Division of Agricultural Sciences 
 UNIVERSITY OF CALIFORNIA 
 
 COST AND EFFICIENCY IN HOUSE 
 PACKING WESTERN HEAD LETTUCE 
 
 R. V. Enochian, F. J. Smith, and L. L. Sammet 
 
 UNIVERSITY OF CALIFORNIA 
 DAVIS 
 
 DEC i % 19S7 
 
 LIBRARY 
 
 CALIFORNIA AGRICULTURAL EXPERIMENT STATION 
 GIANNINI FOUNDATION OF AGRICULTURAL ECONOMICS 
 
 Mimeographed Report No. 199 
 
 September 1957 
 
i 
 
 FOREWORD 
 
 This study reports on the costs and efficiency of house packing western 
 head lettuce. A previous report focused on the costs and efficiency of alter- 
 native methods of lettuce field-packing operations. 
 
 Prior to l Q f>2, most of the lettuce shipped from the Salinas district was 
 house packed. Since that time, due to adoption of the vacuum- cooling process, 
 there has been a rapid change-over to field packing. The shift to field pack- 
 ing has created considerable excess capacity in existing house-packing facili- 
 ties. The immediate problem confronting shippers is how most economically to 
 use these facilities. Since the investment in buildings and equipment has 
 already been made, the effect of this item on costs can be ignored in the im- 
 mediate situation, and a solution can be worked out in terms of direct costs 
 only. This study indicates that direct costs are higher in smaller than in 
 larger packing houses . If a large number of Salinas packing houses were used 
 to pack the 1956 volume of lettuce, none could have been effectively organized 
 except as low-capacity operations and with high costs. The 1956 volume of 
 house-packed lettuce could have been processed through a single packing plant 
 of either i±20- or 630-crate-per-hour capacity. Costs would have been consid- 
 erably lower in the larger plant. It is recognized that consolidation of the 
 house-packing operations of a number of shippers in a single plant would give 
 rise to many administrative problems, the cost of which would have to be weighed 
 against the possible savings from consolidation. 
 
 Eventually, existing plants and equipment will wear out and must be re- 
 placed. The problem of the most economical organization when investment costs 
 for replacement of plants and equipment are included is then of interest. Given 
 a level of demand for house-packed lettuce sufficiently high to permit full ex- 
 ploitation of economies of scale, this study shows that costs, including the 
 fixed costs of buildings and equipment, are lowest with a plant of 630-crate- 
 per-hour capacity. The greatest economies occur between the small- (210 crates 
 per hour) and medium- sized (i|20 crates per hour) plants. Sufficient data are 
 presented to permit computation of costs for any size plant betxreen the range 
 of 210- to 630-crate-per-hour capacity under specified operating conditions. 
 Thus, when and if the demand for house-packed lettuce eventually stabilizes, 
 the information contained in this report should prove useful in the design of 
 optimum-sized plants. 
 
This study was made cooperatively by the Giannini Foundation of Agricul- 
 tural Economics of the California Agricultural Experiment Station and the Agri- 
 cultural Marketing Service, U. S. Department of Agriculture, under authority of 
 the Research and Marketing Act of 19U6. The work was performed as a part of 
 Western Regional Research Project WM-lh relating to the marketing of western 
 head lettuce. 
 
iii 
 
 COSTS AND EFFICIENCY IN HOUSE PACKING WESTERN HEAD LETTUCE 
 
 TABLE OF CONTENTS 
 
 Page 
 
 FOREWORD i 
 
 INTRODUCTION 1 
 
 The Problem 1 
 
 The Physical Organization of the Industry 2 
 
 Method of Cost Estimation k 
 
 Major Cost Components , . 5 
 
 Simplifications in Analysis 5 
 
 PACKING PLANT OPERATIONS AND COSTS 7 
 
 Operations Performed 7 
 
 Factors Affecting Rate of Output and Costs 13 
 
 Crew and Equipment Requirements and Costs 
 
 in Relation to Plant Capacity 15 
 
 Size of Crew in Relation to Plant Capacity 15 
 
 Crew Costs in Relation to Plant Capacity 18 
 
 Equipment Requirements 18 
 
 Equipment Replacement Costs and Annual 
 
 Fixed Costs of Equipment 20 
 
 Variable Repair and Equipment Operating Costs 22 
 
 Costs of Packing Materials and Supplies. ........... 22 
 
 Building Requirements and Costs .... 22 
 
 Space Requirements 22 
 
 Building Replacement Costs and Annual Fixed 
 
 Costs for Buildings 27 
 
 HARVESTING AND HAULING OPERATIONS AND COSTS 30 
 
 Operations Performed 30 
 
 Factors Affecting Crew Requirements and Costs . 32 
 
"to «*.tp.H 
 
 fisxl 1 ! InunnA buss RlioO ^aams^eJ.qsfi sai. 
 . . . .' .BT^C'O 'IMA SKOlTAHHIO OHIJUAH 
 
iv 
 
 Crew and Equipment Requirements and Costs 
 
 in Relation to Output Per Day 33 
 
 Production Standards 33 
 
 Harvesting Crew and Equipment Requirements 35 
 
 Truck Driver and Hauling Equipment Requirements 38 
 
 Harvesting and Hauling Labor and Supervision 
 
 Costs Per Day 42 
 
 Equipment Costs 45 
 
 Operating Costs Per Day 45 
 
 Annual Fixed Costs of Equipment . 1+5 
 
 COMBINED PACKING HOUSE AND HARVESTING -HAULING COSTS 49 
 
 Total Variable Costs Per Day 49 
 
 Annual Fixed Costs , 49 
 
 Total Season Costs and Total Costs Per Packed Crate 52 
 
 IMPLICATION OF RESULTS TO THE PRESENT SITUATION IN THE 
 
 SALINAS DISTRICT 60 
 
 LIST OF TABLES 
 
 Table 
 
 1 Crew Organization, Wage Rates, Labor, and Supervision 
 Costs for Lettuce Packing Plant Operations as Related to 
 Capacity in Crates Per Hour, Salinas District, California, 
 
 1953-54 16 
 
 2 Equipment Requirements, Prices, and Installation Costs 
 for Three Different Capacities of Lettuce Packing Plants, 
 
 Salinas District, 1954 1 9 
 
 3 Replacement Costs and Annual Fixed Costs of Equipment for 
 Lettuce Packing Plants of Three Different Capacities, 
 
 Salinas District, 1954 21 
 
 4 Variable Equipment Repair and Operating Costs Per Day for 
 Lettuce Packing Plants of Three Different Capacities, 
 
 Salinas District, 1954 2 3 
 
 5 Costs of Materials and Supplies for Packing Lettuce, 
 
 Salinas District, California, 1954 24 
 
»H 
 
V 
 
 Table Page 
 
 6 Building Space Requirements for Lettuce Packing House 
 
 of Three Different Capacities, Salinas District, 195^ 26 
 
 7 Replacement Costs and Annual Fixed Costs of Buildings 
 for Lettuce Packing Plants of Three Different Capacities, 
 
 Salinas District, 195^ 28 
 
 8 Cutter Time Requirements in Harvesting Head Lettuce 
 Expressed in Man-Hours Per Basket and Production Stand- 
 ards in Baskets Per Man-Hour with Different Levels of 
 Harvest Density and Length of Harvest Strip, Salinas 
 
 District, 1953- 5^ 36 
 
 9 Lettuce Harvesting Crew Organization and Hours Worked 
 Per Day in Relation to Daily Output and Harvest Density, 
 
 Salinas District, California, 195^ 39 
 
 10 Number of Truck-Trailer Units and Drivers Required for 
 Harvesting an:? Hauling Lettuce in Relation to Distance 
 Traveled, Harvest Density, and Output Per Day, Salinas 
 District, California, 1953- 5^ ^3 
 
 11 Total Daily Lettuce Harvesting and Hauling Labor Costs 
 with Varying Daily Outputs, Harvest Densities, and Round- 
 Trip Distances from Field to Plant, Salinas District, 
 
 California, 1953-5^ ^ 
 
 12 Replacement Costs, Annual Fixed Charges, and Operating 
 Costs Per Hour for Each Equipment Item Used in Harvesting 
 
 and Hauling Lettuce, Salinas District, California, 1953-54. ... w 
 
 13 Total Daily Lettuce Harvesting and Hauling Equipment 
 Operating Costs with Varying Daily Outputs, Harvest 
 Density, and Round-Trip Distances from Field to Plant, 
 
 Salinas District, California, 1953-5^ ^7 
 
 Ik Annual Fixed Costs of Lettuce Harvesting Equipment with 
 Varying Daily Outputs, Harvest Densities, and Round-Trip 
 Distances from Field to Plant, Salinas District, California, 
 1953-5^ ^ 8 
 
 15 Total Variable Lettuce Harvesting- Hauling and Packing Plant 
 Costs Per Day as Related to Output Per Day, Round-Trip 
 Distance from Field to Plant, and Harvest Density, Salinas 
 
 District, California, 195^ 50 
 
 16 Annual Fixed Costs of Harvesting-Hauling and Packing Lettuce 
 as Related to Plant Output Per Day, Round-Trip Distance from 
 Field to Plant, and Harvest Density, Salinas District, Cali- 
 fornia, 195^ 53 
 
 17 Total Season Cost of Harvesting-Hauling and Packing Lettuce 
 as Related to Plant Output Per Day, Round-Trip Distance from 
 Field to Plant, and Harvest Density, Salinas District, Cali- 
 fornia, 195^ 55 
 
3fli JLflcJ 
 
 I 
 
^ 
 
 vi 
 
 Table Page 
 
 18 Total Costs Per Crate of Harvesting-Hauling and Packing 
 Head Lettuce as Related to Plant Output Per Day, Round- 
 Trip Distance from Field to Plant, and Harvest Density, 
 
 Salinas District, California, 195k 57 
 
 19 Monthly Distribution of Ice-Packed Shipments and Hours 
 Worked and Estimated Season Total and Per Crate Costs of 
 Packing House Labor and Direct Supervision in Plants of 
 420- and 630-Crate-Per-Hour Capacity, Salinas District, 
 California, 1956 6k 
 
 LIST OF FIGURES 
 
 Figure 
 
 1 Diagrammatic Layout of Typical "String" of Lettuce 
 
 Packing Houses . 3 
 
 2 Process-Flow Diagram for a Typical Lettuce Packing 
 
 House . 8 
 
 3 Floor Plan for a Typical Lettuce Packing House with 
 
 Ik Packing Stations 9 
 
 k Inside View of a Typical Lettuce Packing House Showing 
 
 the "Packing Line" 11 
 
 5 Crushed Ice Being Blown Into A Refrigerator Car Loaded 
 
 With House-Packed Head Lettuce 12 
 
 6 Relation Between Packout Per Basket and Rate of Output 
 Per Packer Hour in a Sample of Lettuce Packing Houses, 
 
 Salinas District, California, 1953-54 14 
 
 7 Exterior View of Typical Lettuce Packing House 25 
 
 8 Lettuce Harvesting Crew and Loader in Operation 31 
 
 9 The Effect of Harvest Density on Rate of Travel of 
 
 Harvest Crews, Salinas District, California, 1953- 5k 34 
 
 10 The Effect of Harvest Density and Length of Harvest 
 Strip on Output Per Man-Hour of Standardized Baskets 
 of Lettuce, 100 Cubic Feet in Volume, Salinas District, 
 
 1953-54 37 
 
 11 Highway Truck Travel Time in Relation to Round-Trip 
 Distance Between Field and Packing House, Salinas 
 
 District, California, 1953-54 kl 
 
r 
 
vii 
 
 Figure Page 
 
 12 Total Costs Per Crate of Harvesting, Hauling, and 
 Packing Head Lettuce as Related to Plant Output Per 
 Day, Round-Trip Distance from Field to Plant, and 
 
 Harvest Density, Salinas District, 1953- 5^ 59 
 
 13 Distribution of Monthly Carlot Shipments of Ice- 
 Packed lettuce, Salinas District, 1956 62 
 
COSTS AMD EFFICIENCY IN HOUSE PACKING WESTERN HEAD LETTUCE 
 
 by 
 
 R. V. Enochian, F. J. Smith, 2/ and L. L. Sammet^/ 
 
 INTRODUCTION 
 
 Prior to 1952, methods of harvesting and packing western head lettuce in 
 the Salinas district for interstate shipment were highly standardized. Lettuce 
 was harvested from widely scattered fields, hauled to centrally located packing 
 houses, trimmed, packed in wooden crates between layers of crushed ice, and 
 loaded into refrigerated railroad cars for shipment. In 1952 a significant 
 proportion of lettuce prepared for interstate shipment (20 per cent) was field 
 packed. This was a direct outgrowth of the application of the vacuum-cooling 
 principle to lettuce. This new cooling method eliminated the need for direct 
 icing, made it feasible to use a corrugated paper carton rather than the stand- 
 ard wooden crate, and to pack in the field rather than in a centralized packing 
 house. Since that time, the new method has been rapidly adopted, and in 1956 
 approximately 92 per cent of the shipments from the Salinas district were field 
 packed and vacuum cooled.— ^ 
 
 The Problem 
 
 The shift to field packing leaves the industry with considerable excess 
 capacity in its centralized packing facilities. The extent of this excess for 
 
 1/ Enochian, Robert V., Agricultural Economist, Agricultural Marketing Serv- 
 ice7 U. S. Department of Agriculture . 
 
 2/ Smith, Frank J., Cooperative Agent, California Agricultural Experiment 
 Station and Agricultural Marketing Service, U. S. Department of Agriculture. 
 
 3/ Sammet, L. L., Specialist in the Experiment Station, University of Cali- 
 fornia. 
 
 ]\/ Harvesting and packing costs for several different methods of field pack- 
 ing have been considered in an earlier report. Smith, Frank J., L. L. Sammet, 
 a:d R. V. Enochian, Costs and Efficiency in Field Packing Western Head Lettuce 
 (Berkeley: University of California, Division of Agricultural Sciences, Agri- 
 cultural Experiment Station, December, 1955), U6p. (Giannini Foundation Mimeo- 
 graphed Report No. 183.) Processed. 
 
2. 
 
 the Salinas district is indicated by comparison of the 1956 range in monthly- 
 shipments of 62 to 387 cars of ice-packed lettuce with the 1951 range in monthly- 
 shipments of approximately 1,500 to 6,000 cars. For the 1956 season, ice-packed 
 lettuce amounted to only 3»8 per cent of the total shipments. 
 
 Continuing demand from certain markets for ice-packed lettuce, as x-rell as 
 the need for field cleanup after field-packing crews have finished their har- 
 vest, make it reasonable to assume that a limited amount of lettuce will con- 
 tinue to be ice packed, perhaps with a level of volume similar to that of 1956. 
 This directs attention to the problem of how the reduced volume of ice-packed 
 lettuce can be handled most economically. In the present situation of exist- 
 ing plants with much excess capacity, plant investment costs can be ignored 
 as these are sunk costs — assuming no salvage value — and have no bearing on cost- 
 minimizing adjustments in operations with existing equipment. The problem can 
 be resolved in terms of minimizing only the direct costs of operation. Assum- 
 ing, however, a continuing demand for ice-packed lettuce, the present plants 
 and equipment will eventually wear out and require replacement. The problem 
 of most economical organization when investment costs for replacement of plants 
 and equipment are included then is of interest. 
 
 This study, therefore, considers both the immediate and long-term aspects 
 of the problem. Specifically, the costs of harvesting and hauling operations 
 with different conditions as to harvest density, length of haul, length of har- 
 vest strip, and size of operation are considered. Similarly, the costs of plant 
 operations and their relation to size of plant are studied and the combined costs 
 of field harvest, hauling, and packing are estimated. Finally, the cost rela- 
 tionships thus developed are considered in relation to the current level of ship- 
 ments in the Salinas-Wat sonville district. 
 
 The Physical Organization of the Industry 
 
 In the Salinas district individually operated lettuce packing houses usu- 
 ally are located in groups called "strings." A diagrammatic layout of such a 
 group is shown in Figure 1. Each of these strings has a central ice-making 
 plant and a crate-making facility. Ice and crates are delivered on order to 
 individual packing houses by conveyor systems. In most cases these strings 
 were developed by the ice companies which generally own the land, railroad 
 spurs, ice-making facilities, the packing houses, and some of the equipment 
 in the packing houses. 
 
J 
 
1 
 
 Figure 1. Diagrammatic Layout of Typical "String" of Lettuce Packing Houses. 
 
There are various arrangements for charging a firm using the packing facili- 
 ties in a string. Under some of these arrangements, the tenant of the packing 
 house pays a fixed monthly rental for all the facilities owned by the ice com- 
 pany and, in addition, pays the standard price for ice.i^ In other cases the 
 quantity of ice used by the firm determines the rental that will be charged, 
 while some firms pay no rent except insofar as the rent is included in the 
 standard price of the ice. Under still other arrangements, the packing house 
 and all of the equipment in it are owned by the packing firm, and ice is pur- 
 chased at the standard or a somewhat lower price from the ice company. 
 
 Trucks and trailers and other harvesting and hauling equipment are either 
 owned by the packing firms or rented from companies that specialize in this 
 service. Trucks used for hauling culls and trimmings away from the packing 
 house are either owned or rented, or the entire cull-hauling operation may be 
 done on a custom basis. 
 
 Method of Cost Estimation 
 
 Estimated costs, rather than average accounting costs, of a sample of firms 
 are presented in this report. The bases for these estimates are production 
 standards which are measures of the potential output rate of workers of average 
 skills working under relatively efficient operating conditions. For the most 
 part, production standards for harvesting operations were developed from time 
 and production studies, while standards for the packing house operations were 
 derived from daily accounting records of labor utilization and output.-^ 
 
 From these standards, details of which are given in later sections, esti- 
 mates of crew and equipment requirements for various levels of output were de- 
 veloped. Appropriate wage rates were applied to the number of workers in each 
 job category to obtain estimates of the direct labor costc per hour. 
 
 1/ In 19^3, the price per ton was f?U«00. 
 
 2/ Packing house employees were paid on a piece-rate basis, and the maximum 
 output rate per packer hour was determined by management as a quality-control 
 measure. Under these conditions, it was felt that time and production studies 
 would not be as fruitful as they are in the case of field operations where the 
 worker is allowed to find his own level of productivity,, 
 
Requirements for equipment and buildings were estimated from engineering 
 studies of space and equipment layouts for packing houses of different capaci- 
 ties. From these estimates, replacement costs were obtained by applying the 
 appropriate prices for equipment, construction materials, and construction 
 labor „ Price and wage data were obtained from equipment manufacturers and 
 building contractors. Annual fixed charges for depreciation, taxes, insurance, 
 interest on investment, and repairs were determined by applying appropriate 
 percentages to the estimated replacement costs. 
 
 The estimates of direct costs per hour of equipment operation (such as the 
 costs of gasoline, tires, power, water, and repairs) xrere obtained by applying 
 appropriate prices to estimates of physical quantities used per hour. 
 
 Major Cost Components 
 
 Three major cost components— harvesting, hauling, and packing plant opera- 
 tions — are considered in this report. For each of these components, costs are 
 further broken down into direct costs related to hours xiorked and volume of 
 output and fixed costs involving expenses that are not dependent on hours 
 worked or related to specific units of packout. The items included in each 
 category are: 
 
 Direct costs : These include all labor, materials, and supplies 
 used in the packing operations ; operating costs such as fuel, elec- 
 tricity, and vehicle tires j equipment repair expense related to hours 
 of use; and direct supervision. 
 
 Fixed costs : These include depreciation, interest, taxes, and 
 insurance on the investment in buildings and equipment as well as 
 vehicle license fees and other miscellaneous fixed expense associ- 
 ated with the ice-pack operations. 
 
 Simplifications in Analysis 
 
 A great many factors affect the costs of lettuce packing. Since to 
 include all of these specifically would unnecessarily complicate the analysis, 
 certain conditions are assumed. With reference to the organization of activi- 
 ties and allocation of costs within each packing string, for example, it is 
 assumed that each packing firm owns all of the harvesting and hauling equipment, 
 the packing house and loading docks, and all equipment used in the packing, 
 icing, loading, and cull-disposal operations. It is al^o assumed that 
 
bClS £5ojt*I' : . 
 
 ■ ■ 
 
 10 iJ 
 
 I 
 
6. 
 
 the ice company owns the ice-making facilities, the land on which the packing 
 house is built, parking space for motor vehicles, the railroad spurs, and the 
 conveyor system for delivering block ice to the packing house; the price 
 charged for ice includes the costs of these items. Package materials are esti- 
 mated so as to include the costs of assembly and delivery to the packing house. 
 
 Another simplification relates to hours of operation. While this varies 
 among different plants and operating seasons and with respect to time within a 
 given season, the general practice in the plants studied was to schedule opera- 
 tions so as not to exceed 8 hours per day and a UO-hour week in the plant opera- 
 tions. This pattern as to hours worked, therefore, is assumed in the analysis. 
 With the exception of a limited amount of overtime work in connection with re- 
 ceiving operations at the packing house, this permits the calculation of labor 
 costs on the basis only of straight-time wage rates. 
 
 In the plan of analysis, the packing house is recog^zed as the focal point 
 of the ice-packing operations so that when the rate of packing house output is 
 specified this becomes the controlling factor with respect to crew and equipment 
 requirements for both the house and field operations. As a matter of conven- 
 ience, the packing house output rates considered in the analysis are stated in 
 terms of volume packed per eight-hour day. With some storage capacity at the 
 packing house for unpacked lettuce, field and house operations do not need to 
 be perfectly synchronized. The beginning and ending time of the house and field 
 workday do not need to be the same nor do total field and house hours worked per 
 day. Field operations need only to be scheduled to have available a supply of 
 lettuce at the beginning of the house workday and to maintain an adequate level 
 of supply through the day. 
 
 While not directly linked to hours worked in the packing house, field hours 
 worked per day can conveniently vary only within certain limits. If too few 
 field hours are worked, with harvesting rate exceeding the house-packing rate, 
 difficulty might be experienced in recruiting labor for certain field jobs, and 
 an excessive proportion of time would be spent in mobilizing the field crews 
 for work. On the other hand, an excessively long field workday with the har- 
 vesting rate less than the house-packing rate would require an excessively 
 early start to provide the daily total volume required, or the field day would 
 have to extend beyond the end of the packing house workday with substantial 
 carry-over of unpacked lettuce to the next day. To avoid these difficulties, 
 the field work time in relation to an 8-hour packing house workday is assumed 
 to range from a minimum of 6 to a maximum of °§ hours per day. 
 
■ . • ■ • 1 • 
 
7. 
 
 An omission in the cost estimates is allowance for miscellaneous packing- 
 house supplies (for example, janitorial and office supplies) and general ex- 
 penses such as dues, donations, and administrative costs. Some of these have 
 been omitted because of difficulty in obtaining adequate estimates. This is 
 particularly true with respect to administrative expense. Relatively little 
 data were available, and separation of administrative expense for packing and 
 shipping operations for lettuce as compared with other commodities in multi- 
 product firms and from crop production activities of grower-shippers was not 
 possible. IJhile these items in total per year per firm amount to a substantial 
 sum, they are quite small on a per-package basis and are of such nature that 
 their omission does not impair the usefulness of the cost relationships devel- 
 oped in this study. 
 
 The above simplifications and the use of typical production and cost rates 
 at later points in the analysis are consistent with the objective of developing 
 estimates of costs that are representative of efficiently organized operations 
 using harvesting and packing methods and equipment of the types specified. 
 However, the cost estimates may not be appropriate for application to a particu- 
 lar situation in which operating conditions differ from those specified, in 
 which equipment purchases were made in different time periods, or in which dif- 
 ferent rates for wages, depreciation, taxes, insurance, and other costs are ap- 
 plicable. Basic data are presented, however, which would permit adaptation of 
 results to other more specialized situations. 
 
 The discussion immediately following concerns crew and equipment require- 
 ments and costs of the packing house operations as related to size of plant. 
 This is followed by an analysis of field harvesting and hauling costs and a 
 summary section in which combined costs of field and packing house costs are 
 presented. Finally, the cost relationships developed ar^ considered with re- 
 spect to economical organization of house-packing operations xd.th the current 
 volume level of ice-packed lettuce in the Salinas district, 
 
 PACKING PLANT OPERATIONS AND COSTS 
 
 Operations Performed 
 
 Over-all packing plant operations may be conveniently broken down into a 
 number of suboperations or stages which are connected by in-plant transportation 
 or storage links. Figure 2 is an illustration of such a breakdown. Figure 3 
 
8. 
 
 INCOMING LETTUCE 
 
 D Temporary 
 storage 
 
 Transportation 
 
 ICE 
 
 EMPTY BASKETS 
 
 ODD(; 
 
 EMPTY CRATE SUPPLY 
 
 PACKING 
 MATERIALS 
 
 Figure 2. Process-Flow Diagram for a Typical Lettuce Packing House. 
 
Conveyors 
 
 Packed crates 
 
 Crushed ice 
 
 Empty crates 
 
 O 
 
 ^-Car spots 45' apart-- 
 
 T_ ~J 
 
 y<T L.Q o.d_in g _j oc kj _ 
 
 Misc. | >■ — "— ' — - — — — — 'At'is-sa? — - 
 
 Sl0r ° qe | , Lidded V////////A Packing ^////////////////////////% ^ZA 
 
 Shed 7\ 
 foreman s j 
 office - — * 
 
 Baskets 
 
 Receive and 
 grind ice 
 
 Crate 
 lining 
 plat- 
 form 
 
 Full and empty basket storage 
 
 Doorway 
 
 Rest rooms 
 
 Misc. 
 storage 
 
 '••"*-Empty crate 
 supply 
 
 Cull 
 pit 
 
 Cull 
 
 elevator 
 
 Cull | 
 hopper 
 
 227' 
 
 Figure 3. Floor Plan for a Typical Lettuce Packing House with llj Packing Stations. 
 
10 0 
 
 shows the floor plan for a typical lettuce packing plant in which the areas 
 where specific operations are performed are designated. 
 
 Operations begin with the receipt of lettuce from the field. The receiver 
 records the quantity in each lot and the field from which it came. A group of 
 workers, the floor help , roll the baskets off the field truck to temporary stor- 
 age and reload the truck with empty baskets. T rimmers , located at packing sta- 
 tions along the packing line (illustrated in Figure k) } are supplied with full 
 baskets from temporary storage by the floormen.^/ To make the lettuce access- 
 ible, each packing station has an independently operated lift for tilting the 
 baskets. Air pressure for the lift is supplied from a central compressor. 
 Trimmers remove outer leaves, divert undersized and soft or damaged heads to a 
 cull sluice in which a constant stream of water is running. Trimmed heads are 
 placed on a ribbed packing table which runs the full length of the packing line. 
 Packers , equipped with two metal packing stands, sort the lettuce by size and 
 place the heads in xjooden crates lined with *ja::ed paper. Each crate contains 
 either 1*8 or 60 heads depending on size. Half crates containing 2k or 30 heads 
 are sometimes packed. A chemically treated pad and a shovelfull of ice are 
 placed between the first two layers. Packed crates are marked with the packer's 
 number and placed on a power conveyor to the padman , who places a chemically 
 treated pad over the top layer. He pushes the crate along a roller conveyor to 
 the top iceman, who places a shovelfull of ice on top of the pad. The paper 
 folder , when used, folds the paper liner over the pack. In small plants, this 
 job is done by the lidder , who then positions the crate in a semiautomatic lid- 
 ding machine. After lidding, a checker records the packer number and lot, and 
 the crates move to the labeler. Labels, lids, and pads are supplied out of 
 storage by a miscellaneous xjorker . After labeling, the crates continue on a 
 power conveyor to a refrigerator car where car loaders stack and brace the 
 crates. Loaded cars are then "blown" with crushed ice by a car top iceman 
 (see Figure 5). 
 
 1/ A variation in the receiving and trimmer supply operations, not consid- 
 ered" in this report, involves the use of inclined conveyors (commonly called 
 "drapers") at each packing station. These extend at right angles to the pack- 
 ing line. The section of conveyor at each station is individually controlled. 
 Field trailers with tiltable beds are pulled along right angles to these con- 
 veyors depositing lettuce on them. The lettuce is then conveyed upward to the 
 trimmers, who perform the operations described. 
 
Fifs^ire U. Inside View of a Typical Lettuce 
 Packing House Showing the 
 "Packing Line" 
 
Figure 5. Crushed Ice Beinp Blown Into A 
 Refrigerator Car Loaded With House- 
 Packed Head Lettuce 
 
15 
 
 trimmers to the packers. On the other hand, when much poor-quality lettuce is 
 thrown cut with little time spent on trimming, the rate flow of lettuce to 
 the packers is not necessarily reduced even though packout per basket is less. 
 While the percentage of packout or, conversely, the percentage culls may have 
 an important effect on the rate of output, this effect was not separated from 
 the effects of other factors. The limiting output rate of 30 crates per packer 
 hour used by most packing houses in the Salinas district during the 1953 season 
 is the basic rate used in determining crew and equipment requirements in the 
 following section. 
 
 Crew and Equipment Requirements and Costs 
 in Relation to Pl ant Capacity 
 
 Size of Crew in Relation to Plant Capacit y 
 
 A survey of lettuce packing plants in Salinas revealed that the potential 
 capacity of most of them, determined by the number of crates packed per plant 
 hour, was nearly the same. Since one of the objectives of this study is to 
 determine the relationship between capacity of operation and cost — commonly 
 called determination of economies or diseconomies of scale — crew organizations 
 as well as building and equipment requirements for different plant capacities 
 had to be synthesized from record data and observations of plant operations. 
 
 The packer is the focal point of the crew organization of lettuce packing 
 p7.ant operations. Union agreement and long industry experience determine the 
 ratio of the number of workers in each job category to the number of packers. 
 Given the rate of packer output per hour (30 crates in this study) and a target 
 rate of output per plant hour, the over-all crew organization is determined by 
 the number of packers required. 
 
 Plants with capacities of 210, U20, and 630 crates per hour were selected 
 for analysis in this study. The l±20-crate plant was the size typically observed 
 in Salinas. While no plants observed were designed to be operated at 210-crate- 
 per-hour capacity, this size was chosen to see if there were significant dis- 
 economies in small-scale operations. 
 
 On the basis of the above plant output rates and the rate of packer output 
 of 30 crates, the crew organizations shown in Table 1 were developed. The ratio 
 of some workers—for example, the trir.imers to packers— does not vary with ca- 
 pacity of operation. For other workers— for example, the floormen— the ratio 
 decreases with larger operations. For still other workers — for example, the 
 
■ ! 
 
TABLE 1 
 
 Crew Organization, Wage Rates, Labor, and Supervision Costs for Lettuce Packing Plant Operations 
 as Related to Capacity in Crates Per Hour, Salinas District, California, 1953-55 
 
 
 Crew organization and extra 
 
 
 
 
 
 
 
 
 
 
 
 
 
 time per plant hour 
 
 
 
 Wage rate per crate or 
 
 
 Total labor and 
 
 
 Number 
 
 Extra 
 
 Number 
 
 Extra 
 
 Number 
 
 Extra 
 
 
 per 
 
 hour in dollars?/ 
 
 
 supervision costs 
 
 
 of wor- 
 
 time, 
 
 of wor- 
 
 time, 
 
 of wor- 
 
 time, 
 
 Per 
 
 Per 
 
 Per 
 
 Per 
 
 | Per 
 
 Per 
 
 per plant hour 
 
 
 kers 
 
 hours 
 
 kers 
 
 hours 
 
 kers 
 
 hours 
 
 crate 
 
 hour 
 
 crate 
 
 hour 
 
 i crate 
 
 hour 
 
 in dollars 
 
 
 
 
 
 
 
 
 Plant size (crates per 
 
 hour) 
 
 
 
 
 
 
 Item 
 
 210 
 
 520 
 
 630 
 
 210 
 
 520 
 
 630 
 
 210 
 
 520 
 
 630 
 
 Crew required 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 Receiver 
 
 1 
 
 .500 
 
 1 
 
 .500 
 
 1 
 
 .500 
 
 .07500 
 
 1.500 
 
 .07500 
 
 1.500 
 
 .07500 
 
 1.500 
 
 3.00 
 
 3.00 
 
 3.00 
 
 Floor help 
 
 3 
 
 .500 
 
 5 
 
 .875 
 
 7 
 
 1.250 
 
 .O6875 
 
 1.375 
 
 .06875 
 
 1.375 
 
 .O6875 
 
 1.375 
 
 6.88 
 
 11.51 
 
 16.16 
 
 Trimmers 
 
 28 
 
 
 56 
 
 
 85 
 
 
 .06625 
 
 
 .06625 
 
 
 .06625 
 
 
 55.65 
 
 111.30 
 
 166.95 
 
 Packers 
 
 7 
 
 
 15 
 
 
 21 
 
 
 .08125 
 
 
 .08125 
 
 
 .08125 
 
 
 17.06 
 
 35.12 
 
 51.19 
 
 P adman]?/ . 
 
 1 
 
 
 l 
 
 
 1 
 
 
 .06625 
 
 
 .08125 
 
 
 .09875 
 
 
 1.99 
 
 2.55 
 
 2.96 
 
 Crate top icer£' 
 
 1 
 
 
 l 
 
 
 2 
 
 
 .07250 
 
 
 .10250 
 
 
 .08500 
 
 
 2.18 
 
 3.08 
 
 5.10 
 
 Paper folder 0 / 
 
 
 
 1 
 
 
 2 
 
 
 
 
 .09875 
 
 
 .08125 
 
 
 
 2.96 
 
 5.88 
 
 Lidder . 
 
 1 
 
 
 1 
 
 
 1 
 
 
 .01350 
 
 
 .01010 
 
 
 .01010 
 
 
 2.81 
 
 5.25 
 
 6.36 
 
 Checker^/ 
 
 *i 
 
 
 1 
 
 
 1 
 
 
 .06625 
 
 
 .08125 
 
 
 .09875 
 
 
 1.99 
 
 2.55 
 
 2.96 
 
 Labeler 0 / 
 
 1 
 
 
 1 
 
 
 1 
 
 
 .06875 
 
 
 .09875 
 
 
 .13375 
 
 
 2.06 
 
 2.96 
 
 5.01 
 
 Miscellaneous 
 
 1 
 
 .250 
 
 1 
 
 .250 
 
 2 
 
 .250 
 
 .06625 
 
 1.325 
 
 .06625 
 
 1.325 
 
 .06625 
 
 1.325 
 
 2.32 
 
 2.32 
 
 5.31 
 
 Carloader 
 
 1 
 
 
 2 
 
 
 2 
 
 
 .OI92.O 
 
 
 .01920 
 
 
 .01920 
 
 
 5.03 
 
 8.06 
 
 12.10 
 
 Car top icer 
 
 1 
 
 .250 
 
 1 
 
 .250 
 
 1 
 
 .250 
 
 .06875 
 
 1.375 
 
 .08375 
 
 1.375 
 
 .10125 
 
 1.375 
 
 2.50 
 
 2.85 
 
 3.38 
 
 Ice crusher]?/ 
 
 1 
 
 .250 
 
 1 
 
 .250 
 
 2 
 
 .250 
 
 .07875 
 
 1.575 
 
 .09375 
 
 1.575 
 
 .08506 
 
 1-575 
 
 2.75 
 
 3.20 
 
 5.59 
 
 Crate liner 0 ' 
 
 1 
 
 
 2 
 
 
 2 
 
 
 .07500 
 
 
 .07500 
 
 
 .08750 
 
 
 2.25 
 
 5.50 
 
 5.25 
 
 Cull truck driver 
 
 1 
 
 
 2 
 
 
 3 
 
 
 
 1.650 
 
 
 1.650 
 
 
 1.650 
 
 1.65 
 
 3.30 
 
 5.95 
 
 Packer bcssj*/ . 
 
 
 
 1 
 
 
 1 
 
 
 
 2.500 
 
 
 2.500 
 
 
 2.500 
 
 
 2.50 
 
 2.50 
 
 Shed foreman^/ 
 
 1 
 
 
 1 
 
 
 1 
 
 
 
 3.125 
 
 
 3.125 
 
 
 3.125 
 
 3.12 
 
 3.12 
 
 3.12 
 
 Crew costs per hour 
 
 
 
 
 
 
 
 
 
 
 
 
 
 112.15 
 
 207.90 
 
 305.67 
 
 Net 
 
 
 
 
 
 
 
 
 
 
 
 
 
 Plus 5 per cent 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 218.30 
 
 
 for payroll taxes 
 
 
 
 
 
 
 
 
 
 
 
 
 
 117.75 
 
 319.90 
 
 Total cost per 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 1,756.50 
 
 
 eight-hour day 
 
 
 
 
 
 
 
 
 
 
 
 
 
 952.00 
 
 2,559.20 
 
 (Continued on next page.) 
 
I 
 
 I 3J. 
 
 ■ 
 
 i ess, rot rc^i.* 
 
 1 fc& ?c*i£* 
 
 ■ • . ■■ . • • . ■ c 
 
 t> v. r r 
 
Table 1 continued. 
 
 a/ Piece rates for trimmers, packers, lidders, and carloaders are on a straight per-crate basis. Hourly costs for these 
 jobs are obtained by multiplying the appropriate piece rate by the number of crates packed per plant hour Other piece 
 rate job categora.es are paid on the basis of an average packer rate of output per hour (in this study 30 crates) For 
 these jobs hourly costs are computed by multiplying the appropriate piece rate by 30 and then multiplying this product 
 by the number of workers in the particular category. The cost of extra time, obtained by multiplying extra time worked 
 by the hourly rate, is added to the costs of particular job categories where applicable. 
 
 b/ For each packer over 8, | cent per crate is added to the average packer rate. When there are 2 employees, the \ cent 
 shall be paid for each packer over 16 and divided between the 2 employees. 4 
 
 c/ For each packer over 8, | cent per crate is added to the average packer rate. When there are 2 employees, the * cent 
 shall be paid for each packer over 16 and divided between the 2 employees. 
 
 d/ The packer boss received $100 per week and the foreman $125. The hourly rate is based on a to-hour week. 
 
18, 
 
 crate lidder or the receiver— the number remains the same regardless of the 
 size of operation. 
 
 Crew Costs in Relation to Plant Capacity 
 
 Nearly all workers in the packing houses studied were paid a piece rate 
 based on the packout rate with a minimum hourly guarantee. 
 
 Crew costs per hour for crews of different sizes x*ere determined by apply- 
 ing appropriate piece rates to the output rates for each worker. These rates 
 and the costs per crew hour for each job category with ti .. ee different crew 
 sizes are given in Table l.i/ 
 
 Because of the nature of packing house operations, some of the workers in 
 certain job categories report for work earlier or leave later than the remainder 
 of the crew. These include the receiver, some of the floor help, the iceman, 
 the ice blower, and a miscellaneous category. The receiver and floor help gen- 
 erally commence work about two hours before the packing house crew. The ice 
 crusher reports early to receive block ice from the central ice plant and to 
 prepare a supply of crushed ice for the packing crew. A miscellaneous worker 
 reports early to have ready for other workers a supply of pads, lids, labels, 
 paper crate liners, etc., which he keeps supplied throughout the day's opera- 
 tion. The car top iceman leaves later than the remainder of the crew because 
 he must ice the last car of lettuce packed. The extra hours required per day 
 for these jobs with different crew sizes x^ere determined from plant record data. 
 These requirements were converted to man-hours per crew hour for different crew 
 sizes and are given in Table 1, Pay for these extra hours is on an hourly basis. 
 
 Total labor costs per crew hour for each size plant T^ere obtained by add- 
 ing the costs for each job category, and these hourly totals were extended to 
 an eight-hour day. For 210-, U20-, and 630-crate plants, daily costs are $9l}2, 
 $1,71+6, and $2,559, respectively. 
 
 Equipment Requirements 
 
 Equipment requirements for the three sizes of plants are presented in 
 Table 2, The packing line, shown in Figure U, is the focal point of the entire 
 
 1/ The wage rates given in Table 1 were taken from the 1953 Packing House 
 Agreement between the Grower-Shipper • s Vegetable Association of Central Cali- 
 fornia and the United Fresh Fruit and Vegetable Workers' Local Industrial 
 Union No, 78 (CIO). 
 
♦mutfsvnw to ©f.ta" 
 
 o&si aoaiq ftfceq s'sau fcofcifctfa soejBOfi gftiJcAr arid a*>: •«/'£&•.• r Xs rXiosi' 
 <r<j£ ^ 'Jborjfrratel^ ei?»y eosia inatalUfc io rt-ra-io sot wofi *zeq atfaoo wt90 • 
 
 - ■ / 
 
 .... .. fjjta t ' ■ . • ■ . ■ •:• . .. 
 
 , ' , • . . ■ '. 1 : :. 
 
 %m xoq h&'slir^t rj;?ri stixB exIT *fHB#3*q a&i^dal 'to igd #eil *xid aoi -tern art 
 ■ . . • ... . .• •} -r; ■ >■ i; i -j "(c : 
 
 .stoo M»<?yx nu&g too** 1 * fiafii«t9d*ai> ©Ttgw aeais ws*s> dfmaYLL*:. tf.fJbHr stfofc' ^©rtf wx 
 
 s" • .'r't'i 
 
TABLE 2 
 
 19. 
 
 Equipment Requirements, Prices, and Installation Costs for Three Different 
 Capacities of Lettuce Packing Plants, Salinas District, 1954 
 
 
 
 
 
 
 Number of 
 
 units required as 
 
 
 
 Delivered 
 
 
 
 related to plant capacity 
 
 Cost component and equipment 
 
 Unit of 
 
 price per 
 
 Installa- 
 
 Installed 
 
 Capacity in crates per hour 
 
 specification 
 
 measure 
 
 unit 
 
 tion cost 
 
 price 
 
 210 
 
 420 
 
 63O 
 
 
 
 dollars 
 
 
 
 
 Trimming and packing 
 
 
 
 
 
 
 
 
 Baskets 
 
 each 
 
 121 
 
 — 
 
 121 
 
 100 
 
 200 
 
 300 
 
 Air compressor and receiver: 
 
 
 
 
 
 
 
 5 h.p. motor, 80-gallon tank 
 
 each 
 
 625 
 
 12 
 
 637 
 
 - 1 , 
 
 
 
 10 h.p. motor, 120-gallon tank 
 
 each 
 
 1,429 
 
 12 
 
 1,441 
 
 
 1 
 
 
 15 h.p. motor, 120-gallon tank 
 
 each 
 
 1,505 
 
 12 
 
 
 
 
 1 
 
 Air hoists and cradles for dumping baskets 
 
 each 
 
 379 
 
 18 
 
 397 
 
 7 
 
 14 
 
 21 
 
 Air feed line and I beam for hanging hoists 
 
 100 feet 
 
 335 
 
 293 
 
 620 
 
 .7^ 
 
 1.48 
 
 2.22 
 
 Packing table 
 
 100 feet 
 
 1,213 
 
 -1 On 
 
 loO 
 
 1,393 
 
 •7^ 
 
 1.48 
 
 2.22 
 
 Packing stand and humps 
 
 each 
 
 16 
 
 
 16 
 
 14 
 
 28 
 
 42 
 
 OU-LJ. QlSpOGEU. 
 
 
 
 
 
 
 
 
 tJKuuy 11 w ± LfLi n , p . inu uur 
 
 each 
 
 1,242 
 
 72 
 
 1.31* , 
 
 1 
 
 1 
 
 1 
 
 Oill 1 G> "1 Avatar tj -f *- Vi C V| ~r\ tti r\ *- t- 
 
 viiii cievabur vi tn 7 n .p • mo lot 
 
 each 
 
 2,273 I 
 
 450 
 
 4,7505/ 
 
 1 
 
 1 
 
 1 
 
 Cull hopper, complete 
 
 each 
 
 2,027 J 
 
 
 
 1 
 
 1 
 
 1 
 
 Pull tmrk 
 
 each 
 
 5,000 
 
 
 5,000 
 
 1 
 
 2 
 
 3 
 
 Loaded crate conveyor 
 
 
 
 
 
 
 
 
 Head section, with legs, spans 10 feet 
 
 each 
 
 207 
 
 
 
 
 2 
 
 2 
 
 2 
 
 Tall section, vlth legs, spans 10 feet 
 
 each 
 
 191 
 
 
 
 1,7865' 
 
 2 
 
 2 
 
 2 
 
 j u « p . i . p . m ■ mu bur 
 
 each 
 
 316 
 
 
 288 
 
 2 
 
 1 
 
 — 
 
 5 h.p. 1^5 r.p.m. motor 
 
 each 
 
 387 
 
 
 
 
 — 
 
 1 
 
 2 
 
 Sprockets, drive chain, etc* 
 
 set 
 
 35 
 
 
 
 
 2 
 
 2 
 
 2 
 
 Center section, complete 
 
 iw reel 
 
 1,180 . 
 
 
 70 
 
 1 250 
 
 1.70 
 
 3.35 
 
 5.00 
 
 Legs for center section, pair every 10 feet 
 
 pair 
 
 7 
 
 
 •7 
 1 
 
 18 
 
 35 
 
 41 
 
 Roller conveyor, rust proof, 10— foot section 
 
 each 
 
 641 
 
 144 
 
 ±1 
 
 X 
 
 X 
 
 1 
 X 
 
 Curve, right angle, 5-foot section 
 
 each 
 
 62 r 
 
 
 1 
 
 1 
 
 1 
 
 
 
 
 
 
 
 
 
 Turn off, 1 per car spot 
 
 each 
 
 8 
 
 -- 
 
 8 
 
 4 
 
 6 
 
 
 Roller conveyor, 16 -inch on 6 -inch center, 
 
 
 
 
 
 
 
 
 10 -foot section, 1 per 2 car spots 
 
 each 
 
 38 
 
 — 
 
 38 
 
 2 
 
 3 
 
 ■ "4 '-' 
 
 Accordion conveyors, 1 per 2 car spots 
 
 each 
 
 121 
 
 -- 
 
 121 
 
 2 
 
 3 
 
 4 
 
 Slide back skids, 1 per 2 car spots 
 
 each 
 
 39 
 
 — 
 
 39 
 
 2 
 
 3 
 
 4 
 
 Tread plate, vooden, 1 per 2 car spots 
 
 each 
 
 10 
 
 — 
 
 10 
 
 4 
 
 6 
 
 8 
 
 Icing 
 
 
 
 
 
 
 
 
 Ice crusher, complete with sheaves, belts, 
 
 
 
 
 
 
 
 
 and 10 h.p. motor 
 
 each 
 
 1,083 
 
 
 
 
 1 
 
 1 
 
 1 
 
 Ice feed screw, 12 Inch 
 
 each 
 
 206 
 
 
 60 
 
 2,715^ 
 
 1 
 
 1 
 
 1 
 
 Vertical lift, 12 inch with 10 h.p. motor 
 
 each 
 
 1,366 
 
 
 
 
 1 
 
 1 
 
 1 
 
 Horizontal icing screw in 9 -inch V-shaped trough 
 
 100 feet 
 
 991 
 
 
 
 
 1.35 
 
 2.25 
 
 3.15 
 
 Caps for end of screw 
 
 each 
 
 25 
 
 
 
 
 2 
 
 2 
 
 2 
 
 Brackets to hang trough 
 
 each 
 
 4 
 
 
 
 
 3 1 * 
 
 56 
 
 79 
 
 1.5 h.p. motor 
 
 each 
 
 233 
 
 
 
 2,2182' 
 
 1 
 
 
 
 3 h.p. motor 
 
 each 
 
 316 
 
 
 
 
 1 
 
 
 5 h.p. motor 
 
 each 
 
 387 
 
 
 
 
 
 
 1 
 
 Sprockets, drive chain, etc. 
 
 per motor 
 
 35 
 
 
 
 
 1 
 
 1 
 
 1 
 
 Icing screw gates (manual) : 
 
 
 
 
 
 
 
 
 
 Packing and top ice stations 
 
 each 
 
 26 
 
 
 
 
 8 
 
 15 
 
 23 
 
 Car spots 
 
 each 
 
 31 J 
 
 
 
 
 4 
 
 6 
 
 8 
 
 Ice bins, galvanized iron: 
 
 
 
 
 
 
 
 
 Packing station, 5 foot 
 
 each 
 
 56 
 
 12 
 
 68 
 
 7 
 
 14 
 
 21 
 
 Top ice station, 10 foot 
 
 each 
 
 100 
 
 12 
 
 112 
 
 
 
 X 
 
 Scoop shovels 
 
 each 
 
 4 
 
 
 4 
 
 8 
 
 15 
 
 23 
 
 Ice blower, portable, 20 h.p. complete with tubes, 
 
 
 
 
 
 
 
 
 hose, and deflector nozzle 
 
 each 
 
 1,266 
 
 
 1,266 
 
 1 
 
 X 
 
 1 
 
 Miscellaneous, other items 
 
 
 
 
 
 
 
 
 Lidder 
 
 each 
 
 4,000 
 
 
 4,000 
 
 1 
 
 1 
 
 1 
 
 Empty crate conveyor, 14 Inch roller type, on 
 
 
 
 
 
 
 
 
 6 inch centers 
 
 100 feet 
 
 301 
 
 137 
 
 438 
 
 1.00 
 
 1.75 
 
 2.50 
 
 Clamp trucks 
 
 each 
 
 85 
 
 
 85 
 
 2 
 
 2 
 
 2 
 
 Label soaking tank 
 
 each 
 
 85 
 
 
 85 
 
 1 
 
 1 
 
 1 
 
 a/ Cull elevator and cull hopper installed as a unit. 
 
 b/ Bracketed items installed as a complete system. The $1,786 installed price is applicable to 210 crate capacity plants. 
 " For 420 and 630 crate capacity plants, the installed prices are $1,857 and $1,928, respectively, 
 c/ Bracketed items installed as a unit. 
 
 d/ Bracketed items installed as a unit. Installation charges may be computed on the following basis: I = $10 + 62.5F, 
 " where I Is the Installation charge and F is the number of 100-foot sections of icing screw. The $2,218 represents the 
 
 installed price of the system for a 210 crate capacity plant. For 420 and 63O crate capacity plants, the installed prices 
 
 are $3,58l and $4,963, respectively. 
 
20. 
 
 plant operation, and to a large extent its capacity determines the total amount 
 of equipment required for various levels of output. Most of the equipment uti- 
 lized is designed either to supply packers lettuce or other packing materials, 
 such as crates and ice, or to move the packed crates from the packer to the 
 railroad car. 
 
 As a matter of convenience, equipment requirements shown in Table 2 are 
 broken down into six categories, namely, trimming and packing, cull disposal, 
 packed crate conveyor, car loading, icing, and miscellaneous. The kind and 
 amount of equipment used in each of these categories were determined by obser- 
 vation made in packing plants, discussion with packing plant managers, and esti- 
 mates by equipment manufacturers. Where particular equipment items differed 
 slightly either in design or operation but with little discernable difference 
 in performance, the lower cost item was chosen. 
 
 From Table 2 it is clear that some of the items, for example, packing 
 stands, are identical for all sizes of plants and that osrly the amounts vary* 
 Other items are necessarily larger in the larger plants. For example, the 
 capacities of electric motors used in driving conveyors must increase as scale 
 of operation increases because of the greater length of the conveyor involved. 
 
 Equipment Replacement Costs and Annual Fixed Costs of Equipment 
 
 When equipment requirements have been determined, replacement costs for 
 equipment may be computed by applying the appropriate prices to each of the 
 items included and multiplying by the number required. Table 2 includes the 
 price of each equipment item delivered in Salinas, the installation cost, and 
 the total installed price. Certain items are installed as part of an integrated 
 system, for example, conveyors, and for them the installed prices are presented 
 for the system rather than for individual components, 
 
 Estimated equipment replacement costs for the three sizes of packing plants, 
 computed by the above procedures, are presented in Table 3« Also included in 
 the table are the estimated annual fixed costs of equipment which are derived 
 from the replacement costs. Included in fixed costs are allowances for depre- 
 ciation, annual fixed repair, insurance, interest, and taxes. The rates for 
 these charges, as per cents of replacement costs, were determined from infor- 
 mation contained in previous studies of packing plant operation and published 
 estimates of plant equipment use life by the U. S. Treasv y Department. The 
 specific rates used and the sources are included in Table 3. 
 
TABLE 3 
 
 Replacement Costs and Annual Fixed Costs of Equipment for Lettuce Packing Plants 
 of Three Different Capacities, Salinas District, 195U 
 
 
 Replacement costs as related 
 to plant capacity 
 
 Annual fixed cost as related 
 to plant capacity!!/ 
 
 
 Crates per hour 
 
 Crates per hour 
 
 Cost component 
 
 210 
 
 U20 
 
 630 
 
 210 
 
 ^20 
 
 630 
 
 
 dollars 
 
 Trimming and packing 
 
 17,236 
 
 31,638 
 
 51,312 
 
 2,620 
 
 5,265 
 
 7,799 
 
 Cull disposal 
 Packing plant equipment 
 
 6,06U 
 
 6,06U 
 
 6,06U 
 
 922 
 
 922 
 
 922 
 
 Cull trucks 
 
 5,000 
 
 10,000 
 
 15,000 
 
 1,12U 
 
 2,2U8 
 
 3,376 
 
 Loaded crate conveyor 
 
 U,307 
 
 6,560 
 
 8,735 
 
 655 
 
 997 
 
 1,328 
 
 Carloading 
 
 U68 
 
 702 
 
 936 
 
 71 
 
 107 
 
 1U2 
 
 Icing 
 
 6,819 
 
 8,686 
 
 10,576 
 
 1,036 
 
 1,320 
 
 1,608 
 
 Miscellaneous 
 
 U,693 
 
 5,022 
 
 5,351 
 
 713 
 
 763 
 
 813 
 
 Total 
 
 Wi,587 
 
 71,672 
 
 97,97U 
 
 7,lUl 
 
 11,622 
 
 15,988 
 
 a/ The use life for equipment was derived from info mation contained in Samraet, L» L., and I. P, Davis, Buildinr 
 J and Equipment Costs, Apple and Pear Packing (Berkeley: University of California, College of Agriculture, 
 AgriguiWL Experiment Station, December, 1952), p. 19. (Giannini Foundation Mimeographed Report No. lijl.J 
 Processed, Also, U, S. Department of Treasury, Tables of Useful Lives of Depreciable Property (Washington: 
 Gotu 0 Print. Off., 19U8), p. 17. (U. S. Internal Revenue Service Publication 117, Bulletin F.) 
 
 The annual charges for each cost component, excluding cull trucks, computed as a per cent of replacement 
 cost, are as follows: depreciation, 6.7 per cent; repairs, 3.0 per centj insurance, 1.5 per cent; and _ interest 
 and taxes, U.O per cent. For cull trucks these per cents of replacement costs are as follows: depreciation, 
 3 2.5 per cent; interest on investment, 3 per centj fixed repair, 3 per centj and tax and license fees were esti- 
 mated to be $531 per year based on information furnished by the State Department of Motor Vehicles. Insurance 
 was estimated to be $68 per year based on information supplied by a mutual automobile company. 
 
•c-' -Mia 
 
 1 
 
 
 * 
 
 
 ■ 
 
 
 
 ■ - 
 
 
 
 
 
 ... ' - 
 
 
 
 
 
 
 
 
 
 
 
 .. .. 
 
 i ■ . 
 
 
 
 
 
 
 
 I 
 
 
 
 
 
 
 
 
 
 
 ■ 
 
22. 
 
 Variable Repair and Equipment Operating Costs 
 
 Table 1; presents estimated variable repair and equipment operating costs 
 per day for the three sizes of packing plants. This category includes the cost 
 of fuel, lubrication, tires, and repair on cull trucks, and the costs of elec- 
 tric power and repairs for plant equipment. The details of operating costs per 
 hour for cull trucks are presented in a footnote to the table. Variable repair 
 costs were estimated as 0.8 per cent of replacement costs per 100 hours' use. 
 The costs of electric power were estimated to be 1.0 cent per kilowatt hour per 
 horsepower hour. Repair costs for packing plant equipment were estimated as 
 being 0,£ per cent of replacement costs per 100 hours' use. These costs were 
 estimated on an hourly basis and then extended to the standard eight-hour day 
 used in this analysis. 
 
 Costs of Packing Materials and Supplies 
 
 Unit costs of packing materials and supplies taken from accounting record 
 data on a sample of plants are presented in Table 5. Insofar as could be de- 
 termined, these costs did not vary significantly with size of plant. Materials 
 and supplies costs per day, obtained by multiplying the crates packed per day 
 by unit costs, were £;1,UU8, :)2,096, and &U,3U* for plants with 210-, U20-, and 
 630-crate-per-hour capacity, respectively. 
 
 Building Requirements and Costs 
 
 Estimation of replacement costs for buildings is a txro-stage process in- 
 volving estimation of floor space requirements as it is related to output and 
 the construction costs incurred in meeting these requirements. In Salinas the 
 type of building construction used is relatively uniform. Buildings usually 
 have a concrete floor built to truck -bed height on an earth fill. The sides 
 and roof are corrugated, galvanized iron sheets with a clear height from the 
 floor to the underside of the roof trusses of 12 feet and a short-span roof 
 construction, An exterior view of a packing plant of this type of construction 
 is shown in Figure 7. 
 
 Space Requirements 
 
 Floor space requirements for the interior of the packing house and the 
 loading dock are given in Table 6, Also included in the table are the surface 
 area requirements for the cull sluice, cull pit, and ice-crusher pit. 
 
TABLE h 
 
 Variable Equipment Repair and Operating Costs Per Day for Lettuce 
 Packing Plants of Three Different Capacities, Salinas District, 195U 
 
 Capacity, 
 crates 
 per hour 
 
 Estimated equipment 
 replacement costs 
 
 Total 
 installed 
 motor 
 horsepower 
 
 Estimated variable equipment repair and operating cost 
 
 Repair 
 
 Qperating , 
 
 Total 
 
 Packing plant | Cull trucks 
 
 Packing plants/ 1 Cull trucksV 
 
 Power£/ i Cull trucksif/ 
 
 210 
 U20 
 630 
 
 dollars 
 
 73 
 81 
 90 
 
 dollars 
 
 39,587 
 61,672 
 82,97U 
 
 * 
 
 5,000 
 10,000 
 
 15,000 
 
 l5»83 
 2h»6l 
 33.19 
 
 3.20 
 6 o ii0 
 9.60 
 
 5o8U 
 6 a U8 
 7.20 
 
 5.76 
 11.52 
 17.28 
 
 30.63 
 1*9-07 
 67.27 
 
 a/ Variable repair for packing plant equipment is estimated on the basis of 0,5 per cent of replacement cost per 
 100 hours of use. 
 
 b/ Variable repair for trucks is et&imated on the basis of 0.8 per cent of replacement cost per 100 hours of use„ 
 
 c/ Cost of electric power is estimated on the basis of l o 0 cent per kilowatt hour per horsepower hour. 
 
 d/ Operating costs for cull trucks per hour are as follows: gasoline, U8 cents j oil and grease, 5 cents; tires, 
 19 cents j and repairs and miscellaneous, U0 cents. 
 
- 
 
 
 — . 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 . . - ...... - . - 
 
2U. 
 
 TABLE $ 
 
 Costs of Materials and Supplies for Packing Lettuce, 
 Salinas District, California, 195k 
 
 Item 
 
 Costs per cratejV 
 
 
 dollars 
 
 Crates 
 
 .5106 
 
 Liners (2 per crate) 
 
 .0719 
 
 Pads (3 per crate 
 
 .0765 
 
 Lids 
 
 .0886 
 
 Nails, labels, and paste 
 
 .0090 
 
 Car bracing 
 
 .0115 
 
 Crate ice^ 
 
 .0600 
 
 Water 
 
 .0030 
 
 Total 
 
 .8621 
 
 a/ Average of record data from several firms, 
 b/ Includes chemical treatment, 
 
 c/ Based on a charge of &U.00 per ton for ice delivered to the pack- 
 ing house which was typical in the Salinas district in 195U. The 
 average amount of ice per crate was estimated at 30 pounds. Crushed 
 ice blown over the crates after they have been loaded in the rail- 
 road car is paid for by the buyer on f.o.b. sales and is not included 
 in this analysis. 
 
.irrtx.. 
 
TABLE 6 
 
 Building Space Requirements for Lettuce Packing House of 
 Three Different Capacities, Salinas District, 195U 
 
 Plant 
 capacity, 
 
 crates 
 per hour 
 
 Floor 
 
 space 
 
 Surface area of 
 cull sluice, cull pit, 
 and ice-crusher pit£/ 
 
 Enclosed areaf/ 
 
 Loading doclcjV 
 
 
 square feet 
 
 210 
 
 9,210 
 
 1,550 
 
 1,930 
 
 U20 
 
 13,620 
 
 2,U5o 
 
 2,210 
 
 630 
 
 18,030 
 
 3,350 
 
 2,H90 
 
 a/ Estimated from the following equation: A = 60 (80 + 10. 5P) where A is area in square feet, 
 ~~ P is the number of packing stations, and 60 is the width of the packing house in feet. 
 
 b/ Estimated from the following equation: A = 10 (20 + U5C) where A is area in square feet, 
 " G is the number of car spots, and 10 is the width of the loading dock in feet. 
 
 c/ Estimated from the following equation: SA = 1,650 + I4.OP where SA is surface area in square 
 feet and P the number of packing stations. 
 
27. 
 
 Interior space requirements represent the sum of the requirements for each 
 piece of equipment, the necessary storage space, and allowances for passageways 
 through the plant. Over-all interior space requirements were found to be uniquely 
 related to the number of packing stations. This relationship is expressed in 
 footnote a, Table 6. 
 
 In addition to the interior space requirements, a roofed loading dock is 
 required for the packing plant. The important factor affecting the space re- 
 quired in this case was found to be the number of "car spots" needed for posi- 
 tioning refrigerator cars along the dock. While there was some variation in 
 the number of car spots utilized by the packing plants observed, it was deter- 
 mined that k> 6, and 8 car spots, each h$ feet long, would be required for pack- 
 ing plants with capacities of 210, U20, and 630 crates per hour, respectively. 
 The relationship between the number of car spots and loading dock space require- 
 ments is shown in footnote b, Table 6. 
 
 The surface area of concrete required for the cull sluice, cull pit, and 
 ice-crusher pit shown in Table 6 was determined by measurements made in packing 
 plants. These measurements in turn were related to the number of packing sta- 
 tions, and this relationship is shown in footnote c, Table 6. 
 
 3uilding Replacement Costs and Annual Fixed Costs for Buildings 
 
 When total space requirements have been determined, building replacement 
 costs may be estimated. These estimates are presented in Table 7 for the three 
 sizes of packing plants along with estimates of annual fixed costs. The type 
 of construction to which they apply has been described earlier. The prices for 
 materials and wages used in their construction are those which applied in 195U. 
 The relationships between floor space requirements, for both the interior of the 
 plant and the loading dock, and replacement costs are given in the footnotes to 
 Table 7. 
 
 In addition, an estimate is given in the table for installing the switch 
 gear, wiring electric motors, and installing fluorescent lighting over the pack- 
 ing line. The data on which these estimates were based were supplied by an 
 electrical contractor in Salinas. These estimates were related to total re- 
 quired horsepower and the number of packing stations which is shown in foot- 
 note e, Table 7. 
 
 Since the life of buildings extends over a number of years, their costs 
 per operating season must be computed on the basis of annual charges which in- 
 clude depreciation, interest on investment, insurance, and repairs. 
 
exl.t 
 
TABLE 7 
 
 Replacement Costs^' and Annual Fixed Costs—' of Buildings for Lettuce Packing Plants 
 of Three Different Capacities, Salinas District, 195U 
 
 
 Replacement costs as related 
 to plant capacity 
 
 Annual fixed cost as related 
 to plant capacity 
 
 
 Crates per hour 
 
 Crates per hour 
 
 Cost component 
 
 210 
 
 L;20 
 
 630 
 
 210 
 
 U20 
 
 630 
 
 
 dollars 
 
 c/ 
 
 Building and loading dock- 
 
 38,850 
 
 56,990 
 
 75,120 
 
 U,079 
 
 
 7,888 
 
 Cull sluice, cull pit, and ice- 
 crusher pitfy 
 
 1,310 
 
 i,5oo 
 
 1,690 
 
 138 
 
 158 
 
 177 
 
 Wiring , 
 Motors and fluorescent lighting-/ 
 
 1,590 
 
 1, 900 
 
 2,200 
 
 167 
 
 200 
 
 231 
 
 Total 
 
 111, 750 
 
 60,390 
 
 79,030 
 
 U,38U 
 
 6,3U2 
 
 8,296 
 
 a/ Based on 195U prices for building materials and equipment and 195U wage rates for construction labor. 
 
 b/ The use life for buildings was derived from information contained in Sammet, L. L., and I, F» Davis, Building 
 and Equipment Costs, Apple and Pear Packing (Berkeley: University of California, College of Agriculture, Agri- 
 cultural Experiment Station, December, 1952), p. 19. (Giannini Foundation Mimeographed Report No. lhl.) Proc- 
 essed, Also, U. S. Department of Treasury, Tabl e s of Useful Lives of Depreciable Prope rty (Washington: Govt-, 
 Print, Off., 19U8), p. 17. (U. S. "nternal Revenue Service Publication 117, Bulletin FT) 
 
 The annual charges for each cost component computed as a per cent of replacement cost are as follows: 
 depreciation, 3.0 per cent; repairs, 2.0 per cent; insurance, 1<,5 per cent; and interest and taxes, U.O per cent. 
 
 c/ Estimated from the following equation: C = 02,090 + 3.U16A where C is the building cost and A is the total floor 
 space and square feet for the packing house and loading dock. 
 
 d/ Estimated from the following equation: C * &0.678A where C is the cost of cull sluice, cull pit, and ice-crusher 
 pit; and A is the surface area in square feet of this item. 
 
 e/ Estimated from the following equation: C = §300 + 20H + 20P where C is the cost of wiring electric motors and 
 fluorescent lighting, II is the total horsepoxjer rating of the motors, and P is the number of packing stations <, 
 
I 
 
29. 
 
 The rate of depreciation is dependent on the expected use life of the 
 building. In this study it was estimated that buildings would last about 33 
 years with no salvage value at the end of that time. This would lead to a 
 depreciation rate of 3 per cent of replacement costs per year 0 The rates for 
 the other annual charges as per cents of replacement costs were determined 
 from information contained in previous studies of packing plants and published 
 estimates of the U. S. Treasury Department. The rates and sources are included 
 in Table 7. 
 
30. 
 
 HARVESTING AND HAULING OPERATIONS AND COSTS 
 
 Operations Performed 
 
 The harvesting method to which the costs in this section apply is illus- 
 trated in Figure 8 which shows a loader and harvesting crew in operation. 
 Other methods were observed^/ but this one predominated. The crew for each 
 field loader consists of from 12 to 1$ cutters, 2 load arrangers, a crew boss 
 or "pusher," and drivers for the equipment. A field foreman generally over- 
 sees and coordinates the harvesting operations of two loaders. The equipment, 
 aside from the loader, consists of trucks and trailers fitted with baskets for 
 hauling the harvested lettuce to the packing house and a field tractor or "bug" 
 which is used for pulling the trailers through the field while they are being 
 loaded. 
 
 The loader consists of a mechanized conveyor pivot mounted on a specially 
 constructed truck chassis so that it can be swung to a trailing position 
 during highway travel and extended at right angles to the power unit when in 
 use for harvesting. Conveyor lengths varied on different loaders ranging from 
 13 to Ik beds coverage. The conveyor length is limited by regulations on 
 equipment that travel on public highways as well as by technical considerations o 
 
 The rate of travel of the loader through the field is regulated by the 
 driver in accordance with the harvest density-'' — slow at heavy densities and 
 speeding up as the density becomes light. Since there are variations in the 
 harvest density from one end of the field to the other as well as across the 
 beds, the rate of output of the crew depends, in large measure, upon the skill 
 of the loader-driver in adjusting the forward- speed to the harvest density. 
 
 The cutters walk behind the loader — one in each irrigation furrow. They 
 select and cut the mature heads of lettuce and toss them on the conveyor, 
 Each cutter harvests the two rows adjacent to the furrow in which he is walk- 
 ing. The crew boss or "pusher" specifies the desired firmness and size of the 
 
 1/ The most common other method involved use of field trailers drawn through 
 the harvest strip by farm tractors. Six to eight cutters - positioned to the 
 rear and sides of the trailer, cut lettuce from the harvest beds and toss it 
 directly on the trailer, A limited number of studies of this method indicated 
 little difference in the rate of output per man-hour between it and the one 
 described in the text. 
 
 2/ Harvest density is an important concept that will be used throughout this 
 report. It refers to the number of baskets of lettuce harvested per 1,000 
 feet of bed in a given cutting. 
 
 * 
 
■i ' O i, 
 
Figure 8. Lettuce Harvesting Crew and Loader in Operation. 
 
32. 
 
 heads to be cut and spot checks the harvested lettuce to see that the instruc- 
 tions are being followed. He also walks across the beds behind the cutters 
 and harvests any mature lettuce that has been missed. 
 
 Cut lettuce is conveyed toward the power unit, elevated over it, and 
 dumped into baskets on a truck or trailer moving parallel to the loader. 
 Truck capacities vary from five to six baskets and trailer capacities from 
 four to five baskets. The baskets are mounted on casters and range in volume 
 from approximately 100 to 120 cubic feet when loaded— roughly equivalent to 
 7^0 to 900 heads of lettuce. The two load arrangers ride the trucks or trailers 
 as they are being loaded and arrange the lettuce on top of the baskets to assure 
 a full load without spillage en route to the packing house. 
 
 When the end of a harvest strip is reached, the equipment is turned and 
 moved to the next harvest strip. When a truck or trailer is loaded, it is 
 driven from the loader to the edge of the field, and a waiting truck or trailer 
 takes its place — usually with no interruption to the harvesting operation* En 
 route to the packing house, a loaded truck usually picks up a loaded trailer. 
 
 Factors Affecting Crew Requirements and Costs 
 
 Many factors affect crew requirements and costs. A major determinant of 
 the over-all requirements is the scale of operation of the packing plant. 
 Total field crew size, with given levels of productivity, must be large enough 
 to sustain the levels of plant output desired. The productivity of given sizes 
 of harvesting and hauling crews is in turn affected by a number of factors o 
 
 In harvesting operations output rate with a given crew is affected by 
 management policy with respect to the "quality" of pack, scheduled rest periods 
 for the workers, skills of the crew (particularly certain key members), the num- 
 ber of times the field has been previously cut, the condition of the field, the 
 length of the harvest strips, and the harvest density (previously defined). 
 
 The productivity of hauling crews is also affected by these factors since 
 all have a bearing on the time required for loading and, in addition, depend 
 on the distance from the field to the packing plant. 
 
 However, of all the factors bearing on productivity, only a few could be 
 included specifically in the analysis. Harvesting time requirements have been 
 related to harvest density and length of harvest stripj and the number of trucks, 
 trailers, and drivers required has been related to hauling distance and harvest- 
 ing time requirements. Average relationships are presented with respect to the 
 other factors. 
 
33. 
 
 Crew and Equipment Requirements and Costs in Relation to Output Per Day 
 
 Production Standards 
 
 Production standards for labor and equipment in relation to the factors 
 discussed above were developed from time and production studies of the har- 
 vesting and hauling operations. In all, 252 separate field studies were made 
 of 7 different firms representing 15 different crews operating in h3 fields « 
 Each field study represents the observations made of a harvesting crew while 
 working through one harvest strip — one traverse of the fxeld. Observations 
 were made as to the size of the crew, the number of workers in each job cate- 
 gory, the number of trucks and trailers used, the net time required to harvest 
 the strip, the time spent in delays and the reason for the delay, the time 
 spent in turning at the end of each strip, the amount of lettuce harvested, the 
 size of the baskets, the length of the harvest strips, the number of beds cut 
 per strip, the number of times the field had been previously cut, the time of 
 day, the distance from the field to the packing plant, and a log of the time 
 required by the trucks to make a round trip from the field to the packing plant 
 and return o 
 
 The standards are based on net labor requirements to which have been added 
 allowances for unavoidable delays, personal time, and turning time at the end 
 of the harvest stripe Gross time requirements estimated in this way are then 
 converted to output rates per hour to obtain the production standards* 
 
 One of the most important factors affecting the rate of output of a crew 
 is the harvest density 9 This relationship is illustrated in Figure 9 which 
 shows net time requirements per 1,000 feet of strip in relation to harvest 
 density — expressed in standardized baskets of approximately 100 cubic feet — 
 observed in each of the 252 field studies. Average net time requirements in 
 relation to harvest density are shown by the sloping line drawn through the 
 points for individual studies plotted in Figure 9.- The field studies indi- 
 cated that, in addition to the net time requirements, an additional 5 per cent 
 should be allowed for unavoidable delays and personal timej and an average 
 turning time of three minutes at the end of each strip should be included. 
 
 1/ A regression equation fitted to this relationship gave the following 
 result: T = 11.255 + 30.2li8D where T is the travel time in minutes per 1,000 
 feet of bed and D is harvest density in baskets per 1,000 feet of bed. 
 
%4 
 
 100 
 
 c 
 E 
 
 0) 
 
 O 
 O 
 
 o 
 
 - 50 
 
 a. 
 a> 
 E 
 
 > 
 
 D 
 
 0 
 
 1 
 
 i i i 
 • i i 
 
 i i i r — i 1 — 
 
 I'll 
 
 • 
 
 
 ' 1 " 
 
 i 
 
 • 
 
 Individual 
 
 
 
 
 
 harvest strip 
 
 • 
 
 • 
 
 • 
 
 
 
 Average 
 
 • 
 
 • • 
 
 
 
 — 
 
 
 
 
 
 
 • 
 
 ' . • • . 
 
 
 • 
 
 
 • • * • ^ 
 
 
 
 
 1 
 
 
 •• 
 
 • 
 
 • 
 
 
 
 * • • 
 
 ir .:* ... .: • 
 
 
 
 
 
 
 
 
 
 -?•* 
 
 i 
 
 1 1 1 
 
 1 1 1 1 1 1 
 
 1 
 
 1 
 
 1.0 2.0 
 Density - baskets harvested per 1,000 feet of bed 
 
 Figure 9. The Effect of Harvest Density on Rate of Travel 
 of Harvest Crews, Salinas District, California. 
 1953-5U. 
 
35. 
 
 Standard time requirements and output rates per cutter hour— in stand- 
 ardized baskets of 100 cubic feet volume — based on the above data are given 
 in Table 8 for harvest strips of different harvest densities and lengths. Out- 
 put per crew hour for crews of any size may be obtained by multiplying output 
 per man-hour by the number of cutters used. For example, with a crew of 30 
 cutters (two loading machines with 15 men each) and a harvest density of .ij35 
 baskets per 1,000 feet of bed, output per crew hour would be 27.57 baskets. 
 
 The estimates of output per cutter hour given in Table 8 and shown 
 graphically in Figure 10 indicate output rates increase as harvest density in- 
 creases. This rise in output rate becomes smaller, however, as harvest density 
 increases, and little increase is indicated beyond harvest densities of 1.3 
 baskets per 1,000 feet of bed. Output rates are also shown to increase as 
 length of harvest strip increases. However, the rise in output drops rapidly 
 as length of strip increases, and the fixed turning time at the end of the 
 strip is spread over a large total volume. This effect is relatively small 
 with harvest strips greater than 500 feet long. The crew organizations and 
 costs of harvesting and hauling presented in the sections that f olloxtf will be 
 based on strips 1,000 feet in length which is the average for all on whi^b 
 studies were made. 
 
 Harvestin g Crow and Equipment Requirements 
 
 With the data on cutter output rate described above, harvest crew organi- 
 zation can be studie in relation to variations in harvest density and the 
 volume of lettuce required per day at the packing house. Plant and field 
 operating conditions specified earlier, which have particular bearing on field 
 crew organization, include? the 8-hour plant day; the 3 plant sizes of 210-, 
 U20-, and 630- crate -per-hour capacity j and the 6- to 9o-hour limit imposed on 
 field hours per day. 
 
 With the 8-hour per day plant operation and the selected plant sizes, 
 daily outputs of 1,680, 3,360, and 5>0l;0 crates would result. The average pack- 
 out in crates per standardized field basket for firms coooerating in this study 
 was 8.8. While there was some variation around this average, it was considered 
 representative enough to be used as the basis for estimating the number of bas- 
 kets needed — given the number of crates to be packed. Accordingly, the number 
 of baskets required per day for the three sizes of plants are 191, 382, and 
 573> respectively. For packouts per basket of less than 8.8 crates, the bas- 
 ket requirements would be correspondingly higher; and the converse is true for 
 higher packouts per basket. 
 
TABLE 8 
 
 Cutter Time Requirements in Harvesting Head Lettuce Expressed in Man-Hours Per Basket 
 and Production Standards in Baskets Per Man-Hour with Different Levels of Harvest 
 Density and Length of Harvest Strip, Salinas District, 1953-51* 
 
 Harvest density 
 in baskets per 
 
 Time requirements in man-hours per basket for strips of varying length^ 
 
 1,000 feet of bed 
 
 250 feet 
 
 500 feet 
 
 1,000 feet 
 
 1,500 feet 
 
 
 1.101 
 
 1.202 
 
 1.088 
 
 1.052 
 
 •Op*! 
 
 1.161 
 
 1.006 
 
 .925 
 
 .899 
 
 .870 
 
 .982 
 
 .867 
 
 .810 
 
 .791 
 
 1.087 
 
 .877 
 
 • 787 
 
 .71*1* 
 
 .729 
 
 1.301* 
 
 . .81*1* 
 
 .765 
 
 .726 
 
 .712 
 
 
 Output in baskets per man-hour 
 
 .1*35 
 
 .709 
 
 .832 
 
 .919 
 
 • .951 
 
 .652 
 
 .861 
 
 .991* 
 
 1.081 
 
 1.113 
 
 .870 
 
 1.018 
 
 1.153 
 
 1.231* 
 
 1.261* 
 
 1.087 
 
 1.11*0 
 
 1.270 
 
 1.31*1* 
 
 1.372 
 
 1.30k 
 
 1.185 
 
 1.306 
 
 1.378 
 
 1.1*01* 
 
 a/ Time requirements per basket for strips of varying length were estimated by the following equations: 
 
 250 feet T = 2.129750 - 1.9851*60D + .766251D 2 
 500 feet T = 1.770581* - 1.57l*952D + .616 70 3D 2 
 1,000 feet T = 1.559012 - 1.30i*5llD + .5l0l*27D 2 
 
 1,500 feet T = 1.1*93772 - 1.225661D + .l*8o!*l6D 2 
 
 where T is time in man-hours, and D is harvest density. 
 
37. 
 
 Figure 10. The Effect of Harvest Density and Length of Harvest 
 Strip on Output Per Man-Hour of Standardized Baskets 
 of Lettuce, 100 Cubic Feet in Volume, Salinas Dis- 
 trict, 1953-5U. 
 
38. 
 
 Technical and legal limitations on size of equipment also play a role in 
 the determination of crew organization. Field loading equipment usually- 
 covered from 13 to Ik harvest beds when extended at right angles from the power 
 unit (see Figure 8). Operating difficulties concerning side draft and balance 
 prevent extension much beyond these lengths. In addition, since the conveyor 
 part of the loader swings to the rear for overroad travel, its length must be 
 limited to conform to the California Vehicle Code. These considerations sug- 
 gest, for purposes of this analysis, that the conveyor be assumed to extend 
 over Ik harvest beds. This would permit cutter crew sizes up to 1$ men— 1 man 
 working beyond the end of the conveyor. To get the maximum utilization out of 
 the loader, it should where possible be operated with 15 cutters. However, the 
 lower limit of a 6-hour workday for harvesting cre-ws, discussed earlier, makes 
 it necessary to operate with less than 15 men under certain conditions. 
 
 On the basis of the production standards shown in Table 8, the number and 
 sizes of crews necessary to attain the specified levels of output within the 
 limits imposed above were designed. These crew organizations are presented in 
 Table 9« Also included in the table are the number of hours worked per day for 
 the various sized crews and levels of harvest density. Loader and tractor 
 drivers were allowed an extra hour per day to account for the time spent in 
 driving to and from the field. The time actually spent in travel would vary 
 with distance, and this allowance represents an average. 
 
 Cutter crew sizes per loader vary only in the case of those serving the 
 small plants. The number of other workers required per loader is fixed for 
 any level of output. For example, each loader requires one loader driver, one 
 tractor driver, two load arrangers, and one row boss. Insofar as over-all 
 supervision was concerned, it was estimated that one field foreman could handle 
 up to two harvest crews. Assistant supervisors were added as necessary for 
 more than two crews. 
 
 Truck Driver and Hauling Equipment Requirements 
 
 The number of truck drivers and truck-trailer units needed to attain the 
 target levels of output specified above depends on several factors. These 
 include the distance from the field to the packing plant, traffic conditions 
 over the route traveled, condition of the field being harvested, harvest den- 
 sity, the length of harvest strip, the number of crews operating, and the 
 size of each crew. 
 
TABLE 9 
 
 Lettuce Harvesting Crew Organization and Hours Worked Per Day in Relation to 
 Daily Output and Harvest Density, Salinas District, California, 195U 
 
 Baskets of 
 lettuce re- 
 quired per 
 dayV 
 
 Harvest density, 
 baskets per 
 1,000 feet 
 of bed£' 
 
 Number of 
 
 loading 
 
 machines 
 
 and / 
 
 «, . c/ 
 
 drivers— 
 
 Number of 
 field tractors 
 and / 
 drivers— 
 
 Number 
 
 of 
 cutters 
 
 Number of 
 
 load 
 arrangers 
 
 Number 
 
 of 
 row 
 bosses 
 
 Number of 
 supervisors 
 
 and 
 assistants 
 
 dumber of 
 
 hours 
 worked by 
 crew per 
 day 
 
 
 .U35 
 
 2 
 
 2 
 
 30 
 
 h 
 
 2 
 
 1 
 
 7.00 
 
 191 
 
 .652 
 
 2 
 
 2 
 
 29 
 
 k 
 
 2 
 
 1 
 
 6.25 
 
 .870 
 
 2 
 
 2 
 
 26 
 
 h 
 
 2 
 
 1 
 
 6.00 
 
 
 1.087 
 
 2 
 
 2 
 
 23 
 
 h 
 
 2 
 
 1 
 
 6.25 
 
 
 .U35 
 
 k 
 
 i» 
 
 60 
 
 8 
 
 h 
 
 2 
 
 7.00 
 
 382 
 
 .652 
 
 3 
 
 3 
 
 U5 
 
 6 
 
 3 
 
 2 
 
 8.00 
 
 .870 
 
 3 
 
 3 
 
 k$ 
 
 6 
 
 3 
 
 2 
 
 7.00 
 
 
 1.087 
 
 3 
 
 3 
 
 U5 
 
 6 
 
 3 
 
 2 
 
 6.50 
 
 
 .U35 
 
 5 
 
 5 
 
 75 
 
 10 
 
 5 
 
 3 
 
 8.50 
 
 573 
 
 .652 
 
 it 
 
 U 
 
 60 
 
 8 
 
 k 
 
 2 
 
 9.00 
 
 .870 
 
 h 
 
 It 
 
 60 
 
 8 
 
 k 
 
 2 
 
 7.75 
 
 
 1.087 
 
 h 
 
 k 
 
 60 
 
 8 
 
 h 
 
 2 
 
 7.25 
 
 a/ Based on plant output rates of 1,680, 3,360, and 5,01*0 crates per day and a packout of 8.8 crates per 
 ~" standardized field baskets. 
 
 b/ At the average packout of 8.8 crates per basket, these harvest densities are equal to 50, 75, 100, 
 ~" 125 crates per acre. 
 
 c/ The loader and tractor drivers are allowed an additional hour per day to drive to and from the fie 
 ~* being harvested. 
 
trusts 8£G sjjttisq 
 
 fjousj pctx. be-.. gstf. pc gijae fo 
 
 ;A« 
 
ho. 
 
 One of the most important of these factors is distance from field to plant. 
 A log of departure and arrival times of trucks taken at the field was used to 
 estimate the round-trip time requirements at varying distances. This relation- 
 ship is illustrated in Figure 11 »3/ Average travel time per round trip can be 
 estimated from this chart. This includes an average 23 minutes per trip re- 
 quired for the truck and trailer to be unloaded and reloaded with empty baskets 
 plus normal delays at the plant and en route. In addition, approximately seven 
 minutes were required for a truck to be driven from the loader to the edge of 
 the field, coupled to a loaded trailer and, on returning to the field, uncoupled 
 from the empty trailer and driven to the loader. Total time per round trip, 
 therefore, would average slightly over 30 minutes spent in necessary prepara- 
 tion and in terminal operations and delay plus about If minutes for each mile 
 traveled. This means that, for example, when harvest crews were operating at 
 a distance of 10 miles from the plant (20 miles round-trip distance), approxi- 
 mately 60 minutes would be required from the time a loaded truck drives away 
 from the loader to the time it could be in a position to load again. 
 
 A second factor affecting hauling requirements is the size and produc- 
 tivity of the harvesting crews. This determines the time required for actu- 
 ally loading the truck-trailer unit with lettuce. As was indicated earlier, 
 the productivity of the crew, given the length of harvest strip, is prin- 
 cipally affected by the harvest density. Thus, for example, with a crew of 
 
 15 cutters, a harvest strip of 1,000 feet in length, and a harvest density 
 of .625 baskets per 1,000 feet, crew output per hour would be approximately 
 
 16 baskets. This would mean that approximately hO minutes would be required 
 to load a truck-trailer unit (11 baskets). This time plus a travel time of 
 60 minutes, assuming a round-trip distance of 20 miles, would give a total 
 time requirement of 100 minutes per truck-trailer unit for each round trip. 
 On the basis of this total time requirement, the average number of baskets 
 hauled per hour per truck-trailer unit — the production standard — would be 
 6.6. Thus, with a crew output of 16 baskets per hour, 3 truck-trailer 
 units would be required. This is obtained by dividing the hourly output rate 
 (16 baskets) by the production standard (6.6 baskets) and rounding to the 
 nearest whole number. 
 
 1/ A regression analysis of this relationship resulted in the following 
 equation: T = 23.315 + l.li88R where T is round-trip time in minutes, and R is 
 round-trip distance. An additional seven minutes must be allowed for necessary 
 preparation and delay at the field to obtain total operating time. 
 
100 
 
 
 1 1 
 
 1 | 1 | 1 | 
 : 
 
 
 80 
 
 — 
 
 
 : 
 
 • ^ 
 
 — 
 
 60 
 
 
 • 
 
 1 
 
 
 
 40 
 
 
 • 
 
 • 
 
 
 20 
 
 
 m 
 
 \ 
 
 m 
 • 
 • 
 
 • Observed trip time 
 — Average 
 
 
 0 
 
 
 
 1- 1 1 1 1 1 1 
 
 
 0 
 
 
 10 
 
 20 30 40 
 
 50 
 
 Round trip distance - miles 
 
 Figure 11. Highway Truck Travel Time in Rela- 
 tion to Round-Trip Distance Between 
 Field and Packing House, Salinas 
 District, California, 1953-51*. 
 
■ 
 
k2. 
 
 In a similar manner the estimated truck and driver requirements for vary- 
 ing distances, harvest density, and crew size presented in Table 10 were devel- 
 oped. The exact computational procedure is summarized in an equation given in 
 a footnote to the table. This equation is applicable to round- trip distances 
 from field to plant of up to b.0 miles and to the range of crew organizations 
 and harvest densities observed in the Salinas district. As was indicated ear- 
 lier, it would apply only to harvest strips 1,000 feet in length. It assumes 
 that all crews are operating in the same field. Where operations are widely 
 separated, separate estimates xfould be required for each individual operation. 
 
 Harvesting and Hauling Labor and Supervision Costs Per Day 
 
 Total daily harvesting and hauling labor and supervision costs are pre- 
 sented in Table 11 for varying conditions in regard to output per day, harvest 
 density, and distance from field to plant. These costs were obtained by multi- 
 plying the total number of man-hours worked per day in each job category derived 
 from Tables 9 and 10 by the appropriate wage rate shown in the footnotes to 
 Table 11. Costs of each category were added to obtain total labor costs. 
 
 Wage rates for equipment operators and foremen are based on straight time 
 up to eight hours per day and time and one half for all hours over eight. Wage 
 rates for the other job categories are based on straight time for all hours. 
 
 In the field operations studies, the cutters and load arrangers were Mexi- 
 can Nationals who lived in labor camps. In the cost calculations, their wages 
 were inflated by 11 per cent to cover camp costs borne by the employer M The 
 wages of other workers xrare inflated by £ per cent to cover the employer's con- 
 tribution to workmen's compensation, social security, and unemployment insurance 
 funds. 
 
 The typical salary for field foremen was $12$ per week and that of assist- 
 ants was $100. These men usually performed other functions when not supervising 
 harvesting crews, but in this analysis their salaries were assumed to be allo- 
 cated entirely to field harvest work on the basis of a U0-hour week. This is 
 equivalent to $3.13 and $2.^0 per hour, respectively. 
 
 1/ The 11-per cent allowance is based on estimates supplied by employers. 
 
TABLE 10 
 
 Number of Truck-Trailer Units and Drivers Required for Harvesting and Hauling Lettuce 
 in Relation to Distance Traveled, Harvest Density, and Output Per Day- 
 Salinas District, California, 1953-5U 
 
 Distance, field to 
 pacKxng nouse anu 
 return in miles 
 
 Harvest density 
 
 J_Ii UdoAt; uO Pel . 
 
 1,000 feet of bed 3 ./ 
 
 Number of truck-trailers and drivers required*?/ 
 
 Baskets harvested per day 
 
 191 
 
 382 
 
 573 
 
 
 .135 
 
 3 
 
 5 
 
 5 
 
 $ 
 
 .652 
 
 3 
 
 it 
 
 5 
 
 
 .870 
 
 3 
 
 5 
 
 6 
 
 
 1.087 
 
 3 
 
 5 
 
 6 
 
 
 .U35 
 
 ll 
 
 6 
 
 8 
 
 20 
 
 .652 
 
 h 
 
 6 
 
 7 
 
 
 .870 
 
 k 
 
 6 
 
 8 
 
 
 1.087 
 
 h 
 
 7 
 
 9 
 
 
 .U35 
 
 5 
 
 9 
 
 11 
 
 m 
 
 .652 
 
 6 
 
 8 
 
 10 
 
 
 .870 
 
 6 
 
 9 
 
 11 
 
 
 1.087 
 
 6 
 
 10 
 
 12 
 
 a/ At the average packout per basket of 8.8 crates, these harvest densities are equal to 50, 75» 100, 
 and 125 crates per acre. 
 
 b/ Add one trailer to each of the requirements shown to provide a minimum "overlap" in case of truck 
 delay. Truck-trailer requirements are computed by the following equation: 
 
 N . 1 + (1.U88R + 30.315 )C 
 
 660 [1.559012 - 1.30U511D + .510U27D 2 ] 
 
 where N is the number of truck-trailer units required rounded to the next highest whole number, R is 
 the round-trip distance traveled, C is the number of cutters, and D is harvest density in baskets per 
 1,000 feet. 
 

 
 
 
 
 
 - 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
TABLE 11 
 
 a/ 
 
 Total Daily Lettuce Harvesting and Hauling Labor Costs— 7 with Varying Daily Outputs, 
 Harvest Densities, and Round-Trip Distances from Field to Plant 
 Salinas District, California, 1953-5U 
 
 Output, 
 baskets 
 
 pel t ~- ( -s/ 
 
 T J «-\ mwft fill" 
 
 riarvesT/ 
 density, 
 baskets 
 per 1,000 
 feet 
 
 Labor and supervision costs 
 
 Total 
 
 Field harvest 
 
 Hauling 
 
 Truck drivers 
 
 Round- trip distance, 
 miles 
 
 Round-trip distance, 
 miles 
 
 Cutters 
 
 Load ar- 
 rangers 
 
 Row 
 boss 
 
 Loader 
 driver s^/ 
 
 Tractor 
 driver siy 
 
 Super- 
 visors 
 
 5 
 
 20 
 
 Uo 
 
 5 
 
 20 
 
 Uo 
 
 
 
 Hollars 
 
 
 .U35 
 
 20U 
 
 27 
 
 16 
 
 28 
 
 28 
 
 23 
 
 37 
 
 U9 
 
 62 
 
 363 
 
 375 
 
 388 
 
 1 Q/l 
 
 .652 
 
 176 
 
 2U 
 
 lU 
 
 26 
 
 26 
 
 20 
 
 33 
 
 UU 
 
 66 
 
 319 
 
 330 
 
 352 
 
 
 .870 
 
 152 
 
 23 
 
 111 
 
 25 
 
 25 
 
 20 
 
 32 
 
 U2 
 
 63 
 
 291 
 
 301 
 
 322 
 
 
 1.087 
 
 11+0 
 
 2U 
 
 lU 
 
 26 
 
 26 
 
 20 
 
 33 
 
 UU 
 
 66 
 
 283 
 
 29U 
 
 316 
 
 
 .U35 
 
 Uo8 
 
 5U 
 
 32 
 
 56 
 
 56 
 
 Ul 
 
 62 
 
 7U 
 
 111 
 
 709 
 
 721 
 
 758 
 
 
 .652 
 
 35o 
 
 U7 
 
 27 
 
 50 
 
 50 
 
 U7 
 
 56 
 
 8U 
 
 113 
 
 627 
 
 655 
 
 68U 
 
 382 
 
 .870 
 
 306 
 
 Ul 
 
 2U 
 
 U2 
 
 U2 
 
 Ul 
 
 62 
 
 7U 
 
 111 
 
 558 
 
 570 
 
 607 
 
 
 1.087 
 
 28U 
 
 38 
 
 22 
 
 Uo 
 
 Uo 
 
 38 
 
 57 
 
 80 
 
 nU 
 
 519 
 
 5U2 
 
 576 
 
 
 .U35 
 
 619 
 
 83 
 
 U8 
 
 90 
 
 90 
 
 73 
 
 77 
 
 123 
 
 169 
 
 1,080 
 
 1,126 
 
 1,172 
 
 
 .652 
 
 52U 
 
 70 
 
 Ul 
 
 77 
 
 77 
 
 53 
 
 8U 
 
 117 
 
 167 
 
 926 
 
 959 
 
 1,009 
 
 573 
 
 .870 
 
 U52 
 
 60 
 
 35 
 
 6h 
 
 6U 
 
 U6 
 
 82 
 
 109 
 
 150 
 
 803 
 
 830 
 
 871 
 
 
 1.087 
 
 U22 
 
 56 
 
 i 
 
 33 
 
 59 
 
 59 
 
 U3 
 
 77 
 
 115 
 
 153 
 
 7U9 
 
 787 
 
 1 
 
 825 
 
 a/ Wage rates per hour on which these costs are based are as follows: cutters and load arrangers — $0,875; row boss — 
 ~~ $1,075; supervisors — 03.13; assistant supervisors — $2.50; and equipment and truck drivers — $1.65. Wage rates of 
 cutters and load arrangers were inflated by 11 per cent to take care of camp costs. Rates for other workers were 
 inflated by 5 per cent to cover the employer's contribution to workmen's compensation, social security, and un- 
 employment insurance. 
 
 b/ Loader and tractor drivers are allowed an additional hour of wages per day for travel time to and from the packing 
 "" plant regardless of distance. This would tend to overestimate their wage costs slightly for short distances from 
 field to plant and underestimate them for longer distances. 
 
*5. 
 
 Equipment Costs 
 
 In addition to the costs of equipment drivers, there are other operating 
 costs for equipment which include gasoline, oil, grease, tires, maintenance, 
 and variable repairs as well as fixed costs which include depreciation, taxes, 
 licenses, interest on investment, insurance, and fixed repairs. 
 
 Operating Costs Per Day . — Costs of gasoline, oil, grease, and tires for 
 each equipment item are given on an hourly basis in Table 12. They are based 
 on data published in a report of the California Public Utilities Commission M 
 Variable repair and maintenance costs also included in the table were estimated 
 to be 0.8 per cent of replacement costs per 100 hours of use. Equipment operat- 
 ing costs per day shown in Table 13 were obtained by applying these hourly rates 
 to each of the equipment items shown in Tables 2 and 3 and multiplying by the 
 number of hours used per day. 
 
 Annual Fixed Costs of Equipment . --Annual fixed costs of equipment presented 
 in Table ll; are derived from equipment replacement costs shown in Table 12. 
 Fixed costs include allowances for depreciation, interest on investment, taxes, 
 licenses, insurance, and fixed repairs. Depreciation rates are based on an 
 eight-year use life of equipment with no allowance for salvage value. Tax and 
 license fees were estimated from information provided by the California Depart- 
 ment of Motor Vehicles. Insurance rates were supplied by a mutual automobile 
 company and are representative of charges by truck insurers. Interest on in- 
 vestment was estimated at $ per cent of the undepreciated balance of the invest- 
 
 2/ 
 
 ment which is equivalent to about 3 per cent of replacement costs per year.-' 
 
 1/ Malquist, G. L., and Fred P. Hughes, California Public Utilities Commis - 
 sion Report on Cost of Transporting Fresh Fruits and Vegetables by Hotor Vehicle 
 Equipment Within California, Excluding Movements to Canneries and Processing 
 Plants I Los Angeles; June 19, 19b?-)* (.Case No. ItbOO.J 
 
 2/ This estimate is based on the use life of similar equipment used in Cali- 
 fornia apple and pear packing houses. See Sammet, L. L,, and I. F. Davis, Build - 
 ing and Equipment Costs, Apple and Pear Packing (Berkeley: University of Cali- 
 fornia, College of Agriculture, Agricultural Experiment Station, December, 1°52), 
 p. 19. (Giannini Foundation Mimeographed Report No. Tljl ») Processed. (The 
 fifth report in a series on Efficiency in Fruit Marketing.) 
 
1 
 
h6. 
 
 TABLE 12 
 
 Replacement Costs, Annual Fixed Charges, and Operating Costs Per Hour 
 for Each Equipment Item Used in Harvesting and Hauling Lettuce 
 Salinas District, California, 1953-5U 
 
 Item 
 
 Loader, 
 wide 
 tread 
 
 2-ton 
 truck, 
 wide 
 tread 
 
 Field 
 bug, 
 wide 
 tread 
 
 Trailer, 
 wide 
 tread 
 
 
 dollars 
 
 Replacement cost 
 
 8,500 
 
 7,600 
 
 6,000 
 
 2,500 
 
 Fixed annual charges 
 Depreciation!*/ . 
 Tax and license?/ 
 Insurance 
 
 Interest on investment^/ 
 Fixed repair^/ 
 Total 
 
 1,063 
 161 
 
 80 
 
 255 
 
 255 
 i,BiU 
 
 950 
 153 
 75 
 228 
 228 
 1,63k 
 
 750 
 121 
 68 
 180 
 180 
 1,299 
 
 313 
 
 la 
 
 25 
 75 
 75 
 F29 
 
 Operating cqsts per hour*;/ 
 Gasoline*/ 
 Oil and grease£/ 
 Tire si' . 
 Repairs and miscellaneous^/ 
 Total 
 
 .U8 
 .10 
 .08 
 .68 
 
 T3E 
 
 •U8 
 .05 
 .19 
 .61 
 
 1.33 
 
 ,U8 
 .05 
 .08 
 .U8 
 1.09 
 
 .Oii 
 .20 
 
 T2i 
 
 a/ Estimated on the basis of eight-year use life and no salvage value. 
 
 b/ Derived from rates supplied by State of California Department of Motor Vehicles. 
 
 c/ Approximately 5 per cent on undepreciated balance of investment (3 per cent of 
 cost). 
 
 d/ Estimated as 3 per cent of replacement cost, 
 e/ Excluding operator's wages. 
 
 f/ Derived from data in Malquist, G. L», and Fred P. Hughes, California Public 
 Utilities Commission Report on Cost of Transporting Fresh Fruits and Vege - 
 tables by Motor Vehicle Equipment Within California, Excluding Movements to 
 Canneries and Processing; Plants (Los Angeles: June 19, 1952). (Case No, U808 • ) 
 
 g/ Estimated as 0 9 8 per cent of replacement cost per 100 hours of use. 
 
.' t 
 
TABLE 13 
 
 Total Daily Lettuce Harvesting and Hauling Equipment Operating Costs with Varying Daily Outputs, 
 Harvest Density, and Round-Trip Distances from Field to Plant 
 Salinas District, California, 1953-54 
 
 Output, 
 baskets 
 per day 
 
 Harvest 
 density, 
 baskets 
 per 1,000 
 feet of 
 bed 
 
 Loaders 
 
 Tractors 
 
 Equipment item 
 
 Trucks 
 
 Round-trip distance, miles 
 5 I 20 I hO 
 
 Trailers 
 
 Round- trip distance, miles 
 
 5 T 20 I ko 
 
 Total 
 
 Round-trip distance, miles 
 
 20 I 
 
 4o 
 
 191 
 
 382 
 
 573 
 
 .^35 
 .652 
 .870 
 1.087 
 
 .435 
 .652 
 .870 
 1.087 
 
 .^35 
 .652 
 .870 
 1.087 
 
 dollars 
 
 21 
 
 17 
 
 28 
 
 37 
 
 47 
 
 7 
 
 19 
 
 16 
 
 25 
 
 33 
 
 50 
 
 6 
 
 19 
 
 15 
 
 2k 
 
 32 
 
 48 
 
 6 
 
 19 
 
 16 
 
 25 
 
 33 
 
 50 
 
 6 
 
 43 
 
 35 
 
 kl 
 
 56 
 
 84 
 
 10 
 
 36 
 
 29 
 
 k3 
 
 64 
 
 85 
 
 10 
 
 32 
 
 26 
 
 47 
 
 56 
 
 84 
 
 10 
 
 30 
 
 25 
 
 ^3 
 
 61 
 
 86 
 
 9 
 
 64 
 
 52 
 
 57 
 
 90 
 
 124 
 
 12 
 
 54 
 
 kk 
 
 60 
 
 84 
 
 120 
 
 13 
 
 hi 
 
 38 
 
 62 
 
 82 
 
 113 
 
 13 
 
 kk 
 
 36 
 
 58 
 
 87 
 
 116 
 
 12 
 
 8 
 8 
 
 7 
 8 
 
 12 
 
 13 
 12 
 12 
 
 18 
 17 
 17 
 17 
 
 10 
 
 73 
 
 83 
 
 95 
 
 10 
 
 66 
 
 76 
 
 95 
 
 10 
 
 64 
 
 73 
 
 92 
 
 10 
 
 66 
 
 76 
 
 95 
 
 17 
 
 135 
 
 146 
 
 179 
 
 17 
 
 118 
 
 142 
 
 167 
 
 17 
 
 115 
 
 126 
 
 159 
 
 17 
 
 107 
 
 128 
 
 158 
 
 24 
 
 185 
 
 224 
 
 264 
 
 24 
 
 171 
 
 199 
 
 242 
 
 22 
 
 160 
 
 184 
 
 220 
 
 23 
 
 150 
 
 184 
 
 219 
 
TABLE 1U 
 
 Annual Fixed Costs of Lettuce Harvesting Equipment with Varying Daily Outputs, 
 Harvest Densities, and Round-Trip Distances from Field to Plant 
 Salinas District, California, 1953-51* 
 
 
 Harvest 
 density, 
 
 
 
 Equipment item 
 
 
 
 
 
 
 
 Output, 
 baskets 
 
 baskets 
 
 
 
 Trucks 
 
 Trailers 
 
 
 Total 
 
 
 per 1,000 
 feet of 
 
 Loaders 
 
 Tractors 
 
 Round-trip distance, 
 miles 
 
 Round- trip distance, 
 miles 
 
 Round-trip distance, 
 miles 
 
 per day 
 
 bed 
 
 5 
 
 20 
 
 1*0 
 
 5 
 
 20 
 
 1*0 
 
 5 
 
 20 
 
 JiO 
 
 
 
 dollars 
 
 191 
 
 .652 
 .870 
 1.087 
 
 3,628 
 3,628 
 3,628 
 3,628 
 
 2,598 
 2,598 
 2,598 
 2,598 
 
 U,902 
 I*, 902 
 U,902 
 1*,902 
 
 6,536 
 6,536 
 6,536 
 6,536 
 
 8,170 
 9,80l* 
 9,80l* 
 9,801* 
 
 2,116 
 2,116 
 2,116 
 2,116 
 
 2,615 
 2,61*5 
 2,61*5 
 2,61*5 
 
 3,171 
 3,703 
 3,703 
 3,703 
 
 13,21*1* 
 13,210* 
 13,21*1* 
 13,2UU 
 
 1 
 
 15,1*07 
 15,1*07 
 15,1*07 
 15,1*07 
 
 17,570 
 19,733 
 19,733 
 19,733 
 
 382 
 
 .1*35 
 .652 
 .870 
 1.087 
 
 7,256 
 5,14*2 
 5,1*1*2 
 5,1*1*2 
 
 5,196 
 3,897 
 3,897 
 3,897 
 
 8,170 
 6,536 
 8,170 
 8,170 
 
 9,8ol* 
 9,801* 
 9,801* 
 11,1*38 
 
 11*, 706 
 13,072 
 1U,706 
 16,3U0 
 
 3,171* 
 2,61*5 
 3,171* 
 3,171* 
 
 3,703 
 3,703 
 3,703 
 1*,232 
 
 5,290 
 U,76l 
 5,290 
 5,819 
 
 23,796 
 13,520 
 20,683 
 20,683 
 
 2$ t 9S9 
 22, 81*6 
 22,8U6 
 25,009 
 
 32,1*1*8 
 
 27,172 
 
 29,335 
 31,1*98 
 
 573 
 
 .1*35 
 .652 
 .870 
 1.087 
 
 9,070 
 7,256 
 7,256 
 7,256 
 
 6,1*95 
 5,196 
 5,196 
 5,196 
 
 8,170 
 8,170 
 9,80U 
 9,80U 
 
 13,072 
 11,1*38 
 13,072 
 lit, 706 
 
 17,971* 
 16,3U0 
 17,97U 
 19,608 
 
 3,171* 
 3,17U 
 3,703 
 3,703 
 
 l*,76l 
 it, 232 
 U,76l 
 5,290 
 
 6,31*8 
 5,819 
 6,3U8 
 6,877 
 
 26,909 
 23,796 
 2$ t 9$9 
 2$,9S9 
 
 33,39Q 
 28,122 
 30,285 
 32,1*1*8 
 
 39,887 
 31*, 611 
 36,771* 
 38,937 
 
 i 
 
*9. 
 
 COMBINED PACKING HOUSE AND HARVEST ING -HAULING COSTS 
 
 Total Variable Costs Per Day 
 
 Table 15 presents total variable packing plant and field harvesting-hauling 
 costs per day in relation to plant output per day, round-trip distance from field 
 to plant, and harvest density. These costs were derived from those presented in 
 earlier sections. It is clear from the table that, for any given output per day 
 and distance from field to plant, variations in variable costs arise largely from 
 variations in harvest density. With, for example, an output per day of 1,680 
 crates and a round-trip distance of 5 miles, total variable costs decrease from 
 02,857 to 02,770 ($87) as harvest density increases from .U35 to 1.087 baskets 
 per 1,000 feet of bed. On the other hand, as round- trip distance from field to 
 plant increases, variable costs increase. For example, with an output of 3,360 
 crates per day and a harvest density of .1|35 baskets per 1,000 feet of bed, costs 
 increase from s 05,535 to 05,628 (093) as round-trip distance increases from 5 to 
 k0 miles. Further, while variable costs increase with increases in daily output, 
 they do so in less than direct proportion. For example— with a round-trip dis- 
 tance of 5 miles, a harvest density of .135 baskets per 1,000 feet of bed, and 
 outputs of 1,680, 3,360, and 5,0UO crates per day— variable costs are $2,857, 
 05,535, and 08,235, respectively. As compared with the small plant, costs in 
 the medium-sized one are approximately 1.9U times as great (with an output twice 
 as large) and in the large plant 2.88 times as great (xri.th an output three times 
 as large). This less than proportional increase in variable costs is the result 
 of a more efficient utilization of labor and other variable inputs as scale of 
 operation increases. As will be seen in a later section, this has important ef- 
 fects on average cost per unit of output. 
 
 Annual Fixed Costs 
 
 Table 16 shows the annual fixed costs of harvesting-hauling and plant opera- 
 tions in relation to output per day, round-trip distance from field to plant, and 
 harvest density. The dominant factors affecting these costs are apparently dis- 
 tance from field to plant and plant output per day. The effects of harvest 
 density are somewhat less pronounced than they were in the case of daily vari- 
 able costs. For example, with a plant output of 1,680 crates per day and 
 
TABLE 15 
 
 50. 
 
 Total Variable Lettuce Harvesting- Hauling and Packing Plant Costs 
 Per Day as Related to Output Per Day, Round-Trip Distance 
 from Field to Plant, and Harvest Density 
 Salinas District, California, 1954 
 
 Output, 
 crates 
 
 Round- 
 trip 
 distance, 
 
 Harvest 
 density, 
 baskets per 
 
 Labor 
 
 Equipment 
 
 Packing 
 materials 
 
 Total 
 per day 
 
 per , 
 dayl' 
 
 field to 
 plant 
 
 1,000 feet 
 of bed}*/ 
 
 Harvest - 
 hauling 
 
 Plant 
 
 Harvest - 
 hauling 
 
 Plant 
 
 and 
 
 supplies 
 
 
 miles 
 
 
 dollars 
 
 
 5 
 
 .435 
 .652 
 .870 
 I.087 
 
 363 
 319 
 291 
 283 
 
 942 
 
 73 
 66 
 64 
 66 
 
 31 
 
 1,448 
 
 2,857 
 2,806 
 2,776 
 2,770 
 
 1,680 
 
 20 
 
 .435 
 .652 
 .870 
 1.087 
 
 375 
 330 
 301 
 294 
 
 942 
 
 83 
 76 
 73 
 76 
 
 31 
 
 1,448 
 
 2,879 
 2,827 
 2,795 
 2,791 
 
 
 40 
 
 .435 
 .652 
 .870 
 I.087 
 
 388 
 352 
 322 
 316 
 
 942 
 
 95 
 95 
 92 
 95 
 
 31 
 
 1,448 
 
 2,904 
 2,868 
 
 2,835 
 2,832 
 
 
 5 
 
 .435 
 .652 
 .870 
 I.087 
 
 709 
 627 
 558 
 519 
 
 1,746 
 
 135 
 118 
 
 115 
 107 
 
 49 
 
 2,896 
 
 5,535 
 5,436 
 5,364 
 5,317 
 
 3,360 
 
 20 
 
 .435 
 .652 
 .870 
 I.087 
 
 721 
 655 
 570 
 s42 
 
 1,746 
 
 146 
 142 
 126 
 128 
 
 49 
 
 2,896 
 
 5,558 
 5,488 
 5,387 
 5,361 
 
 
 40 
 
 .435 
 .652 
 .870 
 I.087 
 
 758 
 
 684 
 607 
 576 
 
 1,746 
 
 179 
 167 
 159 
 158 
 
 49 
 
 2,896 
 
 5,628 
 5,542 
 5,457 
 5,425 
 
 
 5 
 
 .435 
 .652 
 .870 
 1*087 
 
 1,080 
 926 
 803 
 749 
 
 2,559 
 
 185 
 171 
 160 
 150 
 
 67 
 
 4,344 
 
 8,235 
 8,067 
 7,933 
 7,869 
 
 | 5,040 
 
 20 
 
 .435 
 
 .652 
 .870 
 1.087 
 
 1,126 
 
 959 
 830 
 
 787 
 
 2,559 
 
 224 
 
 199 
 184 
 184 
 
 67 
 
 4,344 
 
 8,320 
 8,128 
 7,984 
 7,941 
 
 
 40 
 
 .435 
 .652 
 .870 
 1.087 
 
 1,172 
 1,009 
 871 
 825 
 
 2,559 
 
 264 
 242 
 220 
 219 
 
 67 
 
 4,344 
 
 8,406 
 8,221 
 8,061 
 8,014 
 
 (Continued on next page.) 
 
■id fit -rri '-f-. ■: 
 
 ■ 
 
 >ll«Fc'.XC 
 
 Bo 
 
 — i 
 
51. 
 
 Table 15 continued. 
 
 a/ Output in crates packed per day is determined by multiplying respective 
 plant capacity rates of output per hour of 210, k20, and 630 crates by 8, 
 the length of packing plant workday assumed in this analysis. Daily out- 
 put rates of 1,680, 3,360, and 5,0^0 crates are the equivalent of 191, 382, 
 and 573 baskets, respectively, where the packout per basket is 8.8 crates. 
 Each crate contains approximately 70 pounds of lettuce. 
 
 b/ At an average packout of 8.8 crates per basket, harvest densities of .^35, 
 ~ .652, .870, and I.087 baskets per 1,000 feet of bed are equivalent to 50, 
 75, 100, and 125 crates per acre, respectively. 
 
ill 
 
TABLE 16 
 
 Annual Fixed Costs of Harvesting-Hau ling and Packing Lettuce as 
 Related to Plant Output Per Day, Round-Trip Distance 
 from Field to Plant, and Harvest Density 
 Salinas District, California, 195*+ 
 
 UU opuk , 
 
 crates 
 packed 
 
 per 
 
 day£/ 
 
 Round -trip 
 distance, 
 field to 
 plant 
 
 Hai've st 
 density, 
 baskets per 
 1,000 feet 
 of bed*y 
 
 Harvest- 
 hauling 
 
 Plant 
 
 Total 
 
 
 
 
 dollars 
 
 
 5 
 
 .1+35 
 .652 
 .870 
 1.087 
 
 13,2l+l+ 
 13,21+1+ 
 13,21+1+ 
 13,21+1+ 
 
 7,11+1 
 
 20,385 
 20,385 
 20,385 
 20,385 
 
 1,680 
 
 20 
 
 .1+35 
 .652 
 .870 
 1.087 
 
 15,*+07 
 15,1+07 
 15,1+07 
 15,to7 
 
 7,11+1 
 
 22,51+8 
 22,5*+S 
 22, 5I+8 
 22,51+8 
 
 
 1+0 
 
 .1+35 
 .652 
 .870 
 I.087 
 
 17, 570 
 19,733 
 19,733 
 19,733 
 
 7,1^1 
 
 2l+,711 
 26,874 
 26,871+ 
 26,874 
 
 
 5 
 
 .1+35 
 .652 
 .870 
 1.087 
 
 23,795 
 18, 520 
 20,633 
 20,683 
 
 11,622 
 
 35,*+l8 
 30,11+2 
 
 32,305 
 32,305 
 
 3,360 
 
 20 
 
 .1+35 
 .652 
 .870 
 1.087 
 
 25,959 
 22,81+6 
 22,81+6 
 
 25,009 
 
 11,622 
 
 37, 581 
 3l+,l+68 
 3l+,l+68 
 36,631 
 
 
 1+0 
 
 .1+35 
 .652 
 .870 
 1.087 
 
 32,1+1+3 
 37,172 
 29,335 
 31,1+98 
 
 11,622 
 
 1+1+,070 
 1+8, 79*+ 
 1+0,957 
 1+3,120 
 
 
 5 
 
 .1+35 
 .652 
 .870 
 1.087 
 
 26,909 
 23,796 
 25,959 
 25,959 
 
 15,988 
 
 1+2,897 
 39,781+ 
 41,947 
 4l,9i+7 
 
 5,0U0 
 
 20 
 
 .1+35 
 .652 
 .870 
 1.087 
 
 33,398 
 28,122 
 30,285 
 
 32,1+1+8 
 
 15,988 
 
 1+9,386 
 l+l+,110 
 
 46,273 
 1+8,1+36 
 
 
 1+0 
 
 .1+35 
 .652 
 .870 
 1.087 
 
 39,837 
 3i+,6ll 
 36,774 
 38,937 
 
 15,988 
 
 55,875 
 50,599 
 52,762 
 
 54,925 
 
 (Continued on next page.) 
 
ovs. 
 
53. 
 
 Table 16 continued. 
 
 a/ Output in crates packed per day is determined by multiplying respective 
 ~ plant capacity rates of output per hour of 210, 1*20, and 6^0 crates by 8, 
 the length of packing plant workday assumed in this analysis. Daily output 
 rates of 1,680, 3,560, and 5,0U0 crates are the equivalent of 191, 382, and 
 573 baskets, respectively, where the packout per basket is 8.8 crates. Each 
 crate contains approximately 70 pounds of lettuce. 
 
 b/ At an average packout of 8.8 crates per basket, harvest densities of 
 
 .652, .870, and I.087 baskets per 1,000 feet of bed are equivalent to 50, 
 75, 100, and 125 crates per acre, respectively. 
 
a round-trip distance of 5 miles, fixed costs are the same for all levels of 
 harvest density. On the other hand, with the same output per day--but with dis- 
 tance increasing from 5 to Uo miles--annual fixed costs increase from $20,585 
 to $24,711 ($4,526). Similarly, with a round-trip distance of 5 miles and a 
 harvest density of .455 baskets per 1,000 feet of bed, costs with outputs of 
 1,680, 3,560, and 5,01*0 crates per day are $20,385, $55,4l8, and $42,897- As 
 in the case of variable costs, these costs increase in less than direct propor- 
 tion to output. For example, fixed costs in the medium-sized plant as compared 
 with the small plant at the above -specified distance and harvest density are 
 approximately 1.74 times as great (with output twice as large) and in the large 
 plant 2.10 times as great (with output three times as large). 
 
 Total Season Costs and Total Costs Per Packed Crate 
 
 Total costs per season for the harvesting-hauling and packing plant op- 
 erations are estimated as the annual fixed costs given in Table 16, plus total 
 variable costs per season obtained by multiplying variable costs per day given 
 in Table 15 by l6o— the length of season selected for the Salinas district. To- 
 tal season costs estimated in this way are given in Table 17. In the smallest 
 plant--none of which were actually observed in operation- -total estimated sea- 
 son costs are almost $500,000 when all costs are considered and in the medium- 
 sized plant—the most common in Salinas --nearly $1,000,000. 
 
 Total costs per packed crate are computed by dividing total season costs 
 (Table 17) by total season volume. » These costs are given in relation to op- 
 erating conditions and daily output^ in plants of three different capacity 
 rates in Table 18 and shown in Figure 12. The table shows that plant costs 
 vary only with size of plant; harvesting and hauling costs, however, are af- 
 fected not only by this factor but also by harvest density and distance from 
 field to plant. For example, with a daily output of 5,560 crates and a round- 
 trip distance of 20 miles, harvesting and hauling costs decrease from 50.6 
 cents to 24.6 cents per crate (6 cents) as harvest density varies from .1+55 to 
 I.O87 baskets per 1,000 feet of bed, and plant costs remain constant at $1.4l8 
 
 1/ For plants with daily outputs of 1,680 , 5,560, and 5,040 crates, total 
 season outputs would be 268,800, 557,600, and 806,400 crates, respectively. 
 
 2/ Daily output is determined by multiplying the capacity rate of output 
 per~hour by the eight-hour workday. 
 
55. 
 
 TABLE 17 
 
 Total Season Cost of Harvesting-Hauling and Packing Lettuce as 
 Related to Plant Output Per Day, Round-Trip Distance 
 from Field to Plant, and Harvest Density 
 Salinas District, California, 1954 
 
 Output, 
 crates 
 packed 
 per 
 dayg/ 
 
 1,680 
 
 5,560 
 
 Round- 
 trip 
 distance, 
 field to 
 plant 
 
 miles 
 
 20 
 
 4o 
 
 20 
 
 4o 
 
 20 
 
 4o 
 
 Harvest 
 density, 
 baskets 
 per 1,000 
 feet of 
 bedV 
 
 .455 
 .652 
 .870 
 I.087 
 
 .455 
 .652 
 .870 
 I.087 
 
 .455 
 .652 
 .870 
 I.087 
 
 .455 
 .652 
 .870 
 1.087 
 
 .455 
 .652 
 .870 
 1.087 
 
 .435 
 .652 
 .870 
 1.087 
 
 .455 
 .652 
 .870 
 1.087 
 
 .455 
 .652 
 .870 
 1.087 
 
 .455 
 .652 
 .870 
 1.087 
 
 Harvesting and 
 hauling costs 
 
 Vari- 
 able 
 
 Fixed 
 
 Total 
 
 Plant costs 
 
 Vari- 
 able 
 
 Fixed 
 
 Total 
 
 Total 
 
 season 
 
 costs 
 
 69.8 
 61.6 
 56.8 
 55.8 
 
 75-5 
 65.O 
 59-8 
 59-2 
 
 77.3 
 71.5 
 66.2 
 65.8 
 
 135.0 
 119.2 
 
 107.7 
 100.2 
 
 138.7 
 127.5 
 111.4 
 107.2 
 
 149-9 
 156.2 
 122.6 
 117.4 
 
 202. k 
 175.5 
 154.1 
 143.8 
 
 216.0 
 185.3 
 3.62.2 
 155.4 
 
 229.8 
 200.2 
 174.6 
 167.0 
 
 13.2 
 13.2 
 13-2 
 13.2 
 
 15.4 
 15.4 
 15.4 
 15.4 
 
 17.6 
 19.7 
 19-7 
 19.7 
 
 23.8 
 18.5 
 20.7 
 20.7 
 
 26.0 
 22.8 
 22.8 
 25.0 
 
 52.4 
 37.2 
 29.3 
 31.5 
 
 26.9 
 23.8 
 26.0 
 26.0 
 
 33.4 
 28.1 
 
 30.3 
 32.4 
 
 39.9 
 34.6 
 36.8 
 38.9 
 
 1,000 dollars 
 
 83.O 
 74.8 
 70.0 
 69.O 
 
 88.7 
 80.4 
 75-2 
 74.6 
 
 94.9 
 91.2 
 
 85.9 
 85.5 
 
 158.8 
 
 137.7 
 128.4 
 120.9 
 
 164.7 
 
 150.3 
 134.2 
 132.2 
 
 182.3 
 173.4 
 151.9 
 148.9 
 
 229.3 
 199.3 
 180.1 
 169.8 
 
 249.4 
 213.4 
 
 192.5 
 187.8 
 
 269.7 
 234.8 
 211.4 
 205-9 
 
 387.4 
 387.4 
 387.4 
 387.4 
 
 387.4 
 387.4 
 387.4 
 387.4 
 
 387.4 
 387.4 
 387.4 
 387.4 
 
 750.6 
 750.6 
 750.6 
 750.6 
 
 750.0 
 750.6 
 750.6 
 750.6 
 
 750.6 
 750.6 
 750.6 
 750.6 
 
 1,115.2 
 1,115.2 
 1,115.2 
 1,115.2 
 
 1,115.2 
 1,115.2 
 1,115.2 
 1,115.2 
 
 1,115.2 
 1,115.2 
 1,115.2 
 
 1,115.2 
 
 7.1 
 7.1 
 7.1 
 7.1 
 
 7.1 
 7.1 
 7.1 
 7.1 
 
 7.1 
 7.1 
 7.1 
 7.1 
 
 11.6 
 11.6 
 11.6 
 11.6 
 
 11.6 
 11.6 
 11.6 
 11.6 
 
 11.6 
 11.6 
 11.6 
 11.6 
 
 16.0 
 16.0 
 16.0 
 
 394.5 
 394.5 
 394.5 
 394.5 
 
 394.5 
 394.5 
 394.5 
 394.5 
 
 394.5 
 394.5 
 394.5 
 394.5 
 
 762.2 
 762.2 
 762.2 
 762.2 
 
 762.2 
 762.2 
 762.2 
 762.2 
 
 762.2 
 762.2 
 762.2 
 762.2 
 
 1,131.2 
 1,131.2 
 1,131.2 
 
 16.0 1,131.2 
 
 16.0 
 16.0 
 16.0 
 16.0 
 
 16.0 
 16.0 
 16.O 
 16.0 
 
 1,131.2 
 1,151.2 
 1,131.2 
 1,131.2 
 
 1,131.2 
 1,131.2 
 1,131.2 
 1,131.2 
 
 477.5 
 469-3 
 464.5 
 465.5 
 
 485.2 
 474.9 
 469-7 
 469.1 
 
 489.4 
 
 435.7 
 480.4 
 480.0 
 
 921.0 
 
 899.9 
 890.6 
 
 885.I 
 
 926,9 
 912.5 
 896.4 
 894.4 
 
 944.5 
 955.6 
 914.1 
 911.1 
 
 1,560.5 
 1,550.5 
 1,511-5 
 1,501.0 
 
 1,580.6 
 1,544.6 
 1,525.7 
 1,519.0 
 
 1,400.9 
 1,366.0 
 1,342.6 
 i,557.i; 
 
 (Continued on next page.) 
 
1 
 
 t xp.y« 
 
56. 
 
 Table 17 continued. 
 
 a/ Output in crates packed per day is determined by multiplying respective 
 plant capacity rates of output per hour of 210, k20, and 6j0 crates by 3, 
 the length of packing plant workday assumed in this analysis. Daily output 
 rates of 1,680, 3,360, and 5,0to crates are the equivalent of 191 ; 532, and 
 573 baskets, respectively, where the packout per basket is 8.8 crates. Each 
 crate contains approximately 70 pounds of lettuce. 
 
 b/ At an average packout of 8.8 crates per basket, harvest densities of .*+35> 
 .652, .870, and I.O87 baskets per 1,000 feet of bed are equivalent to 50, 
 75> 100, and 125 crates per acre, respectively. 
 
jMHSEp 
 
TABLE 18 
 
 57. 
 
 Total Costs Per Crate of Harvesting-Hauling and Packing Head 
 Lettuce as Related to Plant Output Per Day, Round-Trip 
 Distance from Field to Plant, and Harvest Density 
 Salinas District, California, 1954 
 
 Output , 
 
 crates 
 
 packed 
 
 Round- 
 trip 
 distance, 
 
 Harvest 
 densitv. 
 baskets 
 per 1,000 
 
 Harvesting and 
 hauling costs 
 
 Plant costs 
 
 
 per 
 day&/ 
 
 field to 
 plant 
 
 feet of 
 bed?./ 
 
 Vari- 
 able 
 
 Fixed 
 
 Total 
 
 Vari- 
 able 
 
 Fixed 
 
 Total 
 
 Total 
 
 
 miles 
 
 
 dollars 
 
 
 
 5 
 
 .^35 
 , .652 
 I .870 
 I.087 
 
 .260 
 .229 
 .211 
 .208 
 
 .0^9 
 .0U9 
 .01+9 
 .01+9 
 
 .309 
 .278 
 .260 
 .257 
 
 1.1+1+1 
 1.1+1+1 
 1.1*1 
 1.1+1+1 
 
 .027 
 .027 
 .027 
 .027 
 
 1.1+68 
 1.1+68 
 1.1+68 
 1.1*68 
 
 1.777 
 L.746 
 1.728 
 1.725 
 
 1,680 
 
 
 20 
 
 f .^35 
 .652 
 | .870 
 , I.O87 
 
 .273 
 .2*42 
 .223 
 .220 
 
 .057 
 .057 
 .057 
 .057 
 
 • 330 
 
 • 299 
 .280 
 
 .277 
 
 1.1+1+1 
 l.l+l+l 
 1.1+1+1 
 1.1+1+1 
 
 .027 
 .027 
 .027 
 .027 
 
 1.1+68 
 1.1*68 
 1.1*68 
 1.1*68 
 
 1.798 
 1.767 
 l.Tl+8 
 1.7^5 
 
 
 
 1*0 
 
 ' .^35 
 , .652 
 .870 
 , 1.087 
 
 .288 
 .266 
 .246 
 ,2k5 
 
 .065 
 .073 
 .073 
 .073 
 
 .353 
 .339 
 .319 
 .318 
 
 1.1+1+1 
 1.1+1+1 
 
 l.k-'l 
 1.1+1+1 
 
 .027 
 .027 
 .027 
 .027 
 
 1.1*68 
 1.1+68 
 1.1+68 
 1.1*68 
 
 1.821 
 1.807 
 1.787 
 1.786 
 
 
 
 5 
 
 f .435 
 J .652 
 1 .870 
 
 1 1.087 
 
 .251 
 .222 
 .200 
 .186 
 
 .01+1+ 
 
 .03 l + 
 .038 
 .038 
 
 .295 
 .256 
 .238 
 .221+ 
 
 1.396 
 1.396 
 1.396 
 1.396 
 
 .022 
 .022 
 .022 
 .022 
 
 1.1+18 
 1.1+18 
 1.1+18 
 1.1*18 
 
 1.713 
 1.674 
 I.656 
 1.642 
 
 3,360 
 
 < 
 
 20 
 
 f .435 
 .652 
 
 .870 
 . 1.087 
 
 .258 
 .237 
 .207 
 .199 
 
 .01+8 
 .01+2 
 .01+2 
 .01+7 
 
 .306 
 .279 
 .21+9 
 .21+6 
 
 1.396 
 1.396 
 1.396 
 1.396 
 
 .022 
 .022 
 .022 
 .022 
 
 1.1*18 
 1.1*18 
 1.1+18 
 1.1+18 
 
 1.721+ 
 1.697 
 1.667 
 1.661+ 
 
 
 
 1*0 
 
 h 
 
 J .652 
 
 1 870 
 1 1.087 
 
 .279 
 .253 
 .228 
 .218 
 
 .060 
 .069 
 .055 
 .059 
 
 •339 
 .322 
 .283 
 .277 
 
 1.396 
 1.396 
 1.396 
 1.396 
 
 .022 
 .022 
 .022 
 .022 
 
 1.1*18 
 1.1+18 
 I.1+18 
 1.1+18 
 
 1.757 
 1.740 
 1.701 
 1.695 
 
 
 
 t 
 
 5 
 
 ' ^35 
 d .652 
 1 .870 
 
 i nft7 
 
 . i. .UO ( 
 
 .251 
 .218 
 
 .191 
 .178 
 
 .033 
 .030 
 .032 
 .032 
 
 .281+ 
 .21+8 
 
 .223 
 .210 
 
 1.383 
 1.383 
 1.383 
 1.383 
 
 .020 
 .020 
 .020 
 .020 
 
 1.1*03 
 1.1*03 
 I.1+03 
 1.1+03 
 
 1.687 
 I.651 
 I.626 
 1.613 
 
 5,040 
 
 < 
 
 20 
 
 .435 
 I .652 
 .870 
 „ 1.087 
 
 .268 
 .230 
 .201 
 .193 
 
 .Cl+1 
 
 .035 
 .038 
 .01+0 
 
 .309 
 .265 
 .239 
 .233 
 
 1.383 
 1.383 
 1.383 
 1.383 
 
 .020 
 .020 
 .020 
 .020 
 
 1.1*03 
 1.1+03 
 1.1+03 
 1.1*03 
 
 1.712 
 1.668 
 1.642 
 I.636 
 
 
 1 
 
 4o 
 
 , .652 
 .870 
 . I.087 
 
 .285 
 .248 
 .216 
 .207 
 
 .01+9 
 .01+3 
 .01+6 
 
 .01+8 
 
 • 33^ 
 .291 
 .262 
 .255 
 
 1.383 
 1.383 
 1.383 
 1.383 
 
 .020 
 .020 
 .020 
 .020 
 
 I.1+03 
 1.1*03 
 1.1*03 
 1.1*03 
 
 1.737 
 1.694 
 1.665 
 1.658 
 
 (continued on next page.) 
 
* 
 
 1 
 
 l_- 
 
58. 
 
 Table 18 continued. 
 
 a/ Output in crates packed per day is determined by multiplying respective 
 plant capacity rates of output per hour of 210, ^20, and 63O crates by 8, 
 the length of packing plant workday assumed in this analysis. Daily output 
 rates of 1,680, 5,360, and 5,0k0 crates are the equivalent of 191, 382, and 
 573 baskets, respectively, where the packout per basket is 8.8 crates. Each 
 crate contains approximately 70 pounds of lettuce. 
 
 b/ At an average packout of 8.8 crates per basket, harvest densities of .^35, 
 .652, .870, and I.O87 baskets per 1,000 feet of bed are equivalent to 50, 
 75> 100, and 125 crates per acre, respectively. 
 
■ 
 
59- 
 
 < 
 cc 
 
 o 
 
 cc 
 ui 
 
 CL 
 
 H 
 
 V) 
 
 o 
 o 
 
 < 
 i- 
 o 
 
 1.80 
 1.75 
 1.70 
 1.65 
 1.60 
 
 1 
 
 — 
 
 1 1 1 1 1 
 
 ROUND TRIP DISTANCE ■ 
 
 1 1 1 1 
 5 MILES 
 
 — 
 
 
 
 HARVEST 
 
 
 
 ^ DENSITY 
 
 
 
 * .435 
 
 
 
 .652 — 
 
 
 
 --C^ .870 
 
 1 1 
 
 1 1 1 1 1 1 
 
 1.087 _ 
 
 III! 
 
 1.0 
 
 2.0 
 
 3.0 
 
 4.0 
 
 50 
 
 6.0 
 
 £ (.8 0 
 
 cc 
 
 o 
 
 IT 
 UI 
 0. 
 
 H 
 
 en 
 o 
 o 
 
 < 
 i- 
 
 o 
 
 1.75 f- 
 1.70 
 1.65 
 1.60 
 0 
 
 ROUND TRIP DISTANCE - 20 MILES 
 
 HARVEST 
 DENSITY 
 .435 
 
 1.0 
 
 20 
 
 3.0 
 
 4.0 
 
 5.0 
 
 6.0 
 
 ui 180 
 cc 
 
 o 1.75 
 
 DC 
 UI 
 
 °- 1.70 
 l- 
 
 cn 
 
 o 165 
 < 
 
 o l-«0 
 
 1 
 
 1 > 1 ! 1 ' 
 
 v^ROUND TRIP DISTANCE 
 
 1 1 1 1 
 - 40 MILES 
 
 
 
 HARVEST 
 
 
 
 DENSITY 
 
 
 
 — .435 ~~ 
 
 
 
 *"*"-*■ .652 ~ 
 
 
 
 ^ = =^—— _ 870 
 
 
 
 1.087 - 
 
 h 1 
 
 1 1 1 1 1 1 
 
 
 1.0 2.0 3.0 4.0 5.0 
 
 OUTPUT PER DAY - 1000 CRATES 
 
 6.0 
 
 Figure 12. Total Costs Per Crate of Harvesting, Hauling, 
 and Packing Head Lettuce as Related to Plant 
 Output Per Day, Round-Trip Distance from Field 
 to Plant, and Harvest Density, Salinas Dis- 
 trict, 1953-5U. 
 
6o. 
 
 per crate. Total costs per crate decrease from $1,742 to $1,661*. on a season 
 basis this difference amounts to $32,500. It is clear from Figure 11 that the 
 rate of this decrease is smaller at high than at lov harvest densities. For 
 example, as harvest density increases from .1*35 to .652 baskets per 1,000 feet, 
 costs decrease about 2.5 cents per crate as compared to only about .5 cent per 
 crate with the same increment in harvest density in the range of .870 to 1.037 
 baskets per 1,000 feet. Conversely, with an output of 3,360 crates per day 
 and a given level of harvest density— for example, .652 baskets per 1,000 feet- 
 harvesting and hauling costs increase from 25.6 to 32.2 cents (6.6 cents), as 
 round-trip distance increases from 5 to 1*0 miles; plant costs remain at $1,418; 
 and total costs per crate increase from $1,671* to $1.7^. This would mean 
 that, if one firm continuously carried on its field operations at a distance 
 from the plant of 2| miles while another operated at a 20-mile distance, the 
 difference in harvesting and packing costs per season between the two firms 
 would be $35,600. 
 
 As size of plant increases, both harvesting and hauling and plant costs 
 decrease. For example, with a round-trip distance of 5 miles and a harvest 
 density of .870 baskets per 1,000 feet of bed, harvesting and hauling costs de- 
 crease from 26.0 cents to 23-9 cents (2.1 cents) and plant costs decrease from 
 $1.1*86 to $1.1*18 (5 cents) as daily output increases from 1,680 to 3,360 crates; 
 total costs per crate decrease from $1,728 to $1,657 (7-1 cents). As daily 
 output increases from 3,360 to 5,0l*0 crates, harvesting and hauling costs per 
 crate decrease from 23.9 cents to 22.3 cents (1.6 cents) and plant costs from 
 $1.1*18 to $l.lK)3 (1.5 cents). Total costs per crate decrease from $1,657 to 
 
 $1,626 (3.1 cents). 
 
 These comparisons indicate that a large portion of the savings possible 
 with large-scale operation is achieved in the medium-sized plant— the most 
 common in the Salinas district— and the curves in Figure 11 show that nearly 
 all such savings would be accomplished in plants of the largest size considered 
 (63O -crate -per-hour capacity) . 
 
 IMPLICATION OF RESULTS TO THE PRESENT SITUATION 
 IN THE SALINAS DISTRICT 
 
 The preceding analysis illustrates the economies possible with the opera 
 tion of large-scale lettuce packing plants. Since 1952, however, the demand 
 for ice -packed lettuce has rapidly diminished. In 1956, for example, only 
 
• - ; : ; : • ■ . 
 
 if, - ."- ' ■ ■ 
 
 i :.vir.' 
 
 ci do 
 
 0 ttM&O 
 
61. 
 
 1,528 cars— as compared to over 30,000 cars in 1952— were ice packed in the 
 Salinas district. This declining volume raises questions as to the practica- 
 bility of large-scale operation. Even prior to the shift away from ice pack- 
 ing, the variation in seasonal distribution of lettuce shipments had contributed 
 to considerable excess packing plant capacity in the industry, and the present 
 low total season volume has greatly increased this excess capacity. The dis- 
 tribution of these ice-packed shipments from the Salinas district in 19S>6 is 
 shown in Figure 13. The heaviest volume occurred in the months April through 
 July reaching a maximum of 387 cars in May and decreasing thereafter. 
 
 A major problem in the existing situation is how to organize existing and 
 surplus facilities most economically. Some guides are available from the pre- 
 ceding cost analysis, although several adjustments in the final results are 
 appropriate. The preceding analysis would be of interest to those individuals 
 planning the construction of new or the modification of old facilities. In 
 this case it is necessary to consider both variable and fixed costs. Since the 
 immediate problem in the Salinas district is not the construction of new plants 
 but rather the optimum utilization of existing packing facilities, an analysis 
 of alternative packing plant operations can ignore the effect of fixed costs, 
 and the problem can be considered in terms of variable costs only. The analysis 
 can be further simplified by considering only packing plant labor and supervi- 
 sion costs since the other variable costs would differ only slightly from those 
 presented earlier. For example, material and supply costs would be expected, 
 under present conditions, to be slightly higher than those shown previously 
 because of the smaller scale on which they are produced. This would tend to 
 shift costs upward by the amount of the increase, but it would not affect the 
 relative costs of alternative types of organization. Similarly, field harvest- 
 ing and hauling costs would probably approximate those shown earlier in regard 
 to small-scale operation since the fields from which lettuce is harvested for 
 ice packing would be too widely scattered to warrant large-scale field opera- 
 tions. Inclusion of these costs would merely tend to complicate the analysis 
 of alternative methods of packing plant operations while adding little to the 
 conclusions drawn. 
 
 The analysis that follows focuses on a comparison of plant labor and super- 
 vision costs assuming the entire Salinas district output of ice-packed lettuce 
 is processed in a single plant of either 1420-crate-per-hour capacity or in one 
 of 630-crate-per-hour capacity. Table 19 contains a summary of the distribution 
 of shipments of ice-packed lettuce by months from the Salinas district in 1956 
 
£0. QQfljftr. qs/.tv 
 
62. 
 
 400 — 
 
 {2 
 z 
 
 Ul 
 
 a. 
 
 300 
 
 to 
 
 < 200 
 
 i 
 
 H 
 Z 
 O 
 2 
 
 100 
 
 APRIL MAY JUNE JULY AUGUST SEPTEMBER 
 
 Figure 13. Distribution of Monthly Carlot Shipments of Ice-Packed 
 Lettuce, Salinas District, 1956. 
 
63. 
 
 TABLE 19 
 
 Monthly Distribution of Ice-Packed Shipments and Hours Worked and Estimated 
 Season Total and Per Crate Costs of Packing House Labor and Direct 
 Supervision in Plants of 1+20- and 630-Crate-Per-Hour Capacity 
 Salinas District, California, 1956 
 
 
 
 Monthly and total season hours 
 
 
 Monthly and 
 
 U20-crate-per-houi- 
 plant 
 
 630-crate-per-hour 
 plant 
 
 Item 
 
 crates packed 
 
 Regular 
 time 
 
 Over- 
 time 
 
 Regular 
 time 
 
 Over- 
 time 
 
 Month 
 
 
 
 
 
 
 April 
 
 97,920 
 
 176 
 
 £7 
 
 
 
 
 123. 81iO 
 
 18U 
 
 in 
 
 181+ 
 
 13 
 
 June 
 
 88,000 
 
 160 
 
 50 
 
 ll+O 
 
 
 July 
 
 71,360 
 
 170 
 
 
 113 
 
 
 August 
 
 1+8,000 
 
 lilt 
 
 
 76 
 
 
 September 
 
 1*0.000 
 
 95 
 
 
 6U 
 
 
 October 
 
 19,81+0 
 
 U7 
 
 
 31 
 
 
 Season total 
 
 1+88,960 
 
 9h6 
 
 218 
 
 763 
 
 13 
 
 Total season packing 
 house labor and direct 
 supervision costsfy 
 
 
 $277,5lU 
 
 $250,1+00 
 
 Packing house labor 
 and direct supervision 
 costs per crate 
 
 
 $0,568 
 
 $0,512 
 
 a/ Total season plant labor costs were computed by multiplying total labor costs 
 per hour (shown in Table 1 for the two sizes of plants) by the number of hours 
 worked. Costs for overtime hours were computed at 1§ times the rate for regu- 
 lar time hours. 
 
6U. 
 
 (previously shown in Figure 13) as well as an estimate of regular time and over- 
 time hours of plant operation per month for the two sizes of plants. Total sea- 
 son packing labor and supervision costs, shown in the table for the two plants, 
 were computed by multiplying total labor costs per hour (given in Table l) by 
 the total number of hours worked during the season e Costs of overtime hours 
 were computed at 1^ times the rate of regular time hours. Costs per crate were 
 obtained by dividing total season costs by the total season volume shown in the 
 table* 
 
 Table 19 indicates that the entire season's output could have been proc- 
 essed in 1,16U hours of operation in the U20-crate-capacity plant or, alter- 
 natively, in 776 hours in the 630-crate-capacity plant. These hours are based 
 on the assumption that each plant works at its capacity hourly rate of output. 
 In neither plant could the peak daily volume be packed in eight hours so some 
 overtime would be required. In the smaller plant, 218 hours of overtime per 
 season would be required as compared to only 13 overtime hours in the larger 
 plant. 
 
 The cost difference per crate between the U20- and 630-crate plants, shown 
 in Table 19, is approximately 6 cents. This difference arises largely from the 
 greater number of overtime hours worked in the smaller plant. In addition, 
 labor costs per crate in the 630-crate plant are lower than those in the It- 
 erate plant due to a more complete utilization of the labor force. 
 
 As was indicated previously, the above cost differences are based on the 
 assumption that the two sizes of plants are operated at their respective capacity 
 hourly rates of output throughout the season, With this assumption, variations 
 in daily output would be met by varying the number of hours worked . But varying 
 the number of hours worked creates certain problems with respect to the labor 
 force. For example, in Table 19 it is clear that, after the peak of the season, 
 the total number of plant hours worked per month continuously declines. This 
 would mean that fewer hours would be worked per month (or day) per worker as 
 the season progressed. This decline is especially pronounced in the case of 
 the plant of 630-crate-per-hour capacity. It would seem reasonable to suppose 
 that workers would resist excessive decline in hours worked because of its ef- 
 fect on their incomes. As a practical matter, therefore, it would probably be 
 impossible to operate at the capacity rate of output for the entire season. 
 
 An alternative to this would be to operate at or near the 630-crate-per- 
 hour capacity during the peak of the season but at lower rates of output per 
 hour as season volume decreases. This reduction in rate of output per hour 
 
65. 
 
 would be brought about by reducing the number of workers employed. Under these 
 conditions the average number of hours worked by those still employed could re- 
 main relatively constant. 
 
 Labor costs per crate with the above method of operation would be somewhat 
 higher than that shown for the 630-crate plant in Table 19 because the work time 
 of certain members of the crew-f or example, the lidder-would not be as com- 
 pletely utilized with the reduced hourly volume. Nevertheless, this method of 
 operation would still yield lower labor and supervision costs per crate than if 
 a similar method were used in a U20-crate-capacity plant. There would be no 
 change in the number of overtime hours worked in either plant (shown in Table 19), 
 and the reduced volume per hour as the season progressed would affect the costs 
 in the smaller plant in exactly the same way as it does in the larger plant. 
 
 Operation of more than a single packing plant under present conditions in 
 Salinas seems unwarranted. With several plants operating, the daily volume 
 processed through a particular plant could be quite irregular. Recruiting labor 
 under such conditions would be difficult. In addition, because of the low total 
 season district volume, season volume per plant would be lower than those pre- 
 viously discussed. Low volume per plant would undoubted?/ be associated with 
 low rates of plant output per hour. Under these conditions labor and supervi- 
 sion costs would be considerably higher than for the plant sizes discussed in 
 Table 19. 
 
 The consolidation of ice-packing operations of a number of producers into 
 a single plant raises a number of administrative problems. Questions of label- 
 ing, coordination of field and plant operations, and decisions as to whose let- 
 tuce and how much of it to pack in a given day require considerable administra- 
 tive skill. The costs of these added administrative responsibilities would have 
 to be weighed against the possible savings with a consolidated operation.