key: cord-1048674-v2depg74 authors: Peng, Junlong; Wang, Mengyao; Peng, Chao; Hu, Ke title: Research on extremely short construction period of engineering project based on labor balance under resource tolerance date: 2022-03-30 journal: PLoS One DOI: 10.1371/journal.pone.0266036 sha: e9ad7f68fe834615dc18b6b2874240fe07eb54ac doc_id: 1048674 cord_uid: v2depg74 Under the condition of resource tolerance, engineering construction projects face the problem of labor force balance in the working face. Notably, a deviation occurs between the distribution and certain demand of the labor force in the limited working face, which affects the realization of an extremely short construction period. To address this problem, we first introduced the stochastic coefficient of labor force equilibrium to measure the degree of labor balance. Second, a labor force equilibrium model with the realization goal of an extremely short construction period was established. Then, the standard particle swarm optimization (PSO) algorithm was improved from two perspectives to solve the proposed model. The update equation was rounded to solve practical project problems, and a dynamic variable inertia weight was adopted to ensure the PSO algorithm accuracy and convergence speed. Finally, through case analysis, we determined the extremely short construction period and best labor force distribution scheme. Moreover, the case results revealed that the established model is simple, operable and practical and that the proposed algorithm achieves a high search accuracy and efficiency in the model solution process. Overall, under the condition of resource tolerance, this study provides scientific and effective references for managers to realize an extremely short construction period. The construction period of engineering projects has always been considered an important research topic in the construction industry in China and abroad. In domestic engineering projects, the problem of the construction period has remained of great concern. In recent years, major emergencies have frequently occurred in China. Temporary rescue sites, road and bridge restoration, emergency hospitals and other projects have required each builder to rapidly respond to achieve loss and damage minimization [1] [2] [3] [4] . Due to the incident urgency, taking Huoshenshan and Leishenshan Hospitals under COVID-19-related constraints as an example [5] [6] [7] , China raised the efforts of the whole society to provide a large number of resources to ensure rapid high-quality construction within an extremely short period. The world was amazed by the construction speed of these two emergency hospitals. However, under the condition of a large quantity of aggregated human, financial and material resources, i.e., resource tolerance, compression of the project duration to the limit and realization of an extremely short construction period have become notable research issues. At present, scholars have mainly focused on resource constraints and the shortest construction period in engineering project management [8] [9] [10] [11] [12] . In particular, under resource constraints, scholars have investigated methods to reasonably arrange the start time of each activity based on satisfying the logical relationship among project activities, thereby minimizing the project duration. Additionally, the above has been demonstrated to be a nondeterministic polynomial time (NP)-hard problem [13, 14] , and the research in this field largely includes the following two aspects: 1. In regard to the shortest construction period of a single project under resource constraints, Zhang et al. [15] established an optimization model aimed at project construction period minimization and effectively solved the problem via particle swarm optimization (PSO) based on priority and permutation. Peng et al. [16] further proposed the particle representation method based on priority permutation. Compared to the former method, the latter approach was verified to solve the problem more effectively. Vahid et al. [17] formulated a construction sequence plan with the realization goal of the shortest construction period based on building information modeling (BIM), developed computer programs with a genetic algorithm, and generated a stable construction schedule. Liu et al. [18] considered the factors of the material supply, cost constraints and various labor modes, established a model with the minimum construction project duration as the primary goal, and effectively solved the abovementioned problem. Xie et al. [19] focused on the constraints of the prefabricated component supply for prefabricated buildings, conducted in-depth research on the corresponding scheduling problem, effectively and reasonably distributed resources and reduced the completion time. 2. In terms of the shortest construction period of multiple projects under resource constraints, Marimuthu et al. [20] examined, summarized and compared optimization modeling methods. Suresh [21] and Goncalves [22] applied a genetic algorithm to shorten the project duration and improve the utilization rate of resources of the project group through resource allocation. Mohamed et al. [23] developed a multiobjective scheduling optimization model, which could enable construction enterprises to solve resource conflicts under the condition of multiple project priorities and the distribution of limited resources. Wang et al. [24] evaluated multiple projects based on priority, proposed a schedule model with the shortest weighted construction period of multiple projects as the goal, and solved the proposed model with an adaptive PSO algorithm. Hauder et al. [25] , based on the minimum multiproject construction period, proposed two goals: activity balance and resource balance. This approach was demonstrated to be applicable by solving the mixed-integer programming-based constraint model constructed in a large project. All the above studies have provided an important reference and suggestions for the realization of an extremely short construction period of a given project under resource constraints. In contrast, few scholars have performed research on the achievement of an extremely short construction period under the condition of resource tolerance. However, against the background of COVID-19 and innovation-driven development in the 14th Five-Year Plan [26] , it is necessary to thoroughly study the realization of an extremely short construction period of a project from the new perspective of resource tolerance. In the research process, it has been found that even under the condition of resource tolerance, there remain many factors influencing the realization of an extremely short construction period in terms of the engineering quantity [27, 28] , management [29] [30] [31] , technology [31, 32] , and environment [33, 34] . This study only focuses on the factor of labor force balance under working face limitations. Under the condition of resource tolerance, due to the limitation of the working face, we can face the following two situations affecting construction period compression: when the distribution of the labor force in each working face is lower than a certain demand, we cannot increase the construction speed nor minimize the construction period to the highest degree. In addition, many resources (human, financial and material resources) can be wasted. When the distribution of the labor force in each working face is higher than a certain demand, the increase in labor force is not directly proportional to the construction speed. In other words, workers can decrease their work efficiency through working face reduction, thereby affecting the realization of an extremely short construction period. Therefore, under the condition of resource tolerance, it is necessary to perform in-depth research on the realization of an extremely short construction period of a project considering the important influencing factor of labor force balance in the limited working face. We should continuously optimize and adjust the labor force distribution in the limited working face, reduce the deviation between the labor force distribution and demand, balance the labor force distribution and demand, and finally realize an extremely short construction period of the engineering project. To solve this problem scientifically and effectively, this paper first introduces the stochastic coefficient of labor force equilibrium, which effectively optimizes and adjusts the labor force by measuring the degree of labor force equilibrium in the limited working face. Next, the labor force is balanced by reducing the deviation between the labor force distribution and demand. Then, a labor force equilibrium model with the realization goal of an extremely short construction period is established. Based on a labor force balance in the limited working face, an extremely short construction period of the engineering project can be realized. Finally, the paper improves the standard PSO algorithm from two perspectives: the update equation is rounded to solve practical project problems, and a dynamic inertia weight is adopted to ensure the PSO accuracy and convergence speed. Subsequently, the improved PSO algorithm is employed to solve the research model, and the corresponding extremely short construction period and best labor force distribution scheme are determined. This study can provide theoretical support for project managers to realize an extremely short construction period of engineering projects under the condition of resource tolerance. It is assumed that a project comprises a set of V = [V 0 , V 1 , V 2 ,. . .,V n , V n+1 ] activities, where activities V 0 and V n+1 are dummies (no consumption of time and resources, respectively) and denote the initial and final project activities, respectively. The duration and start time of activity V i (i = 1, 2,. . .,n)�V are denoted as d i and s i , respectively. The project duration T is determined by the start time s n+1 of activities V n+1 , and we set the project start time to 0, i.e., s 0 = 0. The engineering quantity of activity V i �V is denoted as C i , and the total labor allocation, total labor demand and labor output quota of activity V i �V are denoted as R i , Q i , and E i , respectively. To facilitate analysis, the following hypotheses are established: 1. Under the condition of resource tolerance, this paper achieves an extremely short construction period with quality assurance. 2. The duration of each activity is not rounded to preserve the accuracy of the determination of an extremely short construction period. 3. The operation process of each activity cannot be interrupted, and the quantities of each activity remain fixed. 4 . Under the condition of resource tolerance, the labor force distribution in the working face of each activity is independent, and there occurs no delay or failure to conduct an activity according to the normal plan due to an insufficient labor force. 5. The impact on the construction period is the same when the labor force distribution in the working face of each activity is higher than or lower than the same unit of the labor force demand. In this study, the goal of realizing an extremely short construction period of the project is reached under the premise of a labor force balance in the limited working face of each activity. Hence, to measure the degree of labor balance in the working face, we introduced the stochastic coefficient of labor force equilibrium K. Notably, the imbalance in the labor force can be divided into two cases in this paper: R i >Q i and R i