inch thick on
each side of the triangle. Place the inverted V-shaped trough thus made inside
the bottomless box and put small triangular strips around the edges to make
a square edge. (See Fig. No. 13.) Grease the form thoroughly and fill the
space left with concrete mixture, one part "ATLAS" Portland Cement and
three parts clean sand or sandy gravel, tamp lightly, and smooth off to top of
box. Let stand until dry. Remove the inner forms within 3 or 4 hours, and
paint the inside with pure "ATLAS" Portland Cement, mixed as thick
as cream.
Fig. 13. Forms for Hog Troughs.
Should a trough with a round bottom be desired, an inner form can be made
by sawing a log the right length, stripping it of bark, and splitting in half.
Put this in the bottomless box described above, flat side down (Fig. No. 13),
grease well and proceed as with triangular trough.
SLOP TANKS.
Every farm should have one or more slop tanks, in order to heat the
slop and prevent it from freezing, so that the cattle can be fed no matter how
cold it may be.
Slop tanks of concrete have proved satisfactory. A concrete slop tank
should be made of one part "ATLAS" Portland Cement to two and one-half
parts clean, coarse sand to five parts of screened gravel or stone. The size
shown in Fig. 14 will require 12 bags of cement, i^/ 2 single loads of sand (20
cubic feet per singe load) and 3 single loads of screened gravel, or better still,
clean cinders.
A 36-inch iron kettle, having a capacity of 75 gallons, costs about $7.00 in
the city market, to which the freight must be added. The forms are very
simple, and can be easily made by a man in a day. The inner form need not
be removed, but can be burnt out the first time a fire is built in it. The tank
must be well reinforced in order to keep it from cracking, due to the difference
in temperature to which the tank is subject. The firing is done from the door
left in the front and the stack takes care of the draft. Do not build a fire
in the tank until the concrete has set for at least two weeks.
djn sfovep/pe
Long/ fuel/net/ *Secf/o/7
Fig. 14. Concrete Slop Tank.
53
FERTILIZING TANKS.
Fertilizing tanks should be made about the shape of and a little larger
than a barrel. If carefully made they will withstand the rough usage to
which they are subjected by being pulled from place to place on drags, and
are unaffected by the fertilizing fluids. Make the tank about 2^/2 inches thick
and well reinforced. As soon as inside form is removed wet and brush with a
layer of pure "ATLAS" Portland Cement of the consistency of thin cream
to make it water-tight. Keep the inside wet until it is to be used.
SLOP TANK AT MORTON, ILL.
RAIN LEADERS.
Rain leaders or gutters are best constructed of concrete because they can
be made for a very small cost, need no forms, are indestructible, and very
attractive.
Excavate a trench 4 inches deep by 9 inches wide in the sand or dirt from
the end of the rain conductor to the required distance from the building. Make
a small batch of concrete, in proportions one part "ATLAS" Portland Cement
to four parts unscreened sand and gravel, and fill the trench, hollowing out
the surface and troweling a little to form the trough. The water may be
carried under the surface if desired by digging a deeper trench, placing it in a
54
FERTILIZING TANK, GREENHOUSE AND RUSTIC SEAT AT WESTWOOD, N. J.
RAIN LEADERS, DUMONT, N. J.
55
length of tin or sheet-iron pipe and surrounding this with concrete. When the
pipe rusts out, the concrete tube will still remain.
RETAINING WALLS.
Concrete retaining walls in most localities cost much less than rubble
masonry. The design of the retaining walls shown in Fig. 15 is what is known
as the gravity section, which means that the earth pressure is resisted by the
weight of the wall. The following table gives the necessary dimensions and
RETAINING WALL AT DUMONT, N,. J.
the amount of materials per foot of length of wall. The amount of material is
figured, assuming that the concrete is made of one part "ATLAS" Portland
Cement, two and one-half parts of clean, coarse sand, and five parts of
screened gravel or stone. The foundation, as shown, is taken 4 feet below
the ground level. In the Southern States, 3 feet, or even 2 feet, will be
sufficient to get below the frost line.
The exposed side or face of the retaining wall can be finished off in the
same manner as described on page 27. The top surface must not be plastered
or it will crack and is apt to peel off. The surface should be smoothed off with
a trowel when the concrete is first laid, then as soon as it has begun to stiffen
scrape off any light-colored scum with a wire brush or old curry comb, wet
slightly, and trowel it, preferably with a wood float, but using no fresh mortar.
56
Fig. 15. Design for Retaining Wall.
DIMENSIONS OF RETAINING WALLS AND QUANTITY OF MATERIALS
FOR DIFFERENT HEIGHTS OF WALL.
Proportions: 1 Part "Atlas" Portland Cement to 2} 2 Parts Sand to 5 Parts Gravel or Stone.
(See Figure 15.)
AMOUNT OF MATERIALS PER
Height of
Wall
Total
Thickness
Thickness
at
Thickness
ONE FT. LENGTH OF WALL
Above
Ground
Height
of Wall
at
Base
Ground
Level
at
Top
Cement
Sand
Gravel or
H
B
A
Stone
Feet
Feet
Ft. In.
Ft. In.
Inches
Bags
Cu. Ft.
Cu. Ft.
2
6
2 2
1 6
10
1 %
43^
9
3
7
2 5
1 7^>
10
2 i/o
5 3/0
11
4
8
2 9
1 11
12
3
7
14
5
9
3 2
2 1
12
3/^
9
19
6
10
3 6
2 4^
15
4M
1 1 3^
23
7
11
3 10
2 8
18
6
14
28
8
12
4 2
2 10
18
7
16MJ
33
Note: A large single load of sand or gravel is about 20 cubic feet.
A large double load of sand or gravel is about 40 cubic feet.
57
DAMS.
If a dam is to be built more than 4 or 5 feet above the bed of the stream,
an engineer should be called upon to design it and look after the construction.
For an ice pond or a pond for watering stock a concrete dam may be built
across a brook without difficulty.
If possible, dig a temporary trench so as to carry the water around the dam
while it is being built. If this cannot be done, run the water through a wooden
trough in the middle of the dam, and after the wall, each side of it, is finished,
DAM AT ARLINGTON, VA.
carry the forms across the opening, and make these tight enough so that the
water is quiet between them ; then place the concrete as described on page 26.
Dig a trench across the stream slightly wider than the width of the base of
the dam, carrying it down about 18 inches or 2 feet below the bed of the brook,
or if the ground is soft, deep enough to reach good, hard bottom. In case the
earth is firm enough for a foundation, but is porous either under the dam or
each side of it, sheet piling consisting of 2-inch tongued-and-grooved plank
can be pointed and driven with a heavy wooden mallet so as to prevent the
water flowing under or around the dam. Build the forms so as to make the
58
wall of the dimensions shown in the table. Wet them thoroughly, then mix
and place the concrete as described on page 24.
Use proportions one part "ATLAS" Portland Cement to two parts clean,
coarse sand to four parts screened gravel or broken stone.
Take special care to make the concrete water-tight by using a wet mix.
If possible, lay the entire dam on one day, not allowing one layer to set before
the next one is placed. If it is necessary to lay
the concrete on two different days, scrape off
the top surface of the old concrete in the morn-
ing, thoroughly soak it with water, and spread
on a layer about J4 inch thick of pure cement
of the consistency of thick cream, then place
the fresh concrete before this cement has begun
to stiffen.
If the forms on the lower side of the dam
are well braced, the forms on the upstream side
may be removed in three or four days, and the
pond allowed to fill. The forms on the down-
stream face should be left in place
well braced for two or three weeks.
No finish need be given to the sur-
face.
Fig. 1 6. Design for Dam.
DIMENSIONS FOR SMALL DAMS AND QUANTITY OF MATERIALS FOR
DIFFERENT HEIGHTS OF DAMS.
Proportions: 1 Part "Atlas" Portland Cement to 2 Parts Sand to 4 Parts Gravel or Stone.
(See Fig. 16.)
Height
Above
Bed of
Stream
Depth
Below
Bed of
Stream*
Thickness
at Base
Thickness
at Top
AMOUNT OF MATERIALS PER FOOT
OF LENGTH OF DAM
Cement
Sand
Gravel or
Stone
Feet
H
Feet
G
Feet
B
Feet
T
Bags
Cu. Ft.
Cu. Ft.
1
2
3
4
5
6
IK
Ifcj
1H
2
2
1
1
2
2
2K
3
1
1
1H
iH
iH
\y>
H
1
1 3 4
2M
3^
iiS
%
1M
4
5
6%
8%
IK
3
8
10
13 K
Hi!
* Make deeper if necessary to get a good foundation.
Note: A large single load of sand or gravel is about 20 cubic feet.
A larg double load of sand or gravel is about 40 cubic feet.
59
WALLS.
Concrete walls are everywhere being built in preference to stone, on
account of the lower cost and thinner walls which are usually required. Unless
stone can be laid at practically no expense, the concrete is cheaper.
Every wall should have a footing, that is, a base wider than the wall it
supports, and must be carried down below the frost line. The depth of such
footings, therefore, must be varied according to the section of country in which
the work is being done. In general, they should be about 4 feet below the
ground level in the Northern and Middle States, and about 3 feet in the
Southern States, while in very mild climates 2 feet will be sufficient. The
footing should be not less than 4 to 6 inches thick and should extend about the
same distance each side of the wall.
HOUSE FOUNDATION AT SUMMIT, N. J.
Care must be taken to see that the foundation is not placed on a soft and
yielding soil. Where the soil is unsuitable, either excavate until rock or a
better material is found, fill in up to frost line with gravel and tamp it well
while placing. When there is any danger of this filling of gravel forming a
pocket in which the water will accumulate, dig a ditch away from the wall so
that the water will run off.
CELLAR AND BASEMENT WALLS. Cellar or basement walls must
withstand the earth pressure that comes upon them. This pressure varies
with the depth of the cellar or basement, and hence the thickness of the walls
60
CONCRETE HOUSE AT DECATUR, ILL.
CONCRETE HOUSE NEAR MORTON, ILL.
6l
should vary with the depth as shown in the following table:
THICKNESSES OF WALLS AND QUANTITIES OF MATERIALS FOR DIFFERENT
HEIGHTS OF BASEMENTS.
Proportions: 1 Part "Atlas " Portland Cement to
Gravel or Stone.
Parts of Sand to 5 Parts of
Depth of
Cement per
Sand per
Gravel or
Height
Foundation
Thickness
Thickness
10 Ft. of
10 Ft. of
Stone per
of
Below
of Wall
of Wall
Length of
Length of
10 Ft. of
Basement
Ground
at Bottom
at Top
Wall
Wall
Length of
Level
Wall
Feet
Feet
Inches
Inches
Bags
Cubic Feet
Cubic Feet
6
4
6
6
6
14 H
29
8
6
10
8
12
29
58
10
8
15
10
24
57
114
The thicknesses are less than for a retaining wall out of doors because the
weight of the building and the floor timbers strengthen it. The back of the
wall may batter or slope to save concrete. If vertical use bottom thickness for
the full height. The earth must not be filled in against the back of the wall
until three or four weeks after placing the concrete unless the forms and
bracing are left in place in front.
a- Fig. 17. Cellar Wall Forms.
62
Where there is no earth pressure against the wall let the forms remain
not less than 24 hours, or until the concrete will withstand the pressure of
the thumb.
Fig. 17 illustrates a simple design for cellar or foundation walls: (a) of
the figure represents view of an ordinary form, 2-inch by 4-inch braces being
attached to the studs as braces; the form sides do not extend to the bottom
so as to allow the concrete to flow out and form a spread footing; (b) repre-
sents a wall for which the bank of earth serves as one side of the form. This
condition may occur when the soil is of a clayey nature, which does not cave
in, or where the new wall is being built against an old one.
CONCRETE BARN AT TAMPICO, ILL.
Cellar or basement walls should be laid with one part "ATLAS" Portland
Cement to two and one-half parts coarse sand and five parts of broken stone
or screened gravel.
As concrete is the best material for cellar walls or footings of any kind, it
is often used for this purpose even where the rest of the building is of wood
or any other material. The building foundation should be brought up to the
required height above the ground level. To attach the wood superstructure to
the concrete foundation place on the concrete, imbedding it in mortar, the
wood sill, which is made with the ends halved and bolted together. In the
West, where the winds are very strong, this sill must be bolted to the concrete ;
this is done by placing occasional bolts in the concrete when laying it, letting
63
the nut end protrude above the foundation to bolt through the sill. Holes can
then be bored in the sill to fit over the protruding bolts and the nuts placed,
thus firmly securing it.
Fig. 1 8. Wall Forms.
WALLS ABOVE CELLAR OR BASEMENT. Concrete walls above the
cellar may be built either as a single solid wall or as two walls with an air
space between them. Such an air space renders the building less subject to
changes of temperature and more completely moisture proof, but it is more
expensive.
A solid concrete wall 6 inches thick is at least equivalent to 12 inches
of brick. Walls 6 inches in thickness should be reinforced with vertical rods
WAR N ING
Many people have been confused
by the meaning of Portland
Cement and accept any cement
bearing the word "Portland."
The word " Portland" signifies
only the kind of cement, but does
not designate the brand.
Specify the word " ATLAS"
when buying cement and you
will get the best.
There is but one grade of
ATLAS Portland CEMENT
the best that can be made the
same for everybody.
This Trade Mark is on every barrel and every bag of
ATLAS Portland CEMENT
PWIUHD '^
ATLAS)
The Directions given in this book have been
prepared, based upon the use of
ATLAS Portland CEMENT
which is of uniform strength and quality, and
made from genuine Portland Cement Materials
only. It contains no furnace slag.
Accept no substitute.
The U. S. Government purchased 4,500,000
barrels of ATLAS Portland CEMENT for use
in the construction of the Panama Canal.
J4 inch in diameter placed 18 inches apart and with horizontal rods Y$ inch in
diameter placed 12 inches apart. Additional rods must be placed at corners
and diagonally across the corners of all openings. Walls of small buildings,
such as hen houses, may be made 4 inches thick with the same reinforcement
described. Where hollow wall construction is used, make each of the walls
4 inches thick and about 9 inches apart, and tie together with galvanized-iron
strips, or place piers of concrete 4 feet apart to connect the two together.
Where such piers are used they are built at the same time as the two walls,
making practically one wall with air chambers at regular intervals. A very
simple method to construct a hollow wall is by using 2-inch planed plank, as
shown in Fig. 31 (p. 102).
Fig. 19. Hollow Wall Forms.*
Fig. 1 8 shows a design of wall forms for building a solid wall of any height.
The form sections are each made 2 feet high and the length depends upon the
length of boards at hand. A 2-foot section made of i-inch boards 10 feet long
weighs 55 pounds, which can therefore be handled easily by one man. The
cleats are made to lap over the top of the form i% to 2 inches, in order to
catch the next section placed on top of the one just filled with concrete. No-
tice, also, that the cleat at one end projects beyond the form bracing so as to
catch the next section and hold it in place. Use bolts for holding the forms
together, as they are better than wires, which cut into the cleats and spring the
forms apart. The bolt holes left in the wall, as shown in Fig. 18, are a
means of constructing a very efficient and cheap scaffolding. All bolts should
*See Footnote p. 18.
65
CONCRETE POSTS FOR SUPPORTING TROLLEY FOR LITTER CARRIER AT NEWBURGH, N. Y.
be well greased so that they can be readily removed. After completing the
wall the bolt holes can be filled with mortar mixed in the same proportion as
the concrete so that the color will be the same as the wall.
Sometimes a building is built with a wood superstructure on top of
concrete walls which are only from four to eight feet above the ground. In
this case the wood superstructure can be attached to the concrete walls in the
same manner as described on page 63 for connecting a wood building to a
concrete foundation.
66
COLUMNS.
Excavate below frost and build forms 2 feet square to within 6 inches of
surface of ground. Fill with concrete, one part "ATLAS" Portland Cement,
two and one-half parts clean, coarse sand and five parts broken stone or
screened gravel, not over one inch in size, and tamp or puddle carefully. From
the center of this foundation build a hollow form one foot square and to desired
height, and fill with concrete of same mixture. Before the form is filled in
fact, before setting it place four steel bars ^4 inch in diameter ver-
tically so that they are about 2 inches inside the corners, and around them,
Fig. 20. Column Form.
at intervals of one foot, wind loops of ^-inch or ^-inch wire, tying these to
the steel rods with fine wire. Make the concrete soft and mushy, so that it
will just flow, and, as it is poured into the top of the mold, work a long paddle,
made like the oar of a rowboat, against the forms to force the stones away
from the surface and drive out bubbles of air which tend to adhere to the
boards and form pockets of stone.
A column 10 inches square, the smallest size it is usually desirable to build
unless it is quite short, will safely support 15 tons, or 30,000 pounds.
67
INTERIOR VIEW OF MANURE PIT AT GEDNEY FARMS, WHITE PLAINS, N. Y.
DETAILS OF PIERS AND FLOOR BEAMS UNDER HORSE BARN AT GEDNEY FARMS, WHITE PLAINS, N. Y.
68
STEPS AND STAIRS.
Steps and stairs are of two kinds : those made in one piece, monolithic, and
those cast in separate moulds and put into place. There are numerous ways
of arriving at the same end, and each man in charge of such work must use
his ingenuity in the use of the materials at hand, and adopt the method best
suited to his requirements. Specifications are given for four ways of making
steps and stairs, all of which have proved successful.
FLYING STAIRS, DAIRY HOUSE AT GEDNEY FARMS, WHITE PLAINS, N. Y.
The rises on all steps and stairs should not be less than 6 inches nor
more than 8 inches, while the tread should be from 9 inches to 12 inches,
except where it is intended that more than one step should be taken on the
tread, in which case 30 inches should be the minimum width.
Foundations for all steps out of doors should extend below frost line or
have a porous base with a drain situated at the lowest point to allow the water
to run off. Steps should be wider than the walk or opening from which they
69
SIDEWALK AND STEPS AT WEST HAVEN, CONN.
lead, to avoid looking cramped, and, in order to secure an artistic effect, should
have some sort of projection, or moulding, at the upper edge. A slight slope
to allow the water to run off is also desirable.
Let us first consider steps to areas or terraced grounds. Excavate the earth
on the slope to the desired depth (see Foundations for Sidewalks) and put in
Aforfcrr F/nish
._
Fig. 21. Concrete Steps.
70
porous foundation with a drain at the lower end to dispose of any water that
may accumulate.
Take two planks the length of the flight of steps on the slope, and wide
enough to house each step, and mark upon them the location of the riser for
each step. Place these planks edgewise on each side on the slope, and brace
CELLAR STEPS AND ICE BOX AT WESTWOOD, N. J.
well on the outside. Place the necessary reinforcement, as given in the table,
the full length of the steps on the slope. Now set planks marked (b.) Fig. 21,
across these housings to form the rise of each step on the lines previously
marked, placing them so that there will be a space below them for a continuous
slab of concrete. The thickness of the slab is given in the table under column
marked "A." These planks should be arranged with a groove at the top, as
shown, to form the projection or moulding at the top of each step. They
should be fastened to the housing planks with cleats in such a way that they
can be removed without disturbing them. Inside of each of these riser forms
place a loose piece of board, well greased, as described for facing curbing on
page 79, so as to provide a space which can later be filled with mortar. Now
pour into the forms thus made concrete in proportions one part "ATLAS"
Portland Cement, two parts clean, coarse sand, and four parts broken stone or
screened gravel, filling each step to within i inch of the top of the riser. As
soon as this concrete has stiffened, but before it has set, carefully draw out
PORCH STEPS AT GREENPORT, L. I., N. Y.
the loose facing board and fill the spaces with mortar one part "ATLAS"
Portland Cement to one and one-half parts clean, coarse sand, and also cover
over the top of the step to the depth of i inch with the same mortar, so that
it will come flush with the top of the riser plank. Float the surface lightly
with a wooden float, and as soon as it has stiffened hard enough to work,
trowel it thoroughly. Early next day remove the riser form, the bottom of
which, as shown in the figure, is beveled and comes only to the top of the
mortar surface, and trowel the face of each riser. A skilled plasterer should
be employed for this work, as the surface is likely to crack if not handled in a
workmanlike manner.
Porch steps, and other short flights, can be built as follows: Build two
8-inch walls to a depth below frost, the upper surface conforming to the desired
72
pitch of the steps, but 3 inches below the points where the inner edges of the
treads meet the risers. Carry the outside form, however, on the same slope to
Fig. 22.
Waffs -fobebu/ff-befow frost
Fig. 23.
Fig. 22. Form for a Single Step.
Fig. 23. Single Steps in Place.
the line of the top of the risers. Between the walls build a sloping platform
out of i-inch boards supported by 2 x 4-inch stuff, well braced and conforming
to the slope of the walls. Upon this sloping platform place ^-inch steel bars
12 inches apart running from top to bottom. Also, crossways place one
2i-inch bar just at the foot of each rise, and fasten these to the y^-inch bars by
soft wire. Next mark for the location of the risers the side forms which project
above the 8-inch walls, place cross plank on each to form these risers, and
proceed in the same manner as has been described for area steps. Forms
should not be removed from under the steps for 28 days. Should the steps be
more than 6 feet wide, a wall similar to the two side walls may be built in the
center.
Sometimes it is easier to build a wall at the top and bottom of the steps
instead of at the sides, and run the principal rods lengthwise of the flight, so
that it is supported at top and bottom. In this case the supporting slab, whose
thickness must be considered as the thinnest place in the steps, is designated
in Fig. 21 by "A." The span, that is, the "distance apart of the beams," in the
table is taken as the length of the horizontal projection of the stairs. The
thickness of the slab and the diameter and spacing of the rods are given in the
table following.
73
DIMENSIONS OF STAIRS
(S=e Fig. 21, Page 70.)
Distance
Between
Floors
Feet
Rise
Inches
Tread
Inches
A
Inches
Size
of Rods*
Inches
Spacing*
Inches
No. of
Rods
in Top
Beam
Size of
Rods
in Top
Beam
Inches
No. of
Steps
10
iy>
10
7
or y%
4
1
y%
16
9
*t\i
10
6 y,
M
or y%
4^4
1
5 /8
15
8
7*
10
6
or ^8
s|
1
N
13
7
7
10
5H
or ^s
9
1
y*
12
6
7M
10
4K
N
or 1^
4
7
1
y*
10
5
7Ji
10
334
or i|
PM
1
y*
8
4
7
10
3M
or^|
6
11
1
v,
7
3
7M
10
2y 2
^
9
1
y*
5
* Select either size and spacing preferred.
Steps cast separate from supporting walls should be made in advance and
allowed to season. The sectional drawing illustrates this form of step. To
build a single step, make form shown in Fig. 22, 14 inches x 7 inches inside
measurement and i inch for projection, and fill as shown to within i inch of
top with concrete, one part "ATLAS" Portland Cement, three parts clean,
coarse sand and six parts broken stone, tamped hard. As soon as this has
stiffened, but before it has set, remove the board "a" next to the face of the
concrete, which should not be fastened to the form, but simply set in and well
greased. This will leave a space on the side and top of step, also a small mould
for the projection at top of step. Fill this with wet mortar, one part "ATLAS"
Portland Cement and one and one-half parts clean, coarse sand, and let set.
The side forms may then be removed and used again. The two side walls for
these steps may be 8 inches wide, spread at the base by allowing the concrete
to flow out under the forms. The top is stepped off to conform to the bottom
and back of steps (Fig. 23.) Place the steps on the walls thus made, after
covering all joints with cement mortar, so that they overlap one another 2
inches. Reinforce all steps and stairs cast separately by iron bars placed
about i inch above the bottom of the slab.
74
SIDEWALKS.
Before laying the concrete a foundation of porous material, such as cinders
or screened gravel, must be placed and as much care should be taken in laying
this as the walk itself. Foundations should generally be 6 inches to 12 inches
deep, depending upon the climate and character of the soil. In sections where
there is a porous soil and a mild climate, foundations are sometimes omitted
entirely. If the soil is clayey, blind drains of coarse gravel or tile pipe should
be laid at the lowest points in the excavation, to carry off any water that might
accumulate in the porous material of the foundation. Walks are frequently
ruined by water freezing in the foundations and heaving them out of position.
Excavate to the sub-grade previously determined upon, 3 inches wider on
each side than the proposed walk, and fill with broken stone, gravel or cinders
to within 4 inches of the proposed finished surface, wetting well and tamping
in layers, so that when complete it will be even and firm, but porous. Place
2-inch x 4-inch scantlings (preferably dressed on inside and edge and perfectly
straight) on top of the cinder foundation, the proper distance apart to form
the inner and outer edges of the walk. The outside or curb strips must be i
inch to 2 inches lower than the inner edge of the walk. This will give a slight
incline to the finished surface and allow the water to run off. A good rule to
follow is to allow %-inch slope to every foot of width of walk. For wide walks
lay off the space between the scantlings into equal sections not larger than
6 feet square, put 2-inch x 4-inch scantlings crosswise and in the center, as
shown in Fig. 24 this will make every alternate space, shown in figure by
diagonal line, the size desired. Fill these spaces with concrete to a depth of 3
inches (this depth should be 4 inches where there is more than ordinary traffic,
or where the blocks are 6 feet square) one part " ATLAS" Portland Cement,
two parts clean, coarse sand, and four to five parts broken stone or screened
gravel then tamp until water begins to show on top. On the same day, as
soon as the concrete has set, remove crosswise and center scantlings, place a
sheet of tar paper on the edges to separate them from all other squares and fill
in the spaces thus left with 3-inch concrete as before. Mark the scantling to
show where the joints come.
The finishing coat should be i inch thick, of one part "ATLAS" Portland
Cement and one and one-half parts clean, coarse sand, or crushed stone screen-
ings. This coat should be spread on before the concrete has taken its set, and
smoothed off with a screed or straight edge run over the 2x4 scantlings, the
object being to thoroughly bond the finishing coat to the concrete base. If the
bond between the finishing coat and the concrete is imperfect, the walk gives
a hollow sound under the feet, and is liable to crack after having been down
75
>.
I
76
one or two years. Smooth with a wooden float, and groove exactly over the
joints between the concrete (Fig. 24), so as to bevel the edges of all blocks.
Do not trowel the finishing coat too much, nor until it has begun to stiffen, as
this tends to separate the cement from the sand, producing hair cracks, and
giving a poor wearing surface. Keep the finished walks protected from dust,
dirt, currents of air and the hot sun during the process of setting, and further
MATERIALS FOR 100 SQ. FT. OF CONCRETE.
BAGS OF CEMENT TO 100 SQ. FT. OF CONCRETE
SURFACE
BAGS OF CEMENT TO 100 SQ. FT. OF MORTAR
SURFACE
Thickness
Inches
Proportions
Thickness
Inches
Proportions
1:1^:3
1:2:4
1:3:6
1:1
1:1^2
1:2
3
4
5
6
8
10
12
NCI XMS-JX-HX^X^).
i-H\ iH\CO\CO\CO\CO\
OC --H -Y - TT~~~TTll-iriW'!^"""T""'-'TT""--'T .
Mixing Ffoom \ /*" 7 -. ^!-j, ^^'\
^ 1 1 1 i 1 1 i i i i I i i J; ; ^LLI i i i I i .m J
Total length 254 rJ.
Trolley
VS//0
Fig. 28. Plan of the Farm Building at the New York Catholic Protectory,
Somers Center, N. Y.
RUNWAYS FROM STABLES.
To construct a runway from a stable make up two or three batches of
concrete in proportions one part "ATLAS" Portland Cement to two parts
sand to four parts gravel or broken stone, spread it in place, and roughly
trowel the surface. If a fine, smooth surface is desired, it may be built like a
sidewalk (see p. 75) with a 4-inch base of concrete and one inch wearing
surface of mortar of one part "ATLAS" Portland Cement to two parts sand.
If the runway is built on a slope which consists of filled ground, care
must be taken to see that the fill is well tamped and not liable to settle. If
there is any danger of the filling settling from under the runway, it must be
designed as a flat slab. In this case the thickness of slab and amount of
reinforcement necessary for the width and span of the runway can be taken
directly from the table on page 30, using the heaviest loading. For example,
if the length to be supported is 8 feet, place ^2-inch rods in bottom of slab,
7*/2 inches apart.
89
DRAINS.
Since well-made concrete, after it has hardened, is not injured by manure,
concrete is being used to replace wooden or masonry drains which are
continually rotting or leaking.
Drains may be made either in place, or tile, described below, may be used.
In any case lay the drain with enough slope to flush properly, and if it is to
receive material liable to clog, make it open or with a removable cover.
INTERIOR VIEW OF BARN AT EAST NORWICH, L. I.
To make a drain in place, dig a trench on the proper slope. Set sections
of form the shape of the inside of the drain so that the concrete will be 3 or 4
inches thick. Pour the concrete, mixed in proportions one part "ATLAS"
Portland Cement to three parts coarse gravelly sand, into the trench under
the form. Remove the form when the concrete has hardened for about one
or two hours, and gently trowel the surface to make it smooth and bring the
cement to the surface.
If the drain is to have lids, the concrete of the sides is left down so as to
leave room for the lid and have the top sunk about T /\ inch below the level of
the floor.
90
TILE DRAINS
Concrete land tile drains, when made of one part "ATLAS" Portland
Cement to three parts clean, coarse sand which has been sifted through a
5/2-inch mesh screen and of a soft, mushy consistency like mortar used for
laying brick, can be depended upon to resist the chemical action of even the
most alkaline ground water. The tile may be made 12 or 18 inches long, and
the inside diameter anywhere from 4 to 12 inches.
The forms for making concrete land tile are simple and inexpensive. One
or two sets of forms with four or six tile each may be made so that they can
MOLDING TILE DRAINS
be filled every morning, and in this way enough tiles can be soon on hand to
drain a large acreage of land. The concrete tile should be made with a
circular bore, and may be either circular or square on the outside. A photo-
graph of a tier of four forms, with two of the tile on a board, is shown above.
Use ordinary stove pipe of the required diameter for the inside mold; this
should project far enough above the top of the wood form so that a good grip
can be had on it in order to remove it from the concrete. If desired,
holes can be punched through the stove pipe near the top and a rod placed
through these holes in order to more easily draw the pipes. To keep the
91
pipes in place when pouring the concrete for each tile, drive four nails in the
floor or platform on which the tile are to be cast, leaving them projecting so as
to locate the end of the pipe and keep it from getting out of position but yet
not hindering its removal. The stove pipes must be thoroughly cleaned and
greased each time they are used, and must not be dented or have any irregu-
larities on them to make them catch.
As shown in the photograph, the wood partitions are permanently attached
to one of the long sides, but the other side is only nailed on temporarily and
the heads of the nails left so that they can be readily withdrawn with a claw
MANURE PIT AT GEDNEY FARMS, WHITE PLAINS, N. Y.
hammer and without jarring the forms unnecessarily. The wood partitions
are spaced far enough apart so that there is one inch of concrete between
stove pipe and the wood, hence make the distance between the sides equal to
the diameter of the stove pipe, plus 2 inches. In order to readily remove the
wood forms, clean and oil them thoroughly before each time using. Mix the
concrete to proportions and consistency given above and place in the mold,
ramming with a stick. The time to remove the stove pipe core varies with
the wetness of the mix and the temperature, but it should be pulled as soon
as the top of the concrete begins to harden, which generally is from one-half
to one hour ; if left too long it is very hard to get them out. The outside forms
92
can usually be removed after two or three hours, or may be left until the next
morning. To remove the wood forms, pull the protruding nails with a claw
hammer, and carefully remove this side. Place this sideboard back again in
position, and carefully turn the whole tier on the side. Next draw out the
other side with the partitions attached. If any of the forms stick, they can
generally be started by tapping them lightly with a hammer; this applies as
well to the stove pipe cores. Scrape the form carefully, re-oil, attach the long
side and they are ready for a second filling.
To save material the outside of the tile may be made round or octagonal.
For the latter tack triangular strips in all corners of the mold.
iin. sfee/ bars
2.4/n. on centers
^6 in.
4/ri.
///? sfee/ bars
vSec/xo/7 of drain
f-3in. chestriut plank
or 2
2
4
10
10
6
M
12
isy 2
4
8
15
5
6
M
12
9>o
3
6
15
8
6
%
12
14^1
4
8
15
12
6
3 /8
12
24
6K
13
20
8
6
X
12
19^
5
10
20
12
6
3/8
12
29^
8
16
20
15
6
12
38
10
20
25
10
6
/4
12
27 y 2
7y 2
15
25
15
6
y 2
12
45
12
24
25
20
6
1 A
12
62
16X>
33
30
10
7
>2
12
37
10
20
30
15
7
1 A
12
58
is y.
31
30
20
7
y*
12
80
22 i|
45
40
15
8
1 A
12
80
22 y,
45
40
20
8
y*
12
114
30V 2
61
40
25
8
%
12
147
3Sy
77
Place vertical rods same size as horizontal, 2 % feet apart.
A cubic yard is about \\ single load or of a double load.
The method of laying out the curves in order to make a section of the
form for a silo shown above is given in Fig. 33.
The complete circles can be laid off in this manner on any level piece of
ground or on a barn floor.
After laying out the circles, divide them into a number of equal parts in
order that the sections shall be alike, eight divisions generally being the most
convenient, for then the sections are not too large to handle easily, nor too
small, making too many in number. Make all the joints between the sections
on lines with the center of the silo except one inside joint, which is cut on an
angle, as shown in the drawing, in order to permit removing the inner forms.
This section which is cut at an angle is placed last and removed first.
The curved boards for the frames of the form sections can be cut either
from one wide plank, as shown in Fig. 33, or from two narrow planks which
are tacked together. The frames may be covered either with sheet iron or
with thin boards 3 or 4 inches wide nailed endwise to the frame.
The forms can be made also by riveting angle irons to the sheet iron to
stiffen it instead of the wood shapes. While the metal form is more expensive
than wood, if a number of silos are to be built, the first cost of the forms can
be larger, because it is divided among several. One man making a form of
this type can rent it to his neighbors, and in this way more than pay for the
extra money spent in making the forms.
10$
Fig. 33- Method of Laying Out Silo Forms.
Excavate the earth to a depth below frost, which in the Northern and
Middle States is about 4 feet, while in the Southern States 3 feet, or even 2
feet, may be sufficient and of the required diameter. If the earth is hard and
will stand alone sometimes it is only necessary to excavate to the outside
diameter of the silo. In other cases the diameter of the circle for excavating
must be 4 or 5 feet larger than the outside diameter of the silo, so as to allow
for a 2 or 2^ -foot trench to make room for placing and removing the outer
form. Grease the forms thoroughly. A mixture of fat or lard with kerosene
makes a good grease for oiling the forms.
Care must be taken in placing the reinforcement. Locate the horizontal
reinforcement by marking on one or two of the 4 by 4-inch upright studs of
the scaffolding the location of all the rods; then there will be no question
whether or not the reinforcement is in the correct position.
106
Before mixing the concrete, bend the horizontal rods into rings so that they
will go in the middle of the wall. Lap the ends 2 feet. To find the length of
rod to go around a silo, add to the inside diameter the thickness of one wall
and multiply this sum by 3 1/7. This gives the circumference of the center
line of the wall. If the length of this circumference is not too long for one
rod, add 2 feet for the lap. If two rods are necessary, add 2 feet for each lap ;
that is, make every rod 2 feet longer than is required for the actual circum-
CONCRETE SILO AT CHARLOTTESVILLE. VA.
ference. By placing the inside form of the silo first, the reinforcement may
be set in advance of the concreting, the horizontal rods being tied to the
verticals by soft wire about 1/16 inch diameter. This is a better way than to
place the horizontal rods as the concrete is being laid. The table gives the
distance apart of the horizontal rods at the bottom of the silo. Increase the
spacing slightly toward the top so that at the top the rods are double the
distance apart they are at the bottom.
107
Mix the concrete, using one part "ATLAS" Portland Cement, two parts
clean sand and four parts broken stone or screened gravel. For mixing of the
concrete, see page 24. Make the mixture of sloppy consistency about like
heavy cream, place it in the forms and ram lightly to distribute the mortar
and drive out air bubbles. Before removing the forms, clean off the top of the
wall with a stiff wire brush or an old horse curry comb, and raise the forms
for the next filling. Before placing the new concrete, wet thoroughly the sur-
face and spread a ^-inch layer of mortar mixed about one part "ATLAS"
Portland Cement to one part sand and then place the concrete. Care must be
CONCRETE SILOS AT EAST NORWICH, L. I.
(The dimensions of these silos are as follows: Footing, 4 feet below ground; 20 feet inside diameter; 24 feet above
ground; 12-inch walls reinforced vertically with 1-inch rods 4 feet c. to c. and horizontally with J^-inch rods 3 feet
c. to c. There were 443 bags of "ATLAS" Portland Cement used.)
used in tamping the concrete, not to push the rods to one or the other side of
the form, but to keep them in the center of the wall.
As soon as the forms are removed roughen the inside surface by scraping
off the skin of cement with a wire brush or a brick; as soon as the walls of
the silo are completed wet the inside surface thoroughly with clean water, and
plaster it with not over a i/i6-inch coat of one part "ATLAS" Portland
Cement to one part clean, coarse sand, screened through a fine screen. Pro-
108
tect the surface from the sun and wet twice a day for seven days. It is very
important to have this inside surface perfectly smooth, for when the ensilage
settles after being packed, any roughness of the walls is liable to cause the
cornstalks to catch and prevent them settling evenly. The ensilage around the
air space thus formed becomes moldy and must be thrown away. This same
thing occurs where the concrete is laid with too little water. The concrete
then is porous and sucks out the moisture from the ensilage, forming a dry
skin of material next to the wall.
Defaif ofCffufc DC.
ff very on Line B-B.
Fig. 34. Details of Silo Built at U. S. Soldiers' Home, Washington, D. C.
The outside surface of the silo is generally good enough if it is rubbed
down with a board or a brick, using water with it, immediately after taking off
the forms while the concrete is fairly soft so as to take off the joint ridges
and leave a uniform surface. By removing the forms the next day after laying
the concrete, it is possible then to entirely remove the skin of cement, leaving
the sand and stone exposed enough to give a very pleasing finish.
For convenience in handling the ensilage, it is well to leave openings or
doors about 20 inches square at least every three feet on one side of the silo.
109
Do
or
n P/ank
iH
H
ii
1
i
i
i
1
I
1
1
(-
1
i
____
i
~T
i
i
;!
'
i
i
i
i 1
c
1 .
- - -Jf^m
i
13
ll
i
i 1
1
1
i
j
!
1
1
1
i
~_Hi
IT
--D
35- Door for Silo at East Norwich, L. I., N. Y.
CONCRETE SILO FOUNDATION AT BRICELYN, MINN.
110
When desired, an opening 20 inches wide may be left the entire height of the
silo if a part of the horizontal reinforcement is run across the opening to
strengthen it; this opening is to be closed by a series of wooden doors. A
good design for a door or a series of doors is shown in Fig. 35.
A chute running to the full height of the silo has sometimes been built
around these doors or openings being constructed simultaneously with the
SILO AT SOUTH CHARLESTOWN, OHIO
walls. Make the walls of the chute 4 inches thick and reinforce them. A
convenient size for such a chute is about 4 feet along the face and 25/2 feet at
the sides.
One method of building a chute is illustrated in Fig. 34. The chute is
made of 1 2-inch tiles and pipe, each length being 24 inches. Alternate lengths
of plain pipe and tiles were used so as to bring the openings 4 feet apart.
in
HOLLOW WALL SILOS.
If it is desired to make the silo with a hollow wall, the construction can
be made similar to the ice-box walls described on page 102. The inside section
of the wall of the silo is made the thickness required in the silo table, page 105,
and the other walls 3 inches thick with lighter reinforcement. Formerly it
was thought necessary to make all silos of hollow wall construction, but this
is now practically superseded by the solid wall built with dense wet mixed
concrete.
'
STORAGE WATER TANK AT BOODY, ILL.
TANKS.
Concrete tanks, if properly built, are superior in all respects to any other
kind of a tank for storing water or grain. They are easy to clean, and do not
rot or rust. The concrete mixture should be in proportions one part
"ATLAS" Portland Cement to one and one-half parts clean but rather fine
sand to three parts screened gravel or broken stone.
A tank in order to withstand water pressure and not leak is best built by
laying the concrete without stopping. Even then there are other essential
things which, if disregarded, will produce a leaky tank. The concrete must
be mixed so wet that it will flow over and around the metal reinforcement and
against the forms. The materials for the concrete must be very carefully
proportioned and the stones small enough to pass a 54-inch mesh screen. A
112
concrete made by using very clean screened gravel makes a denser concrete
than broken stone; it flows into place better and is not so apt to have voids
and stone pockets which let through the water.
SQUARE TANKS (Small). Square tanks do not stand water pressure so
well as round because the sides tend to bulge, but they are all right if not
more than 4 feet deep and 8 feet square. Build outside forms 12 inches wider,
WATER TANK, NEAR MORTON, ILL.
12 inches longer and 6 inches deeper than the inside of the finished tank. Set
mesh reinforcement, or else ^-inch rods running both ways and 6 inches apart,
in bottom of tank and the reinforcement given for a 5-foot round tank in the
sides. Allow the vertical rods to project down into the bottom and the bottom
rods to project up into the sides. Tie horizontal rods to vertical by i/i6-inch
soft wire. Place inner form 4 inches from the outside form. This form can
rest on iron pins driven into the ground. Grease forms thoroughly. Put
concrete into forms at one continuous operation so that there will be no joints
between courses, making it of the consistency of heavy cream. As the
concrete is placed in the bottom, lift the reinforcement a little to allow the
113
concrete to get in under it. When filling the wall take care to keep the
reinforcement in place. By working carefully, the inside form may be
removed as soon as the concrete has become dry on top, say, in two or three
hours, although a better way is to leave it for two or three days and knock
the form to pieces. Leave outside form in place for three or four days.
After the concrete has set and the forms are removed, paint inside of the tank
with pure cement mixed with water to the consistency of cream and brush in
WATER TANK AT MORTON, ILL.
well. This should prevent any leakage. Protect the tank from the sun till
ready to use and wet two or three times a day for a week after removing the
forms. Do not fill with water until tank is two weeks old.
ROUND TANKS. Follow exactly the same methods given for square tanks,
except using thicknesses and reinforcement given in the table. Lay out
circular forms as described on page 20 or page 106. Set the reinforcerhWnt in
place and pour the concrete in the same way as for square tanks.
114
WELL HOUSE WITH HEAVY CONCRETE COLUMNS FOR SUPPORTING STEEL FRAME OF HIGH
WATER TANK AT COLUMBIA, MO.
WATER TANK, SO. CHARLESTON, O.
"5
Tanks sometimes have to be constructed by filling one or two sections of
forms each day, letting it set over night and continuing the next day. This
is bad practice because it is readily seen that a joint is formed on the surface
of each layer of concrete which is placed on top of another layer that has set
up and hardened; to make the joint as tight as possible the top surface of the
old concrete must be specially treated. The operation for treating this
surface is as follows: Scrape off all dirt and scum from the old surface, pick
it with a pick or scrub it thoroughly with a wire brush or horse curry comb
in order to remove all surface mortar and scum and leave a very rough
WATER TANK AT BERRY HILL, L. I., N. Y.
surface. To make the bond between this cleaned surface and the new
concrete, wet it thoroughly, soaking it well, place a y^-inch to ^-inch layer
of one part "ATLAS" Portland Cement to one part sand, or, better still, a
layer of pure "ATLAS" Portland Cement on the cleaned surface, and before
this has set or has begun to stiffen place the new concrete upon it. In some
cases a positive bond between the old and new concrete work is used in
addition to the above by imbedding in the top of the last mass of concrete
laid each day a 4 by 4-inch piece or a V-shaped stick of timber. This timber,
which is removed the next morning, will form a groove to bond the new and
old concrete together.
116
If the tank is built above ground, remove sod and earth until good firm
material is reached. Excavate in any case at least 6 inches below the bottom
of the tank and build foundation 6 inches thick of screened gravel or cinders
or crushed stone, spreading in 4-inch layers and ramming hard. Be sure
that this foundation is drained so that the water cannot collect and freeze in it.
For inlets and outlets to tanks place pieces of pipe in the concrete while
it is being deposited.
Tanks may be roofed with either a wooden or concrete roof. For concrete
lay the concrete on a very flat slope and reinforce it as described in the table
for concrete beams and slabs on pages 30 and 31. A wooden roof is apt to be
cheaper and will answer most purposes.
REINFORCEMENT FOR TANKS.
The table which follows gives a list of sizes of steel required for tanks of
several different dimensions, allowing ample factor of safety. It is extremely
important that the horizontal steel be placed exactly as given. The entire
pressure of the water is assumed, according to the very best practice, to be
taken by the steel, as concrete is not reliable in tension unless reinforced.
The thickness of concrete is only required to imbed the steel and to make the
tank water-tight, and should vary with the height of the tank, but not neces-
sarily with the diameter. A minimum thickness of 4 inches for a 5-foot tank,
running up to 10 inches for a tank 15 feet deep, is suggested.
DATA FOR REINFORCED CONCRETE TANKS.
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
Depth
Diameter
Thickness
of
Diameter
Circumfer-
Spacing
Circumfer-
Spacing
Circumfer-
Diameter
Vertical
Spacing
Vertical
Concrete
ential Rods
ential Rods
ential Rods
Rods
Rods
at Bottom
at Top
Ft.
Ft.
Inches
Inches
Inches
Inches
Inches
Ft.
5 by 5
6
M
6
9
y
1H
5 " 10
6
5 /16
6
9
%
^A
10 " 10
8
y%
6
12
%
2H
10 " 15
8
y*
6
12
1 A
3
15 " 10
12
1 A
6
15
1 A
2K
15 " 15
12
%
6
15
%
3
NOTE. Bend circumferential rods in rings, place in center of wall and lap ends 2 feet. Increase, gradually,
spacing of circumferential rods from bottom to top.
GRAIN ELEVATORS.
Concrete grain elevators of immense size are being built all over the
country by the railroads. For the storage of grain on the farm or in a village,
grain elevators can be built like silos, and the descriptive matter and amount
of reinforcement under silos, pages 103 to 113, will apply. An elevator built in
this way is proof against rats and other vermin, and is water-tight.
117
CORN CRIBS.
The waste caused each year by rats and mice in corn cribs is enormous.
This loss can be prevented by constructing the entire corn crib of concrete, as
well as the floor, which makes it also fireproof.
The corn crib may be constructed with 5 x 5-inch concrete posts, spaced 4
feet on centers, and extending from the concrete foundation to the roof plate,
which may also be a beam of concrete tying the posts together and supporting
the wooden roof. On two of the opposite sides of the posts mold a slot i inch
deep by 2 inches wide its entire length. The sides of the crib may consist of
40 BY 60-FOOT STOREHOUSE AT LOWVILLE N. Y.. WITH CONCRETE PIERS
a series of slats or slabs. Cast or mold these separately 2 inches thick by 5
inches high by 3 feet 8 inches long, and reinforce with two ^-inch rods in the
same way that fence posts are molded. After thoroughly seasoning, place
the slats in the slots in the posts so that there is a %-inch opening between
them. To accomplish this place one slat, then throw some mortar in the
groove in the post on top of it. Place the next slat, and push it into the
mortar at the joint so that a ^2-inch space remains between the two slats.
Continue in this way up to the plate.
The mix of concrete should be one part "ATLAS" Portland Cement to
two parts clean, coarse sand to three parts fine screened gravel, or one part
"ATLAS" Portland Cement to four parts unscreened gravel or sand.
118
CISTERN.
Make a circular excavation 16 inches wider than the desired diameter of
the cistern, or allow for a wall two-thirds the thickness of a brick wall that
would be used for the same purpose, and from 14 feet to 16 feet deep. Make
a cylindrical inner form (see Circular Form) the outside diameter of which
shall be the diameter of the cistern. The form should be about 9 feet long
CONCRETE CISTERN AT ST. CHARLES, ILL.
for a 14-foot hole, and n feet long for one 16 feet deep. Saw the form length-
wise into equal parts for convenience in handling. Lower the sections into
the cistern and there unite them to form a circle (Fig. No. 36), blocking up at
intervals six inches above the bottom of excavation. (Withdraw blocking
after filling in spaces between with concrete and then fill holes left by blocking
with rich mortar.)
119
Make concrete of one part "ATLAS" Portland Cement, two parts clean,
coarse sand and four parts broken stone or gravel. Mix just soft enough to
pour. Fill in space between the form and the earth with concrete, and puddle
it to prevent the formation of stone pockets, using a long scantling for the
purpose and also a long-handled paddle for working between the concrete
and the form. To construct the dome without using an expensive form,
proceed as follows : Across top of the form build a floor, leaving a hole in the
center two feet square. Brace this floor well with wooden posts resting on
the bottom of the cistern. Around the edges of hole, and resting on the floor
Fig. 36. Concrete Cistern.
described, construct a vertical form extending up to the level of the ground.
Build a cone-shaped mold of very fine wet sand from the outer edge of
the flooring to the top of the form around the square hole and smooth with
wooden float. Place a layer of concrete four inches thick over the sand so
that the edge will rest on the side wall.
Let concrete set for a week, then remove one of the floor boards and let
the sand fall gradually to the bottom of the cistern. When all boards and
forms are removed they can be easily passed through the two-foot aperture
and the sand taken out of the cistern by means of a pail lowered with a rope.
This does away with all expensive forms and is perfectly feasible. The
120
bottom of the cistern should be built at the same time as the side walls and
should be of the same mixture, six inches thick.
SQUARE CISTERNS.
Excavate to desired depth and put in 6 inches concrete floor, one part
"ATLAS" Portland Cement, two parts sand and four parts broken stone.
As soon as practicable, put up forms for 8-inch walls (see Walls) and build
the four walls simultaneously. If more than 8 feet square, walls should be
reinforced with a woven wire fabric or steel rods.
CONCRETE CISTERN AT MONROE, N. J.
WELL CURBS.
Concrete makes the best well curb, as it keeps out the surface water and
is easily kept clean.
After the well has been dug to the desired depth, and the sides properly
braced in short sections so that the earth cannot cave in, build a circular form
8 inches smaller than the diameter of the hole, and 4 feet long. (See Circular
Forms.) Lower to the bottom in sections and adjust so that there are 4
inches between the form and the side of the hole. Place concrete mixture, one
part "ATLAS" Portland Cement, two and one-half parts clean, coarse sand
121
SPRING CURB AT MONROE, N. J.
CURB IN INTERIOR OF SPRING HOUSE AT LAKE MASCOMA, N. H.
122
and five parts broken stone or gravel, in this space. To allow the water to
get into the well, place a couple of pints of loose, broken stones in "pockets"
every few feet until the water level is reached. After filling the form to the
top and allowing it to set over night, or until the concrete will bear pressure
of the thumb, raise it 3 feet, brace securely and repeat until ground level is
reached. A slab 4 inches thick and 8 feet square should be built around the
top of the well, first replacing surface soil with a layer of cinders or clean
gravel, well rammed, about 12 inches thick.
SPRING CURB AT MONROE, N. J.
ICE HOUSES.
There has been considerable discussion as to whether or not concrete ice
houses are a success. After thorough investigation the conclusion has been
reached that there are none better, if properly built i. e., with a double wall.
Excavate a foot below the desired depth and put in a layer of coarse
gravel or broken stone, ramming hard. This makes a good floor
and leaves plenty of drainage. Set up forms in shape finished structure is
desired, allowing 16 inches for a wall, and build foundation one part
123
ICE HOUSE AT MONMOUTH, ILL.
ICE HOUSE AT BABYLON, L. I.
124
"ATLAS" Portland Cement, three parts clean, coarse sand and six parts
broken stone, 16 inches wide by 4 feet deep, or below frost. The wall should
be built as shown in Hollow Walls, making two 3-inch walls with a 6-inch
space, each reinforced with one-quarter-inch rods placed 12 inches apart in
both directions. Mixture: One part "ATLAS" Portland Cement, two parts
clean, coarse sand and four parts broken stone. The wall should be built in
sections about 2 feet high at a time, and the outer and inner walls should be
bound together by placing galvanized iron strips, one inch broad by one-sixth
15 BY 20-FOOT CONCRETE ICE HOUSE ATTACHED TO COW BARN AT LOWVILLE, N. Y.
inch, and turned up about an inch at each end between the first and second
section, after the first section of the inner form has been removed. These
strips will not only strengthen the wall, but will serve as a convenient footing
for the second tier of inner forms, etc. The ends and top should be filled
in solid to the depth of 6 inches, leaving no openings for the air to circulate.
The roof should be made slanting, and after the lower or inner side is
completed 5 inches of sand may be placed on top and leveled off. The upper
or outer surface of the roof can then be laid, with suitable reinforcement,
directly upon the sand, and carefully trowelled as soon as it is partly set. The
sand is let out at an opening left for the purpose at the sides when the concrete
has dried for a couple of weeks. There should be several square blocks of
125
concrete placed so as to connect the two, and a strong concrete beam should
form the ridgepole. All openings between the walls and roof and the two
layers of roof should be sealed up solid, so as to give a dead air space between
them. Shrinkage cracks are liable to form on large concrete roof surfaces
so that if a surface is over 20 feet square it should be covered with tar and
gravel or some other kind of roofing.
For a small house the dimensions of beams and slabs for roof may be
obtained from table of Reinforced Beams and Slabs, but for a large house
money will be saved and safety assured by consulting an engineer or architect
experienced in concrete design.
ROOT CELLAR AT KNOXVILLE, IOWA
ROOT CELLARS.
Root cellars are usually built half below and half above the level of the
ground. Excavate 16 inches below the desired level of the floor, and around
the sides build a foundation 12 inches broad, one part "ATLAS" Portland
Cement, three parts clean, coarse sand and six parts broken stone or gravel.
Remove the form and fill between the foundations to a depth of 12 inches
with porous material, tamping well. On this build a floor as described under
Cellar Floors, p. 86. On the foundation and at equal distance from either edge
126
ENTRANCE TO ROOT CELLAR, UNDER WAGON HOUSE, AT U. S. SOLDIERS* HOME,
WASHINGTON, D. C.
ROOT CELLAR, BABYLON, L. I.
127
erect a solid wall 8 inches thick (see Walls), one part "ATLAS" Portland
Cement, two and one-half parts clean, coarse sand and five parts cinders,
broken stone or gravel, leaving an opening at one end for the steps (see
Steps). Build up the end walls so as to form a point in the middle and
high enough to give the roof a sufficient pitch to shed the rain.
Near the top at each end, openings for windows should be left and sash
fitted and plastered in after the concrete has set and forms have been removed.
Bins should be built of size and height to suit convenience, with walls 4
inches thick and reinforced with one-quarter-inch rods placed 12 inches apart
horizontally and vertically.
ROOT CELLAR AT GLEN COVE, L. I.
If a concrete roof is desired, forms should be erected and a roof 3 inches
thick laid on. On the top of this, and before the concrete is dry, a layer
one-quarter inch thick of one part "ATLAS" Portland Cement and one part
sand should be placed, trowelled when partially set, and smoothed with a
wooden float. This surface must be wet three times a day for a week or two.
Forms should not be removed from roof for at least three weeks.
Should the roof be sufficiently long to require support other than the
concrete beam that forms the ridge pole (see section on Reinforced Concrete),
posts can be built in place 8 inches square.
128
Roof and steps should be reinforced with a woven wire fabric or with
steel rods.
MUSHROOM CELLARS.
Mushroom cellars should be built at least two-thirds below the level of the
ground to obtain the best results.
Excavate to the desired depth, and around the edge dig a trench 12 inches
deep and 16 inches broad. In this lay a foundation one part "ATLAS"
Portland Cement, three parts clean, coarse sand and six parts broken stone or
gravel. On the foundations and at equal distance from either edge build a
solid wall (See Walls) 8 inches thick; mixture, one part "ATLAS" Portland
Cement, two parts clean, coarse sand and four parts broken stone, gravel or
cinders.
INTERIOR OF MUSHROOM CELLAR AT WESTWOOD, N. J.
Build a concrete roof 3 inches thick, supported by concrete beams and
posts (see Table, Reinforced Concrete Beams and Slabs). An opening should
be left at one side for steps (see Steps). All walls, posts, beams and roof
should be reinforced. A coat of grout, one part "ATLAS" Portland Cement
to one part fine, clean sand mixed to the consistency of cream, may be applied
to the whole exterior with a brush if a very smooth surface is required.
129
ARCH DRIVEWAYS.
Every farm or house along a country road must have one or more bridges
or culverts where the driveways span the trench or ditch alongside the road.
These arches or small bridges should be constructed of concrete, for then they
will not continually rot out and need repairing and renewal.
An arch driveway consists of a slab supported on each side by a beam
which spans the ditch. The size of the beams, the thickness of the slab,
and the amount and spacing of the reinforcement in the beams and slab can
be taken directly from the table on page 30. For example, take an arch
ARCH DRIVEWAY NEAR COLD SPRINGS HARBOR, L. I.
driveway of 1 2-foot span, having an 8-foot roadway. The heaviest loading,
namely, 125 pounds per square foot, will be taken as given in the table.
Beams 9 inches wide and 16 inches deep, reinforced in the bottom with four
9- 1 6-inch rods, are required. The slab must be 3 inches thick, and be rein-
forced with 5- 1 6-inch rods placed every 6 inches.
The arch or slab should be constructed during a dry spell, in order that
little or no water need be taken care of in the ditch. The forms for the slab
may be made of wood if desired, or it can be constructed as follows: If the
130
ditch is not entirely dry, place a closed wood trough or a pipe in the bottom of
the ditch, to take care of the small amount of water. Throw the earth which
is excavated for the side walls into the ditch, and, if necessary, borrow sand
from the bank beyond to bring the pile of sand to a height level with the
bottom of the new arch or slab to be built and wet it thoroughly. Tamp this
fill and level off the top of the pile. Place some boards for the side walls, and
brace them. Place the necessary reinforcement, upon which lay the concrete,
composed of one part "ATLAS" Portland Cement, with two parts clean,
coarse sand and four parts screened gravel or stone. After the concrete has
set for a week or two, shovel out the earth from under the arch, and the drive-
way is ready for use.
SPILLWAY AT DUMONT, N. J.
CULVERT DRIVEWAYS.
Culvert driveways are used to span small, shallow runways of water.
The bore or opening through which the water passes is generally built
circular, although a square or rectangular opening may be used as well. Line
the bottom or invert of the opening with small cobble stones or gravel, from
which the sand has been screened. To make a circular bore or opening, get
two or three flour barrels or cement barrels, with the heads in, place them
end to end on the cobble or gravel base just laid, and brace them in position
so that they will not be moved when placing the concrete. If desired, a layer
of concrete can first be laid in the bottom of the ditch, on which the barrels can
be placed and braced. After placing the barrels and side forms in position,
lay the rest of the concrete, which should be composed of one part "ATLAS"
Portland Cement to two and one-half parts clean, coarse sand to five parts
gravel or broken stone. The walls should be about 10 inches thick and the
top of the arch 6 inches thick. To remove the forms, knock in the heads of
the barrels and pry out the staves.
WATER PIPES UNDER DRIVEWAYS. Concrete water pipes, which are
covered over with earth, furnish a very good means for taking care of water
underneath driveways. The pipes are constructed in the same manner as the
STUCCO CHICKEN HOUSE AT ALLENTOWN, PA.
concrete tile, described on page 91, and may be made up to 12 or 16 inches
in diameter.
HEN NESTING HOUSES.
Hen nesting houses constructed of concrete are better and if a number
are to be built are cheaper than if constructed of any other material. It is
impossible to keep vermin from any nesting house, and consequently the
132
nests must be cleaned artificially. The only sure way to clean a nest is by
the burning out process. This is impossible, of course, where the nests are
constructed of wood, and the only way therefore is to burn them every so
often and build new ones.
It is hardly necessary to state the advantages of a concrete nest, but a few
of them are: (i) that it is cool in summer and warm in winter; (2) no
- 37- Design for Hen Nesting House.
draughts are possible, hence the hen will not acquire roup; (3) they can be
burnt out after each nesting so as to destroy all germs, leaving the nest clean
and wholesome; (4) if discolored by the fire the nest can be whitewashed
after each firing.
133
A good size for a hen nesting house is 12 inches wide, 15 inches nigh and
i8 inches deep inside dimensions. The walls and back should be 2 inches
thick, while the front is left entirely open, although if desired a lip or ledge
can be cast on the front side. The ledge can be made out of wood and cut
so that it fits snugly in the concrete and this can be removed very easily when
cleaning the nests* The forms, as shown in Fig. 37, are very simple, and are
made so that a number of nests can be built with one set of forms. The
outside forms consist of a rectangular box without any ends and each side
made as a separate member so that they can be easily taken apart after the
concrete has hardened. When nailing the sides together do not drive the
nails home, but leave the heads so that they can be easily drawn with a claw
hammer, or, better still, drive the nail first into a short piece of lath which
can be easily split when the sides of the form are to be removed, and thus the
heads of the nails will stick out from the form ^4 inch and can be easily pulled
out. Nail the outside form together with the two bevel pieces for the top of
the nest tacked in and place on either hard level ground or a plank floor or
platform. Oil the forms well so that they can be easily removed. The inside
form is made as shown in the figure, having a hinge at the peak of the roof
and two hinges at the bottom in order to facilitate removing the form. It is
made in two separate sections which are held together by nailing on two cleats
to serve also to hold them in the outer form and at the right distance, namely,
2 inches from the ground or platform. After placing the forms, which should
be well greased, mix one part "ATLAS" Portland Cement with two and one-
half parts of clean, coarse sand with five parts of screened gravel or broken
stone. Place the layer of concrete in the bottom of the form for the solid
back of the nest and then fill in the concrete for the walls. To remove the
inside form take off the two top cleats, which allow the two slant boards to
swing together on the hinge at the top, and the two side boards swing in on
to the base boards, making it possible to remove them very readily.
Thirteen nests can be made from one barrel (4 bags) of cement, one-half
of a single load (20 cubic feet per single load) of sand and one load of
screened gravel or broken stone. Figuring cement at $2.00 a barrel, sand at
75 cents a cubic yard and gravel at $1.25 per cubic yard, the cost of the
material for the concrete for each nest will be about 25 cents.
CHICKEN HOUSE.
The protection afforded by a concrete chicken house against rats, weasels,
and other vermin, and the ease with which such a structure is kept clean,
should be sufficient reason to give it preference over every other kind.
Excavate a trench 10 inches wide, to a depth below frost, and fill with
concrete one part "ATLAS" Portland Cement, three parts clean, coarse sand
134
CHICKEN HOUSE AT WESTWOOD, N. J.
CHICKEN HOUSE AT MONTCLAIR, N. j.
'35
and six parts cinders. On this foundation, and at equal distance from either
edge, build a solid wall 5 inches thick (see Walls), one part "ATLAS"
Portland Cement, two and one-half parts clean, coarse sand and five parts
clean cinders or screened gravel. The roof may be made of wood or of
concrete. If the house is not more than 8 feet wide, a roof with slope in one
direction may be made of a 4-inch concrete slab reinforced with steel rods or
heavy wire mesh of size suggested in the table of Reinforced Beams and Slabs.
For a shorter span a less thickness may be adopted. A slope of six inches in
eight feet will give sufficient pitch for the water to run off if the surface is
well trowelled, as described under Sidewalks. If the width is more than 8
feet, concrete rafters may be placed and slabs upon them of dimensions to be
selected from the table of Reinforced Beams and Slabs.
CONCRETE CHICKEN HOUSE AT LAUREL GROVE, N. J.
Concrete shelves and water basins can be put in to suit convenience.
A coat of mortar one part "ATLAS" Portland Cement and one part fine
clean sand, mixed as thick as cream, may be applied with a brush to the
outside walls as soon as forms are removed, although with careful placing
of the concrete, the surface may be wet and rubbed down as soon as the wall
forms are removed and before the concrete has hardened, with a board or a
brick, to remove the board marks of the forms and leave a pleasing rough
surface.
The use of cinders is recommended in this construction, as the voids in the
cinders take up the moisture, which is otherwise liable to collect on the inside
of the wall in cold weather. The walls may be made with a hollow space, as
shown in Fig. 31 (p. 102).
136
GREENHOUSES.
A greenhouse built of concrete not only does not require constant repairs,
but saves fuel, as it retains heat and keeps out cold air.
Greenhouses should have a foundation 10 inches broad and 16 inches deep,
or below frost, composed of mixture one part "ATLAS" Portland Cement,
three parts clean, coarse sand and six parts broken stone. On this, and at
equal distance from either edge, erect a wall 7 inches thick, mixture one part
''ATLAS" Portland Cement, two parts clean, coarse sand and five parts
GREENHOUSE AT U. S. SOLDIERS' HOME, WASHINGTON, D. C.
cinders, to the height required for the walls. A ridgepole can be erected, 6
inches wide by 8 inches deep, of concrete, one part "ATLAS" Portland
Cement, two and one-half parts clean, coarse sand and five parts broken stone
or gravel not over three-quarters inch in size, reinforced with two steel bars
each one-half inch in diameter. If total width of house is not over 16 feet,
beams 2^2 inches by 5 inches, extending from ridgepole to side wall,
reinforced with a %-inch bar, will be sufficiently strong to support the
sashes.
Reinforced concrete posts 8 inches square should be placed at intervals
of 10 feet to support the ridgepole.
iS7
CONCRETE GREENHOUSE WITH CONCRETE SASH AT WESTWOOD, N. J.
INTERIOR VIEW OF GREENHOUSE AT WESTWOOD, N. J.
138
CONCRETE GREENHOUSE TABLES.
The tables or benches in greenhouses should be constructed of concrete in
order to save the grower the large expense and annoyance of renewing and re-
placing every few years the old decayed wooden benches. The tables can be
made either as one member, in which case the posts, bottom and sides are cast
in one continuous piece of concrete, or they can be made by constructing them
in parts. In order to facilitate the drainage of the water from the table, holes
INTERIOR VIEW OF GREENHOUSE AT GLEN COVE, L. I.
must be left at the bottom of the benches except when the bottom is cast in a
series of slabs, where the cracks between them will be sufficient.
Make the concrete tables which are cast in one piece 2^ inches Ihick and
of a mixture composed of one part "ATLAS" Portland Cement to two parts of
clean, coarse sand to four parts of cinders, reinforced with a woven wire
fabric or %-inch round rods spaced 7 inches apart. A design for a table and
forms for molding the separate members is shown in Fig. 38. The posts
I3Q
should be 5 inches square, spaced on 6-foot centers, and the table may be made
4 feet wide. If the slab is molded in sections, as shown in the drawing
(Fig. 38), the section should be made about 12 inches in width for convenience
in handling.
The forms if well planned and greased with oil should leave the concrete
surface smooth enough without plastering them, but if desired a coating %
6//7.
End of Form Removed
J in. Boards
Fig. 38. Design of a Separately Molded Greenhouse Table.
of an inch thick, of one part "ATLAS" Portland Cement to one part of clean,
fine sand, may be applied to them. This should be put on after the surface to
be covered has been picked with a stone axe or old hatchet and thoroughly wet.
140
GREENHOUSE AT WESTWOOD, N. J.
INTERIOR OF GREENHOUSE AT U S. SOLDIERS' HOME. WASHINGTON, D. C
141
CONCRETE GREENHOUSE TRAYS.
Greenhouses are so warm that the moisture is soon dried out from the air.
To supply the necessary amount of moisture, it is frequently advisable to
keep a number of trays filled with water about the greenhouse. The larger
the surface of these, the greater the evaporation, and hence the better pro-
ducers of moisture. These trays are most satisfactory if constructed of
concrete, because the concrete, unlike the wood ones, do not rot, and do not
shrink if allowed to become dry and consequently need little attention to see
that they are always filled. The concrete trays can be made very attractive,
and are more serviceable than if made of any other material.
Make the trays like the slabs for tables (see page 140), except form a lip all
around them to the required height. Brush a layer of pure "ATLAS" Cement,
mixed to the consistency of thin cream, over the inner surface two or three
hours after the concrete is poured to make them water-tight. Protect from
sun and keep wet until they are to be used.
Frequently larger tanks are preferred, which may be made 18 inches wide
by 1 8 inches deep, with 6-inch reinforced walls.
CONCRETE FLOWER BOXES.
CONCRETE FLOWER BOXES.
Concrete veranda boxes for flowers do not rot and therefore do not have
to be renewed every two or three years. They are attractive, too, not only on
the porch of any stone, stucco or cement house, but are ornamental to a
frame house.
143
The length of the concrete veranda box is generally determined by the
size of the space in which it is to be placed on the veranda. A good size is
5 feet long, 8 inches deep, and 10 or 12 inches wide. The outside forms
consist of a long rectangular box, which may have the two long sides tapered
if desired, so that the box will be 10 inches at the bottom and 12 inches at the
top. This will make the finished concrete box look more attractive than if
made with perfectly vertical sides. Use planed lumber in the forms and oil
them thoroughly on all the surfaces coming in contact with the concrete.
Line the outside form with poultry netting, folding it at the end or corners
so as to make a reasonably close fit to the walls of the mold. Place the inside
form, which consists of a bottomless frame having dimensions 3 inches smaller
each way than the outside one, so as to make the walls 1^2 inches thick. Set
CONCRETE FLOWER BOX AT PATERSON, N. J.
this inside form on little blocks of wood to keep the form raised i^ inches
from the bottom of the outside form. These wood pieces can be removed
when the concrete is hard, and will leave holes in the bottom of the box for
draining off the excess water.
Mix a batch of concrete composed of one part "ATLAS" Portland Cement
to three parts clean, gravelly sand which has been screened through a %-inch
mesh screen, that is, a screen having openings ^ inch square. Lay the
concrete, which should be of the consistency of mortar for laying brick.
Remove the inner form very carefully in an hour or two, but leave the outside
form at least until the next day. The outside surface generally need not be
finished off further than wetting it down thoroughly and rubbing it with a
wood float or brick, but if desired it may be finished off as described on page 27.
The box must not be moved for at least a week, for fear of cracking it. Wet
it occasionally during this time.
HOT-BED FRAMES.
Excavate a trench to a depth below frost and erect forms for a 4-inch wall.
Fill with concrete mixture one part "ATLAS" Portland Cement, three parts
clean, coarse sand and six parts broken stone or gravel, to level of the ground.
On top of these build forms for a 3-inch wall to height desired, and fill with
concrete of the same proportions. Remove the forms in two or three days
and keep the walls damp for a couple of weeks.
CONCRETE COLD FRAMES AT WESTCHESTER, N. Y,
WINDMILL FOUNDATIONS.
The great danger caused by the rotting of wooden windmill foundations
is obviated by the use of concrete.
Excavate four holes at the proper distance apart, 2^2 feet square and 5
feet deep; build forms for the sides and grease properly. Fill forms 2 feet
deep with concrete, one part "ATLAS" Portland Cement, three parts clean,
coarse sand, six parts broken stone or gravel, of a jelly-like consistency,
tamping well every six inches. To insure proper location of holding-down
bolts, construct template and
hang the bolts from it, as
shown in Fig. 39, and fill in
concrete around them until
flush with top of form, and
allow to set several days be-
fore using. This gives a sub-
stantial anchorage for a steel
tower.
In case a wooden tower is
to be used, run projecting
bolts up through the timber
sills and use large cast-iron
washers under the nuts. The
anchorage in this case should
project at least 6 inches above
the ground.
Fig. 39. Form for Windmill
Foundation.
WINDMILL FOUNDATION AT MONROE, N. J.
145
CONCRETE ROLLER.
A concrete roller may be made as a hand roller to be operated by one or
two men or as a horse roller, when it is, of course, larger and heavier. A
hand roller for two men suitable for rolling lawns should be made about 18
inches in diameter and 24 inches long. This size of roller weighs about 530
pounds or 265 pounds per foot of length. The roller shown below is of
the dimensions first given and has been used very satisfactorily for several
years.
CONCRETE ROLLER AT NEWTON, MASS.
A form for making a concrete roller is very easily and cheaply made, as
shown in Fig. 40. For a roller 18 inches in diameter and 24 inches long cut a
piece of sheet iron 24 inches by 25% inches. The edges must be cut even and
must be square. Make two sets of wood clamps like the circular forms shown
on page 21. The piece of sheet iron cut to the dimensions as given can now
be bent in a circle and nailed, if necessary, to the two wood clamps. Wire
the iron form or jacket with No. 16 wire to hold the form from opening at
the joint when the concrete is placed. Grease or oil the inside of the form
thoroughly so that it will not stick to the concrete. To make an opening
through the center of the roller for an axle or shaft, place a 3^ or %-inch iron
pipe in the center of the form. The axle can be cast in the roller itself if
desired instead of casting a % or %-inch pipe in the roller in which to place
the axle. The concrete should be made of one part "ATLAS" Portland
Cement to two parts of sand to four parts of stone or gravel. It will take a-
little less than one bag of cement for a roller of the above dimensions.
146
-IQ/n
/x J /n
-|/>7. /ron P/j
Fig. 40. Form for Concrete Roller.
147
The handle for a hand roller may be made of 54-inch by i-inch iron, bent
and welded together as shown in the figure. Where the roller is heavier, or
is to be operated by a horse, a heavier handle and different design of handle
can be easily made.
A small roller for rolling seeded ground or golf greens may be made by
pouring concrete into a piece of pipe which forms the outside surface.
DANCE PAVILION AT TWIN LAKE, HARRISTOWN, ILL.
DANCE PAVILION.
The photograph of the pavilion at Twin Lake, Harristown, 111., shows
what can be accomplished by a farmer and one farm hand who had never
before had any experience with concrete. There are 16 posts in the 30 by
4O-foot pavilion, each 8 inches by n inches, and the walls are 3 feet high and
4 inches thick. The lumber used for the forms was not cut up any more than
necessary and was all used for the roof. Thirty-five barrels of "ATLAS"
Portland Cement were required in the construction of the posts, walls and
floor. Sand and gravel found on the farm was used and the concrete was
proportioned one part "ATLAS" Portland Cement to seven parts of aggre-
gate. A 3-inch floor was laid, using the same mix of concrete, and was
surfaced with a %-inch coat of mortar, one part "ATLAS" Portland Cement
to one part of sand.
The time required to make, place and remove forms was two days each for
the two men. It took them 10 days to mix and lay the concrete for the
entire structure.
148
PIAZZA.
In building a concrete piazza the first care should be the supports. Unless
these are strong and have a foundation that will not be affected by frost, the
piazza is liable to prove a failure.
Erect two lines of 4-inch posts, 8-inch bases, 8 feet apart, extending below
frost. The outer line of posts should be slightly lower than the inner line,
which is next to the house to allow water to flow off the piazza. On top of
and connecting these in both directions, build concrete cross beams and
stringers 4 inches by 8 inches. Posts should be reinforced with a 3/8-inch
CONCRETE PORCH STEPS AND LATTICE AT WESTWOOD, N. J.
steel bar and beams with two 3/g-inch bars placed one inch above the bottom.
For a large piazza, refer to dimension of beams and reinforcement in Table
for "Designing Reinforced Concrete Beams and Slabs," pages 30 and 31.
After the concrete has set hard, erect forms and build a solid slab of
concrete over the entire framework, allowing it to project slightly over the
outer edge. This slab should be reinforced with a woven wire fabric or
expanded metal or with steel rods, using the size and spacing given for slabs
in the Beam and Slab Table just mentioned.
If preferred the forms for the beams and floor may be built at the same
time, and the concrete poured in one operation.
U9
A finished surface can be obtained by plastering the surface one-half inch
thick with mortar, one part "ATLAS" Portland Cement and one part clean,
coarse sand, before the concrete has set and trowelling it hard as the mortar
begins to stiffen.
LATTICE.
In building a lattice, the fact that thfre are two thicknesses of concrete,
i. e., the thickness of the panel or border an$ thi thickness f tne lattice itself,
should be borne in mind.
Build a form 8 inches higher arid 8 inches longer than the size the finished
lattice is to be, using 2-inch stuff. Along the top, bottom and at either end,
nail a 4-inch by 4-inch scantling, and on these nail a 2-inch by 8-inch plank
afocte
Efevafion of Lattice w/fh parf of Form removed.
Wank
Section B,&.
Fig. 41. Forms for Concrete Lattice.
(see Fig. 41). On the back of the form, at equal distances apart and equal
distances from the edge of the 2-inch by 8-inch plank, nail securely blocks of
wood of the shape of the holes desired. (See holes in lattice in accompanying
cut.) Lay the form thus made on the ground, face up, and block securely.
Fill with concrete one part "ATLAS" Portland Cement, two parts sand and
four parts fine broken stone or gravel to the level of small blocks for holes,
and pack concrete all around under the 2-inch by 8-inch plank to form panel ;
tamp hard, making sure there are no voids. Smooth off face of concrete
and let stand for a week, or until the concrete is thoroughly dry. If the
surface is not smooth enough a coating of grout, one part "ATLAS" Portland
Cement and one part fine, clean sand, mixed as thick as cream, may be applied
with a brush after first roughening surface and wetting it thoroughly. A
moderately dry concrete should be used in this form.
150
The lattice may be built in place by leaving off the 4-inch by 4-inch block
at the top of form and boarding up the open space in front of "hole-blocks"
with a i%-inch plank and pouring the concrete in from the top (Fig. 41). A
very wet concrete should be used if this plan is followed.
CHIMNEY CAPS.
Chimney caps of concrete are rapidly supplanting stone, brick or iron, as
they are not only cheaper and more durable, but protect the top of chimney
better.
Fig. 42. Forms for Chimney Cap.
CHIMNEY CAP AT CHESTNUT HILL, MASS.
Make a bottomless box the size of the re-
quired cap, and one or more small bottom-
less boxes to correspond to the flue or flues
of the chimney, and % inch higher, so that
the surface of the concrete can be sloped to
allow water to flow off, and set in place (Fig.
42). The thickness is usually about 4 inches,
but this can be varied to suit convenience.
Plaster the inside surface of the large mold
with z inch of stiff mortar and then imme-
diately fill form one-half full with one part "ATLAS" Portland Cement, three
parts clean, coarse sand and six parts broken stone, and put in reinforcing,
either woven wire, expanded metal or ^4-inch rods, complete, and tamp until
water puddles on top. When partly set, trowel smooth.
If it is desired to build the cap in place, the following plan should be
adhered to : Place small rods across the chimney between the flues. On these
build platform of tongue and grooved board planed on upper side and driven
snug together, but not nailed. On this platform place the forms previously
described and fill with reinforced concrete. After the concrete has set (at
least a week is needed) remove platform and rods by raising each side of
chimney cap alternately and knocking platform apart. Remove outer and
inner forms. Raise one end of slab, cover all accessible surface of top of
chimney with mortar, lower cap on bed thus formed and remove rods under
end. Repeat process at opposite end.
REMOVING DECAYED MATTER FROM TREE
BEFORE FILLING
TREE
TREE WITH CAVITY FILLED WITH
CONCRETE
SURGERY.
Tree surgery not only consists in cutting away all the decaying and
dead matter of the tree, but embraces also the pruning and chaining of limbs,
152
scraping, and filling of cavities. Through the skillful methods used by the
tree surgeon it is possible to give a new lease of life to trees which apparently
have reached their limit of existence. The cavities are caused by poor
pruning of limbs, the breaking off of branches and other injuries. While the
treatment of the cavities varies more or less in different cases, if the specifica-
tions given below are followed closely a good job should result.
The tree grows in girth by the deposit of a thin layer of new wood
between the wood and the bark. It is this new layer and others recently
formed which are known as the sapwood and form the active section of the
trunk and branches. The inner rings are gradually covered by the yearly
deposit of this new growth, and in turn the living sapwood becomes heart-
wood, which is dead, and serves merely as a strong framework for the living
parts of the tree. This is the reason why hollow trees may often be found in a
flourishing condition when the heartwood has entirely disappeared.
FILLING THE CAVITY. Cut out all the deceased and decaying part of
the tree without regard to the size of the wound which is made. This must
be cleaned out with the same thoroughness which a dentist uses when cleaning
the cavity of a tooth for a filling. If all of the decayed matter is not removed
the decay will continue as if the filling had not been placed. Disinfect the
freshly cut surfaces with a coat of creosote or crude petroleum oil. Heat some
coal tar and apply a thick coat to the disinfected surfaces. This coat of tar
applied thick serves as a plastic substance to prevent any cracks between the
cement and the wood from shrinkage.*
The cavity, if it is a large one, may be reinforced to better hold the
concrete in place with either some woven wire mesh reinforcement or with
small steel rods placed across from side to side of the cavity. Cut back the
bark for about 3/ o f an inch or so around the entire wound in order to prevent
bruising it while the work is in progress, and in order to get the cement
perfectly flush with the wood, which cannot be done when the bark is not
cut away.
For a large cavity some kind of a form must be used to prevent the
concrete from caving out when it is being placed. For this boards may be
fitted to the opening, leaving a space at the top to pour in the concrete; or
metal, like zinc or tin, may be thoroughly greased and tacked on. When it
is ready mix up a batch of concrete composed of one part "ATLAS" Portland
Cement, two parts of sand and four parts of screened gravel or stone made up
to a rather stiff consistency, about like jelly.
If the opening to the cavity is small, so that no form is required, trowel
the surface of the concrete lightly so as to leave it smooth. If the concrete
is too soft to make a good vertical surface or if the upper part of the cavity is
*Methods similar to these have been used by Mr. G. E. Stone, of the Massachusetts
Agricultural College, for a number of years.
not entirely filled, wait for two or three hours until the concrete has begun
to stiffen, ram it in again to completely fill the hole and then trowel the
surface, adding a little stiff concrete if necessary.
If forms are used, remove them as soon as possible, either in a few hours
or else the next day, and go over the surface so as to slightly roughen it and
remove the form marks.
The bark on a tree treated in this way will in time grow over the concrete
and in some cases not even leave a scar.
CONCRETE AQUARIUM.
Aquariums constructed of concrete can be made attractive and have been
found very serviceable. At the fisheries at Cold Springs Harbor, L. I.,
some of these concrete aquariums have been in service since 1904 and look
as good to-day as when first made.
Make the base or bottom of each tank 18 by 31 inches and the vertical sides
13 by 15 inches, by 2 inches thick. Make the sides with vertical grooves
THIRTY-FOOT DIAMETER CONCRETE FOUNTAIN AT UNION, PA.
(1:4 Mix, 6-inch Thick Walls, 10 inches Deep)
i% inches from the edge in order to set in the glass sides. Leave grooves in
the bottom also so that the glass sides can be puttied in and be made water-
tight at the joints.
CONCRETE BLOCKS.
During the past few years concrete blocks have been used extensively and
many patents have been granted the manufacturers of concrete block
i54
DETAIL OF CONCRETE PEBBLE-FINISHED RESIDENCE AT WESTWOOD, N. J.
STUCCO COTTAGE AT CEDARHURST, L. I.
1.55
machines for the various devices and methods employed. Buildings con-
structed with concrete blocks have proved satisfactory when the blocks have
been made with care and with proper materials.
STUCCO.
Stucco work is cement plastering, and, in one form or another, has been
in use for ages. It is durable, artistic and impervious to weather. For
veneering new buildings, or protecting old structures, and wherever the cost
of solid concrete is prohibitive, Portland Cement Stucco cannot be equaled.
Stucco work may be used to cover wood, brick, stone or any other building
material, provided special precautions are taken in preparing the surface
properly so that it will adhere and not crack or scale off. The work should
be done by an experienced plasterer.
As a rule two coats are used the first, a scratch coat composed of five
parts "ATLAS" Portland Cement, twelve parts clean, coarse sand and three
parts slaked lime putty and a small quantity of hair; the second, a finishing
coat composed of one part "ATLAS" Portland Cement, three or even five
parts clean, coarse sand and one part slaked lime paste. Should only one
coat be desired the finishing coat is used. Some masons prefer a mortar in
which no lime is used, but this requires more time to apply it.
To apply Stucco to brick or stone or concrete, clean the surface of the
wall thoroughly, using plenty of clean water so as to soak the wall. If
the surface is concrete roughen it by picking with a stone axe. Plaster with a
i*/2-inch coat and finish the surface with a wood float, or to make a rough
surface cover the float with burlap. Protect the stucco work from the sun
and keep it thoroughly wet for three or four days; the longer it is kept wet
the better.
In using Stucco on a frame structure, first cover surface with two thick-
nesses of roofing paper. Next put on furring strips about one foot apart, and
on these fasten wire lathing. (There are several kinds, any of which are
good.) Apply the scratch coat ^ inch thick and press it partly through the
openings in the lath, roughing the surface with a stick or trowel. Allow this
to set well and apply the finishing coat */2 inch to i inch thick. This coat can
be put on and smoothed with a wooden float, or it can be thrown on with a
trowel or large stiff-fibered brush, if a spatter-dash finish is desired. A
pebble-dash finish may be obtained with a final coat of one part "ATLAS"
Portland Cement, three parts coarse sand and pebbles not over *4 i ncn m
diameter, thrown on with a trowel.
COLORING FOR CONCRETE FINISH.
The use of colored concrete up to the present time has not been general,
and the effect of coloring ingredients upon the strength of concrete is not
definitely known.
156
METHOD OF APPLYING PEBBLE DASH FINISH
157
In his book on "Cement and Concrete,"* Mr. L. C. Sabin, an eminent
authority, states that the dry mineral colors mixed with the water in
proportions by weight of from two to ten per cent, of the cement give shades
approaching the color used, with no apparent effect on the early hardening
of the mortar.
Mr. Sabin also gives the following table, showing the result obtained
from a dry mortar (wet mortars give a darker shade) :
COLORED MORTARS
Colors Given to Portland Cement Mortars Containing 2 Parts River Sand to 1 Cement.
Dry
Material
Used
WEIGHT OF DRY COLORING MATTER TO 100 POUNDS OF
CEMENT
Cost of
Coloring
Matter per
Pound, Ct.
Yi Pound
1 Pound
2 Pounds
4 Pounds
Lamp Black
Light Slate
Light Gray
Blue Gray
Dark Blue
Slate
15
Prussian Blue
Light Green
Slate
Light Blue
Slate
Blue Slate
Bright Blue
Slate
50
Ultra Marine
Blue
Light Blue
Slate
Blue Slate
Bright Blue
Slate
20
Yellow Ochre
Light Green
Light Buff
3
Burnt Umber
Light Pinkish
Slate
Pinkish Slate
Dull Lavender
Pink
Chocolate
10
Venetian Red
Slate, Pink
Tinge
Bright Pink-
ish Slate
Light Dull
Pink
Dull Pink
2y 2
Chattanooga
Iron Ore
Light Pinkish
Slate
Dull Pink
Light Terra
Cotta
Dull Brick
Red
2
Red Iron Ore
Pinkish Slate
Dull Pink
Terra Cotta
Light Brick
Red
2y 2
*"Cement and Concrete," Louis Carlton Sabin; McGraw Publishing Company, N. Y.
BURNT BARN AT BROOKSIDE FARM SHOWING CONCRETE BUILDING IN REAR IN WHICH THE LEAD
TRAPS ON THE SINKS WERE NOT EVEN MELTED OFF
158
CULVERTS.*
Concrete culverts of all sizes and shapes are being constructed not only
where the roads have been fully developed, but also on a great many farm
roads. They are cheaper than wooden culverts considering that the wooden
ones rot out every few years. If desired, they can be made quite artistic.
Culverts vary greatly in size, from those which are nothing more than a
large sewer pipe to those which span a wide stream.
CULVERT AT HARRISTOWN, ILL.
The bore or opening through which the water passes may be made either
circular or rectangular. Culverts are generally built with a circular bore,
although the forms for these are more difficult to make than for the rectangu-
lar, so that frequently the latter are much cheaper.
A culvert should be built, if possible, during the dry season or when the
water is low. When of such size as to make it impracticable to build it
by having the water flow through the center in a trough or flume, then build
a dam above the culvert and convey the water around one side of the proposed
new structure while the work is in progress by means of a wooden trough or
a deep ditch.
*For further detail information see "Concrete in Highway Construction," published
by The "ATLAS" Portland Cement Co.
159
<0
- tort:
3=
/
i'ftocfis bent
,1 jf^jfek^j. f. ..{?.? a d
f/ff